Internal Audit - External Quality Assessment - Final Report

Noted Finance 1 paper

AI summaryRushmoor Audit and Governance Committee noted an external quality assessment of the Southern Internal Audit Partnership, which found general conformance with new Global Internal Audit Standards and no formal recommendations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSIAP generally achieves the Global Internal Audit Standards
MoneyNot stated
What happens nextAction plan to be implementedSuggestions to aid continuous improvement, with various target dates through 2026 and 2027
Who it affectsRushmoor as a SIAP clientInternal audit service delivery for partner and client authorities

What was decided

The Committee noted SIAP's Report No. SIAP26/02, the external quality assessment of SIAP against the Global Internal Audit Standards in the UK Public Sector.

Why

The independent assessor found SIAP generally achieves the GIAS, with 46 of 52 Standards fully achieved and the remaining six generally achieved, and no partial or non-conformances. Report P14, P40, P44

The result placed SIAP in the top quartile of the ten GIAS reviews the assessor has undertaken to date, with no formal recommendations made. Report P15, P41

The assessor identified key strengths including governance, an experienced team, alignment with the GIAS, and effective use of technology and stakeholder engagement. Report P10, P11, P56, P65, P67

What happens next

SIAP to incorporate practical ethical dilemmas, scenarios and case studies into Learning and Development Plan 2024-2026 training on Domain II by March 2026. Report P73, P157

SIAP to add an annex to the audit plan report listing all high-priority areas not covered, with reasons, by March 2026, to move Standard 9.4 toward full achievement. Report P88, P165

SIAP to update audit Practice Notes to incorporate consideration of the IIA's Topical Requirements (the first on Cybersecurity becomes effective February 2026), with root cause analysis captured at year end. Report P96, P169

Options considered

  • Chosen: Note the EQA report (the only option put to the Committee)

Implications

  • Governance: SIAP's overall governance, including reporting lines, Charters and Quality Assurance and Improvement Programme, was found to align with GIAS expectations. Report P10, P56, P64
  • Staffing: Succession risk and the need for additional advisory skills to support partners and clients through Local Government Reorganisation and Devolution were highlighted. Report P76, P78, P100
  • Risk: Some partners and clients still have actions to progress to confirm in their 2025/26 Annual Governance Statement that they conform with the GIAS in the UK Public Sector. Report P82, P160
  • Other: The assessor made a small number of suggestions for further development rather than formal recommendations; these do not require a formal response. Report P15, P52, P71

Who and where

  • Southern Internal Audit Partnership (SIAP) and its 61 staff Report P26, P107
  • Rushmoor Borough Council and other partner and client authorities, including Hampshire and West Sussex County Councils, five blue light clients, and six other smaller clients Report P26
  • Audit Committees and senior management of SIAP partner and client authorities Report P27, P82

Timeline

  • 1st April 2025: Global Internal Audit Standards became formally effective across the UK public sector Report P1, P18
  • Autumn 2025: EQA validation of SIAP's internal assessment undertaken Report P5
  • December 2025: External Quality Assessment report issued, with action plan appended Report P153
  • December 2025 to March 2027: Target window for delivery of the Internal Audit Strategy objective on a more agile audit process Report P167
  • February 2026: First IIA Topical Requirement (Cybersecurity) becomes properly effective Report P24, P96
  • March 2026: Target date for SIAP action plan items on Domain II training, Standard 9.4 plan annex, and Topical Requirements in audit Practice Notes Report P157, P165, P169

Plain English for the jargon

  • SIAP: Southern Internal Audit Partnership, a multi-client internal audit provider
  • GIAS: Global Internal Audit Standards issued by the IIA, effective in the UK public sector from 1 April 2025
  • EQA: External Quality Assessment, required at least every five years under GIAS
  • IIA: Institute of Internal Auditors
  • PSIAS: Public Sector Internal Audit Standards, the previous UK benchmark replaced by the GIAS
  • CIPFA Code: CIPFA Code of Practice for the Governance of Internal Audit in UK Local Government, addressing Domain III 'essential conditions'
  • Application Note: Global Internal Audit Standards in the UK Public Sector Application Note, supplementing the GIAS for the UK public sector
  • LGR: Local Government Reorganisation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

RESOLVED : That SIAP’s Report No. SIAP26/02, be noted.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Audit and Governance Committee

AUDIT AND GOVERNANCE COMMITTEE Head of Partnership REPORT NO. SIAP 26/02

28th January 2026

SIAP EXTERNAL QUALITY ASSESSMENT – OUTCOME REPORT

SUMMARY: As required by the Global Internal Audit Standards in UK Public Sector this report presents the outcomes from the External Quality Assessment of the Southern Internal Audit Partnership against the new Standards. • The external assessor report of the External Quality Assessment conducted on the Southern Internal Audit Partnership provides an independent oversight of conformance against the new Global Internal Audit Standards in the UK Public Sector as required under Standard 8.4 [External Quality Assessment].

RECOMMENDATION: Members are requested: o to note the report of the External Assessor following the External Quality Assessment of the Southern Internal Audit Partnership against the Global Internal Audit Standards in the UK Public Sector (Appendix A) and the action plan developed against suggested opportunities for future development (Appendix B).

1 Introduction 1.1 The mandate for internal audit in local government is specified within the Accounts and Audit [England] Regulations 2015, which states:

‘A relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.’

1.2From 1 April 2025, the ‘standards or guidance’ in relation to internal audit are those laid down in the Global Internal Audit Standards (GIAS), Application Note: Global Internal Audit Standards in the UK Public Sector (Application Note) and the Code of Practice for the Governance of Internal Audit in UK Local Government. The collective requirements shall be referred to as the Global Internal Audit Standards in the UK Public Sector (the Standards). 1.3 The Standards (8.4) require that ‘the Chief Internal Auditor must develop a plan for an external quality assessment and discuss the plan with the Audit Committee. The external audit assessment must be performed at least once every five years by a qualified, independent assessor or assessment team. The requirement for an external assessment may also be met through a self- assessment with independent validation.

External Quality Assessment

1.4An External Quality Assessment of the Southern Internal Audit Partnership was undertaken during September to December 2025. The scope was comprehensive including review of the Southern Internal Audit Partnership’s:

• Conformance with the Global Internal Audit Standards in the UK Public Sector. • Mandate, charter, strategy, methodologies, processes, risk assessment and internal audit planning. • Performance measures and outcomes. • Qualifications and competencies including those of the Chief Internal Auditor. • Integration into the organisation’s governance processes. • Contribution towards the organisation governance, risk management, and control processes. • Contribution to the organisations operations and ability to attain its objectives. • Ability to meet the expectations of stakeholders.

1.5The External Quality Assessment was undertaken by John Chesshire of JC Training Ltd who met all of the necessary requirements of the enhanced qualification and experience required of an external assessor in the public sector. John is also the current Chairman of the Internal Audit Standards and Advisory Board whose role includes oversight of the development and periodic revision of the Global Internal Aduit Standards. As such John is ideally positioned to provide the most credible assessment of the Southern Internal Audit Partnership against the new Standards. External Quality Assessment Outcome

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit: External Quality Assessment: Final ReportReport 615 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 14 attended
BO
Councillor Bill O'DonovanChair, present
PC
Councillor Peter CullumVice-Chair, present
CC
Councillor Craig CardCommittee Member, present
SC
Councillor Sue CarterCommittee Member, present
AC
Councillor Alex CrawfordCommittee Member, present
CG
Councillor Clive GrattanCommittee Member, apologies
SS
Councillor Sarah SpallCommittee Member, apologies, sent representative
PT
Councillor Paul TaylorCommittee Member, apologies, sent representative
JV
Councillor Jacqui VosperCommittee Member, present
IW
Councillor Ivan WhitmeeCommittee Member, apologies
BW
Councillor Becky WilliamsCommittee Member, apologies
TD
Councillor Thomas DayReserve, present as substitute

All 14 on the meeting page

On this subject at Rushmoor

Search all
  1. Internal Audit - External Quality Assessment - Final ReportThis decision
  2. Internal Audit Progress ReportNoted
  3. Internal Audit - Audit Charter and Audit Plan 2026/27Approved
  4. Internal Audit - Progress ReportNoted
  5. Internal Audit - Audit Progress Report UpdateNoted
  6. Internal Audit - Audit Progress ReportAgreed

More from Rushmoor Audit and Governance Committee

All decisions
MeetingDecisionOutcome
29 Sep 2026 Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. Noted Open
29 Sep 2026 Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. Noted Open
29 Sep 2026 Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... Approved Open
29 Sep 2026 Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... Noted Open
30 Jul 2026 Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies