NOS. 16-18 THE MEADS, FARNBOROUGH - ADDITIONAL BUDGET REQUIREMENT
AgreedExecutive1 paper
AI summaryRushmoor Cabinet approved up to £35,000 extra capital budget plus £15,000 contingency to complete building works at 16-18 The Meads, Farnborough, for Loungers, funded from capital receipts. Total project budget now stands at £786,590.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedExtra budget and contingency for The Meads project
MoneyUp to £50,000£35,000 budget increase plus £15,000 contingency
What happens nextComplete by 11 September 2026Revised practical completion date
Who it affectsFarnborough town centre, LoungersNew leisure operator opening
What was decided
Cabinet approved an increase to the project's capital budget of up to £35,000 to enable completion of the works by the end of September 2026.
A contingency of up to £15,000 was also approved, alongside the £35,000 for known variations, as the full extent of variations cannot be confirmed until practical completion. Report 3.11
Both the budget increase and contingency are to be funded from capital receipts balances.
Why
Contract variations during construction pushed the forecast additional budget above the £50,000 officer approval threshold, requiring formal Cabinet approval. Report 3.5
No single major issue drove the cost rise; variations span foundations, utilities and fire systems, asbestos, tenant requirements, design complexities and five extra weeks of contractor prelim costs. Report 3.6, 3.7, P14, P15, P16, P17, P18
The Council has entered a construction contract and a lease with Loungers, so withholding or delaying payment would expose it to contractual liability and possible claims. Report 3.9, 3.10
What happens next
Works are expected to practically complete on 11 September 2026, after which the unit will be transferred to Loungers for their detailed fit out ahead of opening. Report 2.3, 3.8
The 15-year Loungers lease will commence automatically once works complete, running without a break clause.
The report notes that the method of calculating project budgets and contingencies should be thoroughly reviewed.
The money
£35,000 capital budget increase to cover known contract variations Report 3.11
£15,000 additional contingency requested alongside the variation costs Report 3.11
£786,590 total capital budget for the project after this decision Report 5.4
£521k original capital budget agreed in September 2025 Report 2.1
£197,590 additional budget agreed in March 2026 Report 2.2
£21,000 additional budget secured via ROED on 23 June 2026 Report 3.3
£3.7m Council's capital receipts balance as at 1 April 2026 Report 5.7
£4k per year opportunity cost of using an additional £50k of capital receipts (avoided MRP and interest) Report 5.7
£52k net present value loss over 15-year Loungers deal reported in September 2025 Report 5.8
£250k net present value loss reported in March 2026 Report 5.8
£18,432 variation cost for tenant requirements Report P16
£27,189 variation cost for design complexities Report P17
£10,707 additional contractor prelim costs for 5-week delay Report P18
Options considered
Chosen: Approve the additional budget and contingency. Ensures works are completed and the unit can be handed over to Loungers; alternatives would have significant financial and legal impact. Report 3.12
Rejected: Withhold or delay payment to the contractor. Liability would arise under the construction contract, and Loungers could also claim damages for late completion under the lease. Report 3.9, 3.10
Implications
Financial: Total capital budget for the project rises to £786,590, and the net present value loss over the 15-year Loungers deal will increase further above the £250k reported in March 2026. Report 5.4, 5.8
Legal: Not approving the budget would put the Council at risk of failing its contractual obligations under the construction contract and the Loungers lease. Report 3.9, 3.10, 5.3
Financial: Using an extra £50k of capital receipts forgoes about £4k per year in MRP and interest savings that would otherwise be available by paying down borrowing. Report 5.7
Financial: The original September 2025 decision was taken without a 'whole asset' strategy for The Meads and without the cumulative cost context now available, so the long-term value for money of the scheme remains undetermined. Report 5.5, 5.6
Risk: Financial resilience risk linked to the appointment of a small local contractor continues until practical completion and through any defects liability period. Report 5.9
Risk: If Loungers ceased trading, the 15-year lease with no break clause means rent would remain due, recoverable as a debt if the company entered administration. Report 5.1
Equalities: An updated Equality Impact Screening Assessment confirms positive or neutral impacts across all protected characteristics; no full Equality Impact Assessment is required. Report 5.11, 5.12
Other: Officers recommend a thorough review of how project budgets and contingencies are calculated.
Who and where
Loungers (prospective tenant of 16-18 The Meads, Farnborough) Report 2.3
Farnborough town centre visitors and residents Report 2.4, 6.1
K7 Renovations (the contractor carrying out the works) Report 2.2, 5.9
Rushmoor Borough Council (as freeholder, contracting authority and budget holder) Report 3.9, 3.10, 5.4
Timeline
September 2025: Cabinet agreed original capital budget of £521k Report 2.1
March 2026: Cabinet agreed further budget extension of £197,590 Report 2.2
23 June 2026: ROED secured £21,000 additional budget for variations forecast at that time Report 3.3
7 August 2026: Original planned completion date before delay Report 3.8
End September 2026: Deadline set by Cabinet decision for completion of works
11 September 2026: Revised expected practical completion date Report 2.3, 3.8
January 2027: Long-stop date for completion of works under the Loungers agreement for lease Report 5.1
Plain English for the jargon
ROED: Record of Executive Decision, used by officers to approve spending within delegated limits.
Shell and core: Basic building works to extend and prepare a unit, leaving detailed interior fit out to the tenant.
Prelim costs: Preliminary costs a contractor can claim for matters such as delays outside their control.
MRP: Minimum Revenue Provision, the council's annual charge for repaying borrowed capital.
Capital receipts: Money received by the Council from selling capital assets, used here to fund the project.
Net present value: All future cashflows discounted to today's values, used to assess the financial viability of a deal.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25
Resolved
It was agreed that the method by which project budgets and contingencies were calculated should be thoroughly reviewed. The Cabinet RESOLVED that an increase to the project’s capital budget of up to £35,000, to enable the completion of the works by the end of September, 2026, plus the provision of a contingency of up to £15,000, be approved, both funded from capital receipts balances.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
2.1In September 2025, Cabinet considered Exempt Report No. REG2504 and agreed the allocation of a capital budget of £521k, consisting of £397k building adaptations works to the 16 – 18 The Meads unit and a £124k contribution to Loungers’ fit out costs.
2.2In March 2026, Cabinet then considered Exempt Report No. REG2602 and agreed a further budget extension of £197,590. This decision followed a protracted tendering process during which only one response was received from an initial framework with one other coming from a subsequent invitation to quote exercise. The latter, from K7 Renovations, was successful and was the lowest price received.
2.3The works started on site on the 5th May 2026 and are expected to practically complete on 11th September 2026. Following completion of the Council’s shell and core works, the unit will be transferred to Loungers for them to carry out detailed fit out in advance of their opening.
2.4As stated in the March paper, the arrival of the Loungers in Farnborough will represent a step-change in the quality of the town centre’s offer. It will complement the investment the Council has made in the Landings and, in conjunction with the redevelopment of the Meads Block 3 site will provide a new town square for Farnborough.
3. DETAILS OF THE PROPOSAL
3.1As part of the proposed lease for 16-18 The Meads to Loungers, the Council has committed to carry out works to extend the relevant units and fit out to shell and core level.
3.2The works comprise:
- Strip out / clearance - Extension of unit - Doors glazing - Landlord plumbing and electrical works
3.3A Record of Executive Decision (ROED) was prepared on 23rd June 2026 which secured £21,000 in additional budget to cover cost variations forecast at that time.
3.4The ROED reported that because the project involves work to an existing building, there were still unknown elements to the works and that if further issues were identified it may be necessary for further budget to complete the project. If forecast costs were to take the cumulative total additional budget above the £50,000 limit for officer approval, then formal Cabinet permission would be sought.
3.5Since this time, further contract variations have been necessary and the total forecast increase in the budged required has now exceeded the £50,000 threshold and, therefore, requires Cabinet approval.
3.6There is not one single issue that has had to be addressed during the build. The breakdown of the variations can broadly be grouped as follows:
Category Total Cost
Foundations £38,828
Utilities & Fire Systems £7,550
Asbestos £3,411 Tenant Requirements £18,432
Design Complexities £27,189
Additional Prelim Costs (5 weeks) £10,707
3.7The additional contractor prelim costs (costs a contractor can claim for delays outside their control) have arisen because of the 5-week delay to the completion date of the works as a consequence of the contract variations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.