COUNCIL DELIVERY PLAN AND RISK REGISTER QUARTER 2 UPDATE
NotedExecutive1 paper
AI summaryRushmoor Borough Council Cabinet noted delivery plan progress, with 18 of 23 priorities on track, and approved risk register changes that raise scores for local government reorganisation uncertainty and inaccurate financial position reporting. [D] [3.1] [5.6] [5.11]
Written from the decision and the officer reportPDF Pro
OutcomeNotedRisk changes include removal, addition, reframing and rescoring. [5.6] [5.7]
MoneyNot stated
What happens nextReview major risks [5.4]Portfolio holders check assessments and risk reduction with officers. [5.4]
Who it affectsCouncil services and risks [1.3]Delivery plan and service performance monitored quarterly. [1.3]
What was decided
Cabinet noted progress towards the Council Delivery Plan and the latest service performance information for July to September 2026. Report 1.3
Cabinet approved the Corporate Risk Register changes set out in section 5. Report P36
Why
Regular performance management helps the Council understand service performance, drive improvement and check that decisions are carried through. Report 1.1, 1.2
The Corporate Risk Register highlights factors that could affect future plan delivery or service performance. Report 2.6
The changes archive the external policy context risk because it is covered by uncertainty in future local government arrangements, and replace the general financial sustainability risk with three more specific financial risks. Report 5.6, 5.7, 5.9
What happens next
Portfolio holders should regularly discuss risks with the largest gaps with officers and check whether assessments and risk reduction actions are adequate. Report 5.4
Performance data collection through the performance app will be automated during Q3. Report 4.4
Continue testing the performance app and developing performance dashboards, with a delivery plan performance review due by March 2027. Report P115, P116
The money
£1.445 million LEP Legacy Fund support for flexible and serviced workspace at The Meads Business Centre Report 3.2, P78
approx £20k Possible software upgrade budget for the social housing allocations policy Report P91
Implications
Risk: The residual risk for uncertainty in future local government arrangements rose from 6 to 8, moving from medium to high. Report 5.6
Risk: Both inherent and residual scores for inaccurate financial position reporting increased to high, significantly increasing the risk gap. Report 5.11
Risk: The residual risk for the airport planning appeal rose from 9 to 12. It remains high, but the risk gap increased. Report 5.12
Risk: The report identifies no key risks arising from the decision itself. Report P51
Legal: The report identifies no direct legal implications. Report P52
Financial: Detailed financial performance information for the year is reported directly to Cabinet. Report P53
Staffing: There are no direct resource implications from the report. Report P54
Equalities: There are no direct equalities impact implications from the report. Report P55
Who and where
Council services and the Council Delivery Plan Report 1.3, 2.6
Rushmoor residents and local businesses Report 3.7
Council staff and councillors Report 3.7
Portfolio holders and officers Report 5.4
Young people, community groups and voluntary sector partners Report 3.4, P102, P103
Local social housing providers, private landlords and tenants Report P84, P85, P90
People using temporary or supported housing Report P88, P89
Future unitary authorities Report 3.7, P113
Timeline
26 February 2026: The Council Delivery Plan was approved. Report 2.1
30 September 2026: The quarter two delivery position was recorded, with 18 of 23 priorities on track. Report 3.1
29 October: A Government announcement led to a pause in local government reorganisation implementation. Report 3.7, P113
2 November 2026: The Youth Hub was on track to open. Report 3.2, P76
24 November 2026: Cabinet noted delivery progress and approved the risk register changes. Report P1
March 2027: A new local government reorganisation decision was expected to be proposed. Report 3.7, P113
end of 2027: The new Farnborough Pools and Fitness site was due to be completed. Report 3.4
1 April 2029: The date when future unitary authorities were expected to vest. Report 3.7, P113
Plain English for the jargon
Council Delivery Plan: The approved plan setting Council priorities and key projects for the next year. [2.1]
Priority status: Blue means complete, red means not on track, amber means delivery is at risk or only part delivered, and green means on track. [2.3]
Corporate Risk Register: Risks that could affect delivery of the Council Plan or service performance. [2.6]
Strategic risk: A risk involving wider conditions where the Council has only partial influence, such as local economic conditions. [P40]
Standing corporate risk: An operational risk relating to the Council's work. [P43]
Risk gap: The difference between the current residual risk and the target position. [5.4]
Residual risk: The current risk position used to calculate the risk gap. [5.4]
Local government reorganisation: The reorganisation programme involving future unitary authorities. [3.7] [P113]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43
Resolved
RESOLVED that (i) the progress made towards delivering the Council Delivery Plan and the latest performance information in relation to Council services, as set out in Report No. ED2620, be noted ; and (ii) the changes to the Corporate Risk Register, as set out in Section 5 of the Report, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
CABINET COUNCILLOR GARETH WILLIAMS LEADER OF THE COUNCIL 24 NOVEMBER 2026
KEY DECISION: NO REPORT NO. ED2620
COUNCIL DELIVERY PLAN AND RISK REGISTER QUARTER 2 UPDATE
SUMMARY AND RECOMMENDATIONS:
This report sets out the performance monitoring for the Council Delivery Plan for the first quarter of 2026/27. Annex A sets out progress on key projects and activities, and Annex B sets out a range of indicators and measures used by the Council to monitor how the Council runs services and how the borough is performing.
The report also sets out the key risks that could impact on the Council’s services and the delivery of the Council’s key priorities and includes the updated register of risks at Annex C and the associated dashboard report at Annex D.
The Cabinet is recommended to:
i) Note the progress made towards delivering the Council Delivery Plan and the latest performance information ii) Consider changes to the Corporate Risk Register as set out in sections 5 of this report.
1. INTRODUCTION
1.1Regular performance management is used to understand service performance and drive improvement across the Council’s services.
1.2Effective performance management: • Helps to ensure that the Council is achieving what it set out to do and giving good value for money – without measuring results it is difficult to tell success from failure • It enables the understanding of “how the Council is doing” • Helps to identify success (so that it can be rewarded and learnt from) and to identify failure (so that it can be corrected and learnt from) • Is linked to good decision making - using information about how things are now in order to make decisions about how to make them better • Helps to ensure decisions have been carried through • Is at the heart of good management
1.3This report sets out performance monitoring information for the Council’s Delivery Plan, Council Performance Data and the Risk Register for the period of July to September 2026. Annex A sets out progress on key projects and activities and Annex B sets out a range of indicators and measures used by the Council to monitor how the Council runs services and how the borough is performing. Annex C sets out risks that affect the Council’s performance.
2. BACKGROUND TO THE DELIVERY PLAN
2.1The Council Delivery Plan was approved at Council at its meeting on 26 February 2026. The plan sets out the Council’s priorities and the key projects and activities the council will take over the next year that contribute towards delivering the strategic priorities.
2.2The Plan is structured across five themes: • Skills, Economy, and Regeneration. • Homes for All: Quality Living, Affordable Housing. • Community and Wellbeing: Active Lives, Healthier and Stronger Communities. • Pride in Place: Clean, Safe and Vibrant Neighbourhoods. • The Future and Financial Sustainability.
2.3The Delivery Plan currently includes 23 priorities which for performance monitoring are each assigned a status of blue (complete), red (not on track), amber (risk of non-delivery or part delivery only) or green (on track). Each priority also has a direction of travel status to enable members to see whether the status of a project or activity is improving or not since the previous quarter. Some of the priorities do not have a direction of travel status this quarter, as they are new this year.
2.4The Delivery Plan priorities have outcomes and outputs that will measure the success of the priority. As outcomes tend to be longer term measures, these will be reported at the end of the year. Outputs will be reported each quarter, where quarterly data is available. Our residents’ surveys were complete in quarter 2, outcome measures from these surveys have been included in the quarter 2 report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.