COUNCIL DELIVERY PLAN, PERFORMANCE AND RISK REGISTER QUARTERLY UPDATE Q3 OCTOBER TO DECEMBER 2025/26

Noted Executive 1 paper

AI summaryRushmoor Cabinet notes Q3 2025/26 performance, with 74% of delivery plan priorities on track and changes to the corporate risk register, including two new risks and one reduced risk score.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted17 of 23 priorities on track, six amber
MoneyNot stated
What happens nextNot stated
Who it affectsRushmoor residents, businesses and council servicesFive themed priorities covering skills, homes, community, pride, finance

What was decided

Cabinet noted the progress made towards delivering the Council Delivery Plan and the latest performance information for Q3 2025/26. Report P8

Cabinet also noted the changes highlighted in the Corporate Risk Register, as set out in Section 5 of the report. Report 5.4

Why

Regular performance management is used to understand service performance and drive improvement across the Council's services. Report 1.1, 1.2

The Council Delivery Plan was approved by Council on 10 July 2025 and is structured across five themes covering skills and regeneration, housing, community and wellbeing, pride in place, and financial sustainability. Report 2.1, 2.2

17 of the 23 (74%) priorities were on track at the end of quarter 3 (31 December 2025), with six priorities holding an amber status. Report 3.1, 3.7, P30

What happens next

A new timetable for local plan preparation is to be brought to Cabinet in March 2026, once the new plan-making system can formally commence. Report P82

The organisational structure review, originally due by October 2025, will be completed by 31 March 2026, after which the Performance Management Framework will be updated. Report 3.7, P30, P100, P104

Two new risks have been added to the escalated service risks section of the risk register, but both are redacted from the public version. Report 5.11, 5.3

The money

  • £3.4m Planned reserve drawdown in the 2025-26 budget Report 6.4
  • £1.8m Net budget reduction savings target for 2025-26, reported as achieved Report 6.4
  • £38K Additional Active travel grant secured in Q3 Report 3.4, P26

Options considered

  • Chosen: Note the Q3 performance and delivery plan progress. Recommended to Cabinet in the report Report P7, P8
  • Chosen: Note the changes to the Corporate Risk Register. Recommended to Cabinet in the report Report 5.4, P8

Implications

  • Risk: Inherent risk score for 'negative economic and social trends' reduced from 12 to 9, though it remains high. Report 5.6
  • Financial: 2025-26 savings target of £1.8m reported as achieved; overall MTFS position remains challenging and is being monitored closely. Report 6.4
  • Equalities: Officers identify no direct equalities impact implications arising from the report. Report P51
  • Legal: Officers identify no direct legal implications; the report is for information purposes only. Report P47
  • Risk: Six priorities carry amber status, including private rented sector housing, temporary accommodation at Clayton Court, the new Local Plan, Civic Quarter regeneration, the organisational review, and Delivery Plan monitoring processes. Report 3.7, P30
  • Other: Two new risks have been added to the escalated service risks section, though both are withheld from the public register for sensitivity. Report 5.11

Who and where

  • Rushmoor residents and businesses across the borough Report 1.3, 2.2
  • Private rented sector landlords and tenants, given new Renters' Rights requirements Report 3.7, P30, P81
  • Residents of Clayton Court temporary accommodation Report 3.7, P30, P81
  • Council staff, given the ongoing organisational structure review Report 3.7, P100
  • Visitors to the National Armed Forces Day event planned for June 2026 Report 3.2, P22

Timeline

  • 10 July 2025: Council Delivery Plan approved at Council meeting Report 2.1
  • October to December 2025: Period covered by the Q3 2025/26 performance report Report P3, 1.3
  • December 2025: Residents survey carried out, including face-to-face and online components Report P78, P90, P97, P102
  • 31 December 2025: End of Q3, with 17 of 23 priorities on track Report 3.1
  • January 2026: Local Government Reorganisation consultation response drafted and submitted Report 3.6, P28, P98
  • March 2026: New timetable for local plan preparation to be brought to Cabinet Report P82
  • 31 March 2026: Organisational structure review to be completed Report 3.7, P30, P100, P104
  • 27 and 28 June 2026: National Armed Forces Day event to be hosted in Rushmoor Report 3.2, P22

Plain English for the jargon

  • RIBA stage: A work stage defined by the Royal Institute of British Architects used to plan building design and construction.
  • CCIA: Climate Change Impact Assessment, used by the Council to evaluate climate effects of decisions.
  • MTFS: Medium Term Financial Strategy, the Council's multi-year financial planning document.
  • RAG status: Red, Amber, Green rating used to flag whether a priority is on track, at risk, or not on track.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item61

Resolved

RESOLVED that (i) the progress made towards delivering the Council Delivery Plan and the latest performance information in relation to Council services, as set out in Report No. ED2601, be noted ; and, (ii) the changes highlighted in the Corporate Risk Register, as set out in Section 5 of the Report, be noted.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

CABINET COUNCILLOR GARETH WILLIAMS LEADER OF THE COUNCIL 10 FEBRUARY 2026

KEY DECISION: NO REPORT NO. ED2601

COUNCIL DELIVERY PLAN, PERFORMANCE & RISK QUARTERLY UPDATE Q3 OCTOBER TO DECEMBER 2025/26

SUMMARY AND RECOMMENDATIONS:

This report sets out the performance monitoring for the Council Delivery Plan for the third quarter of 2025/26. Annex A sets out progress on key projects and activities and Annex B sets out a range of indicators and measures used by the Council to monitor how the Council runs services and how the borough is performing.

The report also sets out the key risks that could impact on the Council’s services and the delivery of the Council’s key priorities and includes the updated register of risks at Annex C.

The Cabinet is recommended to:

i) Note the progress made towards delivering the Council Delivery Plan and the latest performance information ii) Consider changes to the Corporate Risk Register as set out in section 5 of this report.

1. INTRODUCTION

1.1Regular performance management is used to understand service performance and drive improvement across the Council’s services.

1.2Effective performance management: • Helps to ensure that the Council is achieving what it set out to do and giving good value for money – without measuring results it is difficult to tell success from failure • It enables the understanding of “how the Council is doing” • Helps to identify success (so that it can be rewarded and learnt from) and to identify failure (so that it can be corrected and learnt from) • Is linked to good decision making - using information about how things are now in order to make decisions about how to make them better • Helps to ensure decisions have been carried through • Is at the heart of good management

1.3This report sets out performance monitoring information for the Council’s Delivery Plan, Council performance data and the risk register for the period of October to December 2025. Annex A sets out progress on key projects and activities in the Council’s Delivery Plan and annex B sets out a range of indicators and measures used by the Council to monitor how the Council runs services and how the borough is performing.

2. BACKGROUND TO THE DELIVERY PLAN

2.1The Council Delivery Plan was approved at Council at its meeting on 10 July 2025. The plan sets out the Council’s priorities and the key projects and activities the Council will take over the next year that contribute towards delivering the new strategic priorities.

2.2The Plan is structured across five themes: • Skills, Economy, and Regeneration. • Homes for All: Quality Living, Affordable Housing. • Community and Wellbeing: Active Lives, Healthier and Stronger Communities. • Pride in Place: Clean, Safe and Vibrant Neighbourhoods. • The Future and Financial Sustainability.

2.3The Delivery Plan currently includes 23 priorities which for performance monitoring are each assigned a status of blue (complete), red (not on track), amber (risk of non-delivery or part delivery only) or green (on track). Each priority also has a direction of travel status to enable members to see whether the status of a project or activity is improving or not since the previous quarter. The Delivery Plan key measures of success, have a status code to whether they are on track to meet the target, currently not on track to meet the target or the target has been met.

2.4Annex B sets out a mix of measures and indicators that have been selected to show council service performance and also provide a picture of how the borough is performing.

2.5The Corporate Risk Register is also included in the Council’s quarterly performance reports to highlight factors that could impact on the future delivery of the Council Plan or affect the Council’s service performance.

3 PROGRESS AGAINST THE DELIVERY PLAN

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
COUNCIL DELIVERY PLAN, PERFORMANCE AND RISK REGISTER QUARTERLY UPDATE Q3 OCTOBER TO DECEMBER 2025/26Report 2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
GA
Councillor Gaynor AustinCommittee Member, present
KD
Councillor Keith DibbleCommittee Member, present
CG
Councillor Christine GuinnessCommittee Member, present
JH
Councillor Julie HallCommittee Member, present
SP
Councillor Sophie PorterVice-Chair, present
GW
Councillor Gareth WilliamsChair, present

On this subject at Rushmoor

Search all
  1. COUNCIL DELIVERY PLAN, PERFORMANCE AND RISK REGISTER QUARTERLY UPDATE Q3 OCTOBER TO DECEMBER 2025/26This decision
  2. Council delivery plan and risk register quarter one update and performance management frameworkNoted
  3. Council delivery plan, performance and risk register quarterly update q2 july to september 2025/26Noted
  4. Council delivery plan 2025/26Approved
  5. Planning delivery fundApproved

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open