Procurement Board, Wednesday 18 April 2018 at 10.00am

Request for Approval to Award Contract - Extension and Alteration Works at Worsley Leisure Centre

Approved Committee 1 paper

Procurement Board approved this item on Wednesday 18 April 2018. Below is the council's own wording, with the papers it was decided on.

Item5c

Resolved

Salford City Council - Record of Decision I, Paul Dennett, City Mayor, in exercise of the powers conferred on me by the Scheme of Delegation of the Council do hereby approve:- (a) The award of the following Stage 2 contract for a project approved under the approved Invest to Save Place Capital Programme in accordance with the following:- ( i ) and approves the outcome of the mini-competition (Stage 2) procurement process conducted through the North West Construction Hub (NWCH) Framework to award Wates Construction Limited as constructor partner to undertake extension and alteration works at Worsley Leisure Centre and to accept the contract price of £1,344,470.00 as detailed in the table below:- Detail required Title/Description of Contracted Service/Supply/Project Appoint a Construction Contractor Partner to undertake extension and alteration works to Worsley Leisure Centre Name of Successful Contractor Wates Construction Limited Supplier Registration Number (to be supplied by Corporate Procurement) 01977948 Type of organisation (to be supplied by Corporate Procurement) Private Limited Company Status of Organisation (to be supplied by Corporate Procurement) SME Contract Award Price £1,344,470.00 Full Project Contract Value Including Fees and approved QRA (if applicable ) £1,523,241.00 Full Project Contract Duration 8 months Contract Start Date 14/05/2018 Contract End Date 14/12/2018 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Choose an item. Contact Officer (Name & number) Gregory Durkin 0161 779 4942 Lead Service Group Environment & Community Safety How the contract was procured? (to be supplied by Corporate Procurement) Framework Call-off (Mini Competition) Framework Details (where applicable) (Procurement Body, Framework Reference & Title, Start/End Dates, Hyperlink, etc.) Low Value Construction Framework Agreement – North West Construction Hub Lot 3 Funding Source Capital Programme The Reasons are : to enable the works to progress as programmed to start on site and be completed in time for December 2018. Options considered and rejected were : None. All procedures are in accordance with normal Standing Orders. Assessment of Risk : The programme has been developed to achieve the delivery of the contracts to meet the necessary completion dates. The source of funding is : Approved Invest to Save Capital Programme for Place in the 2017/18 financial year. Legal Implications : Supplied by: Tony Hatton, Principal Solicitor, tel. 219 6323. When commissioning contracts for the procurement of goods, services or the execution of works, the Council must comply with the Public Contract Regulations 2015 (PCR) and its own Contractual Standing Orders (CSO’s), failing which a contract may be subject to legal challenge from an aggrieved provider. The proposed award of the contract follows a tender exercise by mini competition in accordance with the Low Value Construction Framework Agreement – North West Construction Hub Lot 3. The purpose of a framework agreement is to select through a procurement/evaluation process a number of providers who can meet the service requirements of the Council, as and when those services are required. If they are required then the Council will undertake an exercise to call off the services from ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendations

That Procurement Board :-

(a) Approves the outcome of the mini-competition (Stage 2) procurement process conducted through the North West Construction Hub (NWCH) Framework to award the contract to Wates Construction Limited as constructor partner to undertake extension and alteration works at Worsley Leisure Centre as detailed in the table below:-

Detail required Title/Description of Contracted Appoint a Construction Contractor Partner to Service/Supply/Project undertake extension and alteration works to Worsley Leisure Centre Name of Successful Contractor Wates Construction Limited Supplier Registration Number 01977948 (to be supplied by Corporate Procurement) Type of organisation Private Limited Company (to be supplied by Corporate Procurement) Status of Organisation SME (to be supplied by Corporate Procurement) Contract Award Price £1,344,470.00 Full Project Contract Value Including Fees and £1,523,241.00 Full Project approved QRA (if applicable ) Contract Duration 8 months Contract Start Date 14/05/2018 Contract End Date 14/12/2018 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Choose an item. Contact Officer (Name & number) Gregory Durkin 0161 779 4942 Lead Service Group Environment & Community Safety

How the contract was procured? Framework Call-off (Mini Competition) (to be supplied by Corporate Procurement) Framework Details (where applicable) (Procurement Body, Framework Reference & Low Value Construction Framework Agreement – Title, Start/End Dates, Hyperlink, etc.) North West Construction Hub Lot 3 Funding Source Capital Programme

___________________________________________________________________

Executive summary

The purpose of this report is to seek approval for the tendering procedures relating to the intended award of the above mentioned contract.

___________________________________________________________________

BACKGROUND DOCUMENTS (NOT OPEN TO THE PUBLIC)

Exempt under Paragraph 3 of Schedule 12 A of the Local Government Act 1972

“Tender Submissions and Evaluation documents” ___________________________________________________________________

KEY DECISION: Yes

___________________________________________________________________

DETAILS:

1. Background,

1.1In early 2015 Salford City Council, with the support of Salford Community Leisure, commenced work on developing a facility improvement programme for the city’s indoor leisure facilities. The process was developed in partnership with Sport England, whose officers have worked closely at each stage with colleagues in Salford. In addition, Sport England revenue monies have assisted in funding external consultancy firms who have worked on the various processes.

1.2With regard to the above, assessments were undertaken which covered:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Request for Approval to Award Contract: Extension and Alteration Works at Worsley Leisure CentreReport 147 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

2 of 6 attended
PB
Paula BoshellCommittee Member, present
PD
Paul DennettCommittee Member, apologies
CF
Christine FliskCouncil Staff, expected
JH
Joanne HardmanCouncil Staff, expected
BH
Bill HindsChair, present
JM
John Merry CBECommittee Member, apologies

On this subject at Salford

Search all
  1. Request for Approval to Award Contract - Extension and Alteration Works at Worsley Leisure CentreThis decision
  2. Request for approval to award the contract for the delivery of Bikeability cycle training 2026-2029 (Simi Drummond)Approved
  3. ADDENDUM REPORT - Request approval to extend the contract for Community Protection/ Refuse Collection software (Place) from 01/04/2026 to 31/03/2028 (Matt Wylie)Approved
  4. Request for Approval - Approval for a variation to the extension of a Salford City Council Contract that was originally called off through the STAR framework 3924: AGMA Civil & Structural Engineering Professional Services for the appointmenApproved
  5. Request for Approval - Contract Award - Salford Handy Person Service - Rob TurnerApproved
  6. Request for Approval - Exception to Contractual Standing Orders - Contract Award - Allied Health Professionals Therapy for Children and Young People - Karen SmithApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies