Salford City Council
Procurement Board, Wednesday 29 May 2019 at 10.00am

Request for Approval - Expenditure for Agecroft Prison Footbridge Scour Repair

Approved Committee 6 papers

Procurement Board approved this item on Wednesday 29 May 2019. Below is the council's own wording, with the papers it was decided on.

Item5c

Resolved

Salford City Council - Record of Decision I Councillor Bill Hinds, Lead Member for Finance and Support Services and chairman of the Procurement Board, in exercise of the powers contained within the City Council constitution do hereby approve:- The award of the Contract for Agecroft Prison Footbridge Scour Repair Works as detailed in the table below: Detail required Title/Description of Contracted Service/Supply/Project Agecroft Prison Footbridge Scour Repair Works Name of Engineering Consultant Name of Successful Contractor Urban Vision Partnership Highway Services Supplier Registration Number (to be supplied by Corporate Procurement) 05292634 Type of organisation (to be supplied by Corporate Procurement) Private Limited Company Status of Organisation (to be supplied by Corporate Procurement) SME Contract Value Other Costs £ £200,304.74 Contract Duration 6 Weeks Contract Start Date 24/06/2019 Contract End Date 02/08/2019 Contact Officer (Name & number) Inam Ul-Haque 0161 779 4908 Lead Service Group Partner (please identify below) Urban Vision How the contract was procured? (to be supplied by Corporate Procurement) Development Services Partnership Agreement Framework Details (where applicable) (Procurement Body, Framework Reference & Title, Start/End Dates, Hyperlink, etc.) Development Services Partnership Agreement Funding Source Department for Transport Capital Grant for Highways Flood Recovery Works 2016/2017 The Reasons are: If the defects are not addressed the banks in the vicinity of the footbridge foundations could erode further and undermine the structure, closing the footbridge, which will impact the local pedestrian traffic between two parks at the Salford-Bury boundary. Options considered and rejected were : Not to award the Contract Assessment of Risk : Medium Funding is available from the Department for Transport Capital Grant for Highways Flood Recovery Works 2016/2017. Urban Vision is experienced in undertaking similar repairs. The source of funding is: The Department for Transport Capital Grant for Highways Flood Recovery Works 2016/2017. Legal Advice obtained Yes – Tony Hatton, Principal Solicitor, Tel. 0161 234 4987 Financial Advice obtained Yes – Alison Woods, Finance Manager, Ext 1135 Procurement Comments Yes – Christine Flisk, Procurement Manager, Ext 6245 Contact Officer : Inam Ul-Haque Tel No 0161 779 4908 * This decision is not subject to consideration by another Lead Member * The appropriate scrutiny committee to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed: BILL HINDS Dated: 29 May 2019 Lead Member FOR DEMOCRATIC SERVICES USE ONLY * This decision was published on 29 May 2019 * This decision will come in force at 4.00 p.m. on 5 June 2019 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Bridge Scour Assessment Clifton and Agecroft, Salford

July 2018

Salford City Council Quality Management Job No CS/094310

Project Salford City Council Level 2 Scour Assessment

Location Metropolitan Borough of Salford

Title Bridge Scour Assessment

Document Ref Bridge Scour Issue / Revision V0 Assessment_Clifton_Agecroft_ 005.docx

File reference Bridge Scour Assessment_Clifton_Agecroft_Final

Date 27/07/2018

Prepared by Martin Smith Signature (for file)

Checked by Kevin Hemmings Signature (for file)

Authorised by Daniel Stansfield Signature (for file)

Revision Status / History Rev Date Issue / Purpose/ Comment Prepared Checked Authorised

V0 02/10/2018 Final MDS KH DS

Capita Property and Infrastructure Ltd Velocity House Solly Street Sheffield South Yorkshire S1 4DE

Telephone: 01228 673779 Project contact: [email removed]

i Limitations This Report has been prepared for the sole use of the Salford City Council in accordance with the Agreement under which our services were performed. No other warranty, expressed or implied, is made as to the professional advice included in this Report or any other services provided by Capita. This Report is confidential and may not be disclosed by the Client nor relied upon by any other party without the prior and express written agreement of Capita. The conclusions and recommendations contained in this Report are based upon information provided by others and upon the assumption that all relevant information has been provided by those parties from whom it has been requested and that such information is accurate. Information obtained by Capita has not been independently verified by Capita, unless otherwise stated in the Report. The methodology adopted and the sources of information used by Capita in providing its services are outlined in this Report. Where assessments of works or costs identified in this Report are made, such assessments are based upon the information available at the time and where appropriate are subject to further investigations or information which may become available. Capita disclaim any undertaking or obligation to advise any person of any change in any matter affecting the Report, which may come or be brought to Capita’s attention after the date of the Report. Certain statements made in the Report that are not historical facts may constitute estimates, projections or other forward-looking statements and even though they are based on reasonable assumptions as of the date of the Report, such forward-looking statements by their nature involve risks and uncertainties that could cause actual results to differ materially from the results predicted. Capita specifically does not guarantee or warrant any estimate or projections contained in this Report.

Copyright

© This Report is the copyright of Capita Property and Infrastructure Ltd. Any unauthorised reproduction or usage by any person other than the addressee is strictly prohibited.

ii Contents 1. Introduction 1 1.1 Background 1 1.2 Site Location and Structure Information 1 2. Data Gathering 4 2.1 Walkover Survey 4 2.2 Asset data 4 2.3 Structure Description 4 2.4 Previous Analysis 5 2.5 Underwater Examination 5 2.6 Coring Information 5 2.7 Topographic Survey/ Drawings 5 3. Method 8 3.1 General 8 3.2 Hydraulic Model Build, Design Flood, Water Levels and Velocities 8 3.3 Depth of Scour 12 3.4 Risk Rating 14 4. Hydraulic Model Results 16 4.1 Design Floods, Water Levels and Velocities 16 4.2 Depth of Scour 16 4.3 Risk and priority rating 17 4.4 Superstructure-Assessment of Vulnerability 18 5. Conclusions and Recommendations 19 5.1 Conclusions 19 5.2 Recommendations 19

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
05(c): Bridge Scour Assessment_Clifton_Agecroft_Final_Issued_v2Report 3.7 MB DownloadRead as text
PDF
05(c): Delegated Decision Notice: AuthorisedDecisions 819 KB Download
PDF
05(c): UV008285-UV-SGN-ZZ-DR-S-01Report 445 KB Download
PDF
05(c): UV008285-UV-SGN-ZZ-DR-S-03Report 451 KB Download
PDF
05(c): Visual_Geomorphological_Assesment_Final_v2Report 6.5 MB Download
PDF
Request for Approval: Expenditure for Agecroft Prison Footbridge Scour RepairReport 125 KB Download

At this meeting

Whole meeting

Who was there

2 of 9 attended
PB
Paula BoshellCommittee Member, apologies
MC
Miranda Carruthers-WattOfficer, expected
PD
Paul DennettCommittee Member, apologies
CF
Christine FliskCouncil Staff, expected
JH
Joanne HardmanCouncil Staff, expected
CH
Chris HeskethOfficer, expected
BH
Bill HindsChair, present
JM
John Merry CBECommittee Member, present
PN
Paul NugentCouncil Staff, expected

On this subject at Salford

Search all
  1. Request for Approval - Expenditure for Agecroft Prison Footbridge Scour RepairThis decision
  2. Request for approval to award the contract for the delivery of Bikeability cycle training 2026-2029 (Simi Drummond)Approved
  3. ADDENDUM REPORT - Request approval to extend the contract for Community Protection/ Refuse Collection software (Place) from 01/04/2026 to 31/03/2028 (Matt Wylie)Approved
  4. Request for Approval - Approval for a variation to the extension of a Salford City Council Contract that was originally called off through the STAR framework 3924: AGMA Civil & Structural Engineering Professional Services for the appointmenApproved
  5. Request for Approval - Contract Award - Salford Handy Person Service - Rob TurnerApproved
  6. Request for Approval - Exception to Contractual Standing Orders - Contract Award - Allied Health Professionals Therapy for Children and Young People - Karen SmithApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies