CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Salford City Council
Procurement Board, Wednesday 5 February 2020 at 10.00am

Request for Approval - Contract Award - Minor Civils Framework

Approved Committee 1 paper

Procurement Board approved this item on Wednesday 5 February 2020. Below is the council's own wording, with the papers it was decided on.

Item5c

Resolved

Salford City Council - Record of Decision I Paul Dennett, City Mayor , in exercise of the powers contained within the Council Constitution do hereby approve t he award of the Contract for the Minor Civils Framework as detailed in the tables below: Detail required Title/Description of Contracted Service/Supply/Project Minor Civils Framework Name of Successful Contractor Lot 1 – Argyle Construction Lot 2 – Tarmac Bethell Construction Ltd George Cox & Sons Ltd Eric Wright Civil Engineering Ltd NMS Civil Engineering Ltd A E Yates Ltd Supplier Registration Number (to be supplied by Corporate Procurement) Lot 1 – Argyle NW Construction Ltd 02829893 Lot 2 – Tarmac Bethell Construction Ltd - 00264322 George Cox & Sons Ltd - 02775128 Eric Wright Civil Engineering Ltd - 02565379 NMS Civil Engineering Ltd - 01910241 A E Yates Ltd - 06893528 Type of organisation (to be supplied by Corporate Procurement) Private Limited Company Status of Organisation (to be supplied by Corporate Procurement) Non-SME Contract Value £4,000,000 Full Project Contract Duration 18 Months Contract Start Date 17/02/2020 Contract End Date 16/08/2021 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Shoaib Mohammad, Assistant Director Technical Services Lead Service Group Place How the contract was procured? (to be supplied by Corporate Procurement) Tender (Open) Framework Details (where applicable) (Procurement Body, Framework Reference & Title, Start/End Dates, Hyperlink, etc.) N/A Funding Source Combination of Above (please detail below) The reasons are that this framework is required in order to be able to deliver the services that Urban Vision currently provide and as a top up facility to the Direct Labour Organisation within Highways Construction at Swinton Hall Road Depot. Assessment of Risk is that the risk of not having this framework available to UV after the transition period relate to the ability to be able to continue to provide the service and to allow for a smooth transition . The source of funding is Approved Highways Capital (£9.036m) and Revenue (£2.831m) Budgets 2019/20 . Legal Advice obtained . Financial Advice obtained . Procurement Advice obtained. Climate Change Implications considered. Contact Officer: Hayley Nixon Tel No 686 7413 * This decision is not subject to consideration by another Lead Member * The appropriate scrutiny committee to call-in the decision is the Growth and Prosperity Board Scrutiny Panel. Signed: PAUL DENNETT Dated: 05 February 2020 City Mayor FOR DEMOCRATIC SERVICES USE ONLY * This decision was published on 05 February 2020 * This decision will come in force at 4.00 p.m. on 12 February 2020 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board approve the award of the Contract for the Minor Civils Framework as detailed in the tables below:

Detail required Title/Description of Contracted Minor Civils Framework Service/Supply/Project Lot 1 – Argyle Construction Lot 2 – Tarmac Bethell Name of Successful Contractor George Cox Eric Wright NMS A E Yates Supplier Registration Number Lot 1 – (to be supplied by Corporate Procurement) Lot 2 - Type of organisation Private Limited Company (to be supplied by Corporate Procurement) Status of Organisation Non-SME (to be supplied by Corporate Procurement) Contract Value £4,000,000 Full Project Contract Duration 18 Months

Sample B – award of contract Contract Start Date 17/02/2020 Contract End Date 16/08/2021 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Procurement Board (extension > £150k) Period? Shoaib Mohammad, Assistant Director Contact Officer (Name & number) Technical Services Lead Service Group Place How the contract was procured? Tender (Open) (to be supplied by Corporate Procurement) Framework Details (where applicable) N/A (Procurement Body, Framework Reference & Title, Start/End Dates, Hyperlink, etc.)

Funding Source Combination of Above (please detail below)

Executive summary

The purpose of this report is to seek approval for the award of the above mentioned contract.

BACKGROUND DOCUMENTS:

The approval to go out to competition for the above items was given at the meeting of the Procurement Board on 26th June 2019.

KEY DECISION: Yes

DETAILS:

1. Background,

In preparation for services at Urban Vision (UV) coming back to the council from 1st February 2020, Salford City Council (SCC) has been undertaking a transition programme in preparation to receive and operate the service with minimal disruption.

One of the key parts of the transition programme covers the SCC readiness to run the services effectively and efficiently from 1st February 2020, which includes ensuring we have the relevant procurement strategy in place to receive and operate the service.

Sample B – award of contract As such the Procurement work stream has been putting the necessary steps in place to have compliant routes to market for all services, materials and contractors required by the service.

There has been a detailed analysis undertaken of the current suppliers to UV and procurement strategy identified in order to ensure the continuity of service and its effective performance post transfer. As such, there is a requirement to procure and manage contracts with third party suppliers, and to procure goods and services as and when they are required to allow for continuity of delivery.

The purpose of this report is request approval to award a contract in line with SCC’s Contractual Standing Orders for a Minor Civils Framework to provide the following services as a top up facility to the Direct Labour Organisation (DLO), defined as the local authorities’ business unit which undertakes works as described in the Local Government Act 1980 and or other works including construction and maintenance, which SCC has to deliver Highways Maintenance in house. As such only those works that can’t be delivered in house will be awarded via this framework at SCC’s discretion.

 General Civil Engineering Works o Works including, but not limited to;  Carriageway/ Footway construction/ reconstruction  Carriageway/ Footway resurfacing  New Traffic Signal Control junctions  New Traffic Islands

 General Highway Asset Maintenance Activities o Works including, but not limited to;  Pot hole repair  Gully Maintenance  Carriageway/ footway resurfacing/ patching programmes  Carriageway Surface Treatment

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Request for Approval: Contract Award: Minor Civils FrameworkReport 168 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 9 attended
PB
Paula BoshellCommittee Member, present
MC
Miranda Carruthers-WattOfficer, expected
PD
Paul DennettCommittee Member, apologies
CF
Christine FliskCouncil Staff, expected
JH
Joanne HardmanCouncil Staff, expected
CH
Chris HeskethOfficer, expected
BH
Bill HindsChair, present
JM
John Merry CBECommittee Member, present
PN
Paul NugentCouncil Staff, expected

On this subject at Salford

Search all
  1. Request for Approval - Contract Award - Minor Civils FrameworkThis decision
  2. Request for approval to award the contract for the delivery of Bikeability cycle training 2026-2029 (Simi Drummond)Approved
  3. ADDENDUM REPORT - Request approval to extend the contract for Community Protection/ Refuse Collection software (Place) from 01/04/2026 to 31/03/2028 (Matt Wylie)Approved
  4. Request for Approval - Approval for a variation to the extension of a Salford City Council Contract that was originally called off through the STAR framework 3924: AGMA Civil & Structural Engineering Professional Services for the appointmenApproved
  5. Request for Approval - Contract Award - Salford Handy Person Service - Rob TurnerApproved
  6. Request for Approval - Exception to Contractual Standing Orders - Contract Award - Allied Health Professionals Therapy for Children and Young People - Karen SmithApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies