CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Salford City Council
Procurement Board, Wednesday 21 April 2021 at 10.00am

Request for Approval - Recommendation to Islington Mill Arts Club on Award of Contract - Apppointment of Building Contractor

Approved Committee 1 paper

Procurement Board approved this item on Wednesday 21 April 2021. Below is the council's own wording, with the papers it was decided on.

Item6a

Resolved

Salford City Council - Record of Decision I Paul Dennett, City Mayor , in exercise of the powers contained within the Council Constitution do hereby approve the award of the contract by Islington Mill Arts Club for the appointment of a building contractor for the refurbishment works at Islington Mill & New Islington Mill. Detail required Answers Title/ Description of Contracted Service/Supply/Project Islington Mill & New Islington Mill refurbishment - Appointment of a building contractor Name of Successful Contractor KrolCorlett Construction Supplier Registration Number (to be supplied by Corporate Procurement) 05974400 Type of organisation (to be supplied by Corporate Procurement) Private Limited Company Status of Organisation (to be supplied by Corporate Procurement) SME Contract Value £4,125,521.36 Full Project Contract Duration 46 weeks + 12 months defects period Contract Start Date 05/07/2021 Contract End Date 02/06/2023 Optional Extension Period 1 n/a Optional Extension Period 2 n/a Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Perry Twigg [phone removed] Lead Service Group Place How the contract was procured? (to be supplied by procurement) Open Tender Framework Details (where applicable) (procurement body, framework reference & title, start/ end date N/A Funding Source Grant Ethical Contractor Mayor’s Employment Charter Committed to sign up to the Charter Accredited Living Wage Employer ? The Reasons are To enable the refurbishment of Islington Mill and New Islington Mill to be undertaken and support IMAC, in their ambitions in the short term to refurbish and expand managed workspace and business support provision for a creative industries hub centred on Islington Mill. Options considered and rejected were Not to support the project, however this was discounted and authority to support/progress the project was given by the City Mayor at the Property and Regeneration Briefing on the 23 rd March 2020. Assessment of Risk Medium: The key risk was that tender returns were greater than the estimated value/available funding. Taking the value of this tender (4.13 million) and adding to this the previously tendered advanced roof works (£0.36 million) and advanced asbestos removal (£0.02 million) the total value of the package 2 works is £4.51 million. This is less than the estimated value of £4.62 million for this package of works. Although the above risk has currently been eliminated, both Islington Mill and New Islington Mill are historic buildings which are notoriously complex to refurbish. Whilst best endeavours have been made by the consultancy team through surveys and design work to ensure that risk is minimised, unforeseen problems frequently arise when works are undertaken on site, leading to increased cost. Wherever feasible, ‘Value Engineering’ will be utilised to manage this risk. Delays in accepting this tender and not commencing the works in July 2021 could also potentially lead to the loss of Arts Council England funding, which is time limited. The consultancy team responsible for the design and procurement of the building works are liaising closely with Arts Council England in connection with programme to mitigate this risk. LEGAL IMPLICATIONS: Supplied by: Tony Hatton ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board recommend the award of the contract by Islington Mill Arts Club for the appointment of a building contractor for the building works at Islington Mill & New Islington Mill

Detail required Answers Title/Description of Contracted Islington Mill/New Islington Mill Refurbishment - Service/Supply/Project Appointment of a building contractor Name of Successful Contractor KrolCorlett Construction Supplier Registration Number (to be supplied by Corporate Procurement) 05974400

Type of organisation Private Limited Company (to be supplied by Corporate Procurement) Status of Organisation (to be supplied by Corporate Procurement) SME

Contract Value £4,125,521.36 Full Project Contract Duration 46 weeks + 12 months defects period Contract Start Date 05/07/2021 Contract End Date 02/06/2023 Optional Extension Period 1 n/a

Sample B – award of contract Detail required Answers Optional Extension Period 2 n/a Who will approve each Extension Procurement Board (extension > £150k) Period? Contact Officer (Name & number) Perry Twigg [phone removed] Lead Service Group Place

How the contract was procured? Open Tender (to be supplied by procurement) Framework Details (where applicable) (procurement body, framework N/A reference & title, start/ end date Funding Source Grant Mayor’s Employment Charter Ethical Contractor Committed to sign up to charter

Accredited Living Wage Employer √

Executive summary

The purpose of this report is to seek approval for recommendation that Islington Mill Arts Club award the above mentioned contract.

BACKGROUND DOCUMENTS:

Authority to go out to tender was given at Procurement Board on the 25th March 2020, item 5a.

Authority to proceed with the project was given at the City Mayor Property and Regeneration Briefing on the 23rd March 2020, item 5a.

KEY DECISION:

Yes

Sample B – award of contract DETAILS:

Background

Approval to go out to competition on 3 packages of work in connection with the Islington Mill project was given by Procurement Board, at the meeting on 25th March 2020, item 5a.

This report relates to an element of the second package of work as follows: -

Package 2 – Procurement of a building contractor (Estimated value £4.62 million)

To deliver the project on site, which will include demolitions, repairs, building works, finishes, fitting’s, electrical and mechanical installations.

Islington Mill Arts Club will be the contracting organisation for these works with a grant funding agreement in place between the Council and IMAC.

As part of the funding arrangements for the project, Islington Mill Arts Club are required, under the Council’s guidance and supervision, to follow public sector procurement regulations, which is in line with ERDF requirements and undertake an open competitive processes for this package of work.

Ahead of the works identified above commencing, two packages of advanced works have already been procured through separate open tender processes.

a) Roof repair works at Islington Mill approved at Procurement Board on 23rd September 2020.

b) Asbestos removal at New Islington Mill approved by Strategic Director, Place on 22nd March 2021.

2. The Procurement Process

An advert was published to notify the market in January 2021 in relation to a new up and coming project giving contractors the opportunity of what information and work was involved in the project so they could allocate time to apply for the opportunity once it was fully advertised.

Following a good response for the market engagement, the opportunity was advertised in the northwest portal (the chest), Contracts Finder and the FTS (find a tender service) which replaces the advertisement in the OJEU as an open procedure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Request for Approval: Recommendation to Islington Mill Arts Club on Award of Contract: Apppointment of Building ContractorReport 444 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 8 attended
PD
Paul DennettCommittee Member, expected
CF
Christine FliskCouncil Staff, expected
JH
Joanne HardmanCouncil Staff, expected
CH
Chris HeskethOfficer, expected
AH
Anthony HiltonOfficer, expected
BH
Bill HindsChair, expected
TK
Tracy KellyCommittee Member, expected
JM
John Merry CBECommittee Member, expected

On this subject at Salford

Search all
  1. Request for Approval - Recommendation to Islington Mill Arts Club on Award of Contract - Apppointment of Building ContractorThis decision
  2. Request for approval to award the contract for the delivery of Bikeability cycle training 2026-2029 (Simi Drummond)Approved
  3. ADDENDUM REPORT - Request approval to extend the contract for Community Protection/ Refuse Collection software (Place) from 01/04/2026 to 31/03/2028 (Matt Wylie)Approved
  4. Request for Approval - Approval for a variation to the extension of a Salford City Council Contract that was originally called off through the STAR framework 3924: AGMA Civil & Structural Engineering Professional Services for the appointmenApproved
  5. Request for Approval - Contract Award - Salford Handy Person Service - Rob TurnerApproved
  6. Request for Approval - Exception to Contractual Standing Orders - Contract Award - Allied Health Professionals Therapy for Children and Young People - Karen SmithApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies