Salford City Council
Procurement Board, Wednesday 10 January 2024 at 10.00am

Tootal Grove Affordable Homes (Konrad Magdzinski)

Approved Committee 1 paper

Procurement Board approved this item on Wednesday 10 January 2024. Below is the council's own wording, with the papers it was decided on.

Item5d

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, in exercise of the powers contained within the Council Constitution do hereby approve: · the variation to the contract sum to enable the building of 21 affordable homes at Tootal Grove, as detailed in the table below: Detail required Answers Title/Description of Contracted Service/Supply/Project Construction of 16 move on units and 19 affordable homes. Name of Successful Contractor PLP Construction Ltd. Supplier Registration Number (to be supplied by Corporate Procurement) 03244506 Type of organisation (to be supplied by Corporate Procurement) Private Limited Company Status of Organisation (to be supplied by Corporate Procurement) SME Contract Value (£) £7,377,513 Contract Duration 16 months Contract Start Date 01/03/2024 Contract End Date 29/08/2025 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) KONRAD MAGDINSKI 793 2197 Lead Service Group Place How the contract was procured? (to be supplied by procurement) ICN Framework Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Innovation Chain North (ICN) is a framework for construction and associated professional services procured under the Public Contracts Regulations 2015 and is OJEU compliant. It has been designed to support the delivery of new homes and associated social infrastructure across the North of England. The framework includes lots for contractors, associated professional services as well as a Dynamic Purchasing System (DPS) for the supply of Modular Homes. Funding Source Grant Ethical Contractor (EC): Mayor’s Employment Charter ? EC: Committed to sign Charter ? EC: Accredited Living Wage Employer ? The purpose of this report is to seek approval for a variation the increase in costs to enable the building of 21 affordable homes at Tootal Grove. The scheme has significant benefits including: · Reducing the use of temporary accommodation, particularly if it reduces the need to place homeless out of the city and placing vulnerable residents in permanent accommodation is shown to have positive impact on health. · RSAP provision will provide valuable move on accommodation with support for people who have experienced multiple disadvantage and tenancy failure. · It will provide valuable, affordable “stepping stone” accommodation for those who are seeking to address issues within their life such as mental health challenges, substance misuse, domestic abuse. · RSAP accommodation acts as a “trial tenancy”. The length of stay is expected to be up to 2 years which allows the occupant to prove their tenancy readiness to other landlords. Many may be bypassed on the register without this positive tenancy evidence. · Affordable supported accommodation is rare and allows people to access employment without the burden of high cost supported accommodation that is the norm within exempt accommodation schemes. · RSAP units have been designed to be day to day cost effective for the occupant - leading to financial viability for the occupant and increasing the sustainability of the tenancy. Assessment of Risk : High The RSAP funding is time limited and requires a start on site before March 2024 to enable grant ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board approve the variation to the contract sum to enable the award of contract for the building of 21 affordable homes at Tootal Grove.

Detail required Answers Title/Description of Contracted Construction of 16 move on units and 19 Service/Supply/Project affordable homes. Name of Successful Contractor PLP Construction Ltd Supplier Registration Number (to be supplied by Corporate Procurement) 03244506

Type of organisation Private Limited Company (to be supplied by Corporate Procurement) Status of Organisation (to be supplied by Corporate Procurement) SME

Contract Value (£) £ 7,377,513 Contract Duration 16 months Contract Start Date 01/03/2024 Contract End Date 29/08/2025 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Procurement Board (extension > £150k) Period? Contact Officer (Name & number) Konrad Magdzinski 793 2197

Sample B – award of contract Detail required Answers Lead Service Group Place How the contract was procured? ICN Framework (to be supplied by procurement) Innovation Chain North (ICN) is a framework for construction and associated professional services procured under the Public Contracts Regulations 2015 and is OJEU compliant. It has been designed to support the delivery of new Framework Details (where applicable) homes and associated social infrastructure (procurement body, framework across the North of England. The framework reference & title, start/ end date includes lots for contractors, associated professional services as well as a Dynamic Purchasing System (DPS) for the supply of Modular Homes.

Funding Source Grant

Ethical Contractor (EC): Mayor’s Employment Charter √ EC: Committed to sign up to charter √ EC: Accredited Living Wage Employer √

Executive summary

The purpose of this report is to seek approval for a variation the increase in costs to enable the building of 21 affordable homes at Tootal Grove.

BACKGROUND DOCUMENTS

• Homelessness Strategy • Lead Member for Property and Regeneration 8th November 2021: Salford’s Rough Sleepers Accommodation Programme (RSAP) Update • Procurement Board Report 11th May 2022: Construction of Move On accommodation through the Rough Sleepers Accommodation Programme (RSAP) • Procurement Board Report 31st Jan 2023 Award of contract for move on accommodation and affordable homes.

KEY DECISION: No

Sample B – award of contract DETAILS:

Background

On 31st January 2023 Procurement Board approved the council entering a contract with PLP Construction Ltd. to enable the building of 35 affordable homes at Eccles New Road and Tootal Grove. Each scheme had been value engineered to deliver savings and the councils cost consultant carried out a value for money assessment on the total scheme costs that concluded costs were reflective of the site conditions.

Since January both sites have discovered additional unforeseen contamination that has resulted in the scheme needing significant redesign and has extended the pre contract works period. The contractor was able to resolve issues at the Eccles New Road site and entered into contract with the council in June 2023 for the contract sum of £2,470,108 within the January 2023 Procurement Board approval, and work has currently started on site.

PB Approval Total Eccles New Road Tootal Jan 23 Contract Sum £ 7,186,826 £ 2,480,108 £ 4,706,718 Dec 23 Contract Sum £ 7,377,513 £ 2,480,108 £ 4,897,405 Increase £ 190,687

Tootal Grove originally had an original contract sum approval for £4,706,718. The contamination issues were more extensive and required an alternative design that has required additional planning approval, confirmed 8th December 2023. This has extended the pre contract works and costs have increased. The new cost for the Tootal Grove scheme is now £4,897,405.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tootal Grove Affordable Homes (Konrad Magdzinski)Report 178 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 6 attended
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, present
BH
Bill HindsCommittee Member, present
TK
Tracy KellyCommittee Member, apologies
JM
John Merry CBECommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Tootal Grove Affordable Homes (Konrad Magdzinski)This decision
  2. Tootal Road, John Atkinson Court, Myrtle Leaf Grove, Birch Leaf Grove - TRO 2158.Agreed

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies