MediaCity Development Regeneration Framework Approval

Approved Executive 2 papers

Cabinet approved this item on Tuesday 26 March 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Salford City Council - Record of Decision (Cabinet) I Paul Dennett, City Mayor, in exercise of the powers contained within the City Council Constitution do hereby: Approve the content of the development framework, in consultation with Cabinet. The Reasons are : The Regeneration Framework for MediaCity and Quayside has been prepared for the area and suggests enhancements, linking existing developments and significant public realm to new opportunities designed to further animate and activate the remaining development plots. Making use of the new Salford Quays Vision and continuing on from the highly successful early phases of MediaCity, the new masterplan offers up the opportunity to provide clarity on the approach to the primary area in the new town centre designation in the Local Plan. The framework approach has allowed the masterplan designers to look beyond the immediate development plots and show how other opportunities can integrate to create a more coherent high quality environment. A number of options were considered throughout the masterplan development with the reasoning behind the preferred option explained in the draft document. As well as enhancements to the public realm and connections there is the opportunity to provide additional homes, office floorspace, hotel and retail and leisure floorspace, over and above those already approved through existing applications. Consistent with other Regeneration Framework consultation, the draft document went to consultation for comment online, with a permanent exhibition held for a 6 week period. The results of the consultation were positive with a 74% approval of comments received. Overall, the Development Framework incorporates all of the lessons learned throughout the past ten years, meets the economic challenges post-pandemic and seeks to create a critical mass of people who live, visit and work in the area, that will not just provide more Salford opportunities, but also meet the challenges of creating a green, healthy, vibrant and sustainable town centre. Assessment of Risk : Low The Framework is designed to comply with the new Local Plan and largely builds from a number of known principles already accepted and approved as part of the 2016 Planning Approval. The process of consultation will mirror the process carried out for similar supplementary documents to ensure that if challenged it has a strong, considered understanding of issues. Risk of overdevelopment or significant harm to residential neighbours: Low, the changes whilst significant in planning terms are largely within parameters already set by the previously approved planning applications. Whilst residential numbers will increase, massing and scale will potentially be reduced with more public realm uses. The source of funding is : Funding for the consultation is provided by Peel L&P/Peel Media Legal Advice obtained : All processes will align with the legal requirements of a framework document with legal comments sought for the full draft. Whilst the document will not form a Development Document, the document will be approved by the council and with the process mirroring the Statutory processes for a Supplementary Planning Document it can be perceived to have a certain weight. All recommendations ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Cabinet

Part 1: Open to the Public – Item No

REPORT OF THE LEAD MEMBER FOR PLANNING, TRANSPORT AND SUSTAINABLE DEVELOPMENT

TO CABINET

ON

26th March 2024

TITLE: MediaCity Development Regeneration Framework Approval

RECOMMENDATIONS: That, the City Mayor in consultation with Cabinet approves the content of the development framework.

EXECUTIVE SUMMARY: 1.0 Summary

1.1The first phase MediaCity opened in 2011 and has since been extremely successful bringing new homes, jobs and subsequently vitality to Salford Quays.

1.2In 2016, a Reserved Matters planning application was approved covering a major next phase that would approximately double MediaCity in size. Since then several plots have been delivered with minor amendments and a further application for the C3 office has recently been approved.

1.3The passage of time together with changes in market conditions and planning context as well as ownership mean that future development is likely to come forward as a variance from the existing permissions.

1.4A new Development Framework will be prepared that covers the principles of development across the whole of the Salford Quays Principal Shopping Area

1 (as described in the Local Plan), it will include an interpretation of the planning policy to guide new development including layout, massing, access and uses. It will include comprehensive consultation with the public and stakeholders to reach shared objectives.

1.5Peel Media have commissioned Deloitte to give planning advice and provide the document, with Prior and Partners acting as Masterplanners, TTHC advising on movement and transport. A working group with Salford City Council has been established to ensure that the document aligns with up to date policy and guidance.

1.6A development framework allows a number of benefits for future planning of the area that would allow stakeholder engagement, discussions about future infrastructure requirements, whilst securing a status that provides flexibility where required to respond to timely opportunities to adapt but also the security and certainty as to how the framework will be interpreted.

1.7The new framework promotes an increased densification of the MediaCity site, with an increase in housing and office provision as well as looking at how they improve the interface with Quayside including linking spaces, supporting the way the area works better together. More emphasis is placed on the public realm, public transport arrival and activating spaces to improve the experience. More smaller scale retail for independents, health and community uses in Quayside, covered shelter and green space are all suggested in line with the requests coming through from community contained in the 2030 Vision.

1.8Main changes for the area from previous plans include:

• Increased density for both residential and office development (within the remaining MediaCIty phases), with an enhanced urban grain, whilst utilising the same radiating street pattern with a more human scale.

• Less car parking designed to reflect current reduced demand as a result of post pandemic Work from Home practices.

• Increased opportunities for activities, landscaping, public realm and ground floor activation.

• Better interaction between the Lowry, Quayside and MediaCity grouping the success of the place as an entirety.

• A character area based approach focusing on the unique aspects of the different areas.

2 1.9. The framework is compliant with the new Local Plan in its approach to all items. The framework highlights the fact that significant levels of public realm and infrastructure provision have already been delivered to mitigate the impact of the whole of the MediaCity development (rather just the components that have already been built to date) and builds upon the Quays vision 2030.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MediaCity Development Regeneration Framework ApprovalReport 1.9 MB DownloadRead as text
PDF
MediaCity and Quayside: EQIA ScopingReport 150 KB Download

At this meeting

Whole meeting

Who was there

15 of 31 attended
MA
Muna Abdel AzizCouncil Staff, expected
SA
Sharmina AugustCommittee Member, present
MB
Michele BarnesCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
SB
Sam BettsOfficer, expected
JC
Jim CammellCommittee Member, apologies
TC
Thomas CurranOfficer, expected
PC
Philip CusackCommittee Member, present
PD
Paul DennettCommittee Member, present
SD
Sarah DixonOfficer, expected
JF
Joanne FarrellOfficer, expected
JH
Jane HamiltonCommittee Member, present

All 31 on the meeting page

More from Salford Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Crisis Resilience Fund 2026/27Salford City Council - Record of Decision I Paul Dennett, City Mayor, in exercise of the powers contained within the ... Noted Open
25 Aug 2026 2026/27 Revenue Budget Monitoring and Capital Budget Monitoring - Quarter 1Salford City Council - Record of Decision (Cabinet) 2026/27 – Revenue Budget Monitoring – Quarter 1 I Paul Dennett, C... Approved Open
25 Aug 2026 Nature, Towns and Cities Programme - Nature City Accreditation and Refresh of the Greenspace StrategySalford City Council - Record of Decision (Cabinet) I Paul Dennett, City Mayor, in exercise of the powers contained w... Approved Open
11 Aug 2026 Proposal to designate a citywide Additional HMO Licensing Scheme for properties that fall within the Definition of Section 257 Houses in Multiple Occupation of the Housing Act 2004Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open
11 Aug 2026 Planned Carriageway Patching Programme - Local Highway Maintenance Fund 2026/27Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies