Single Homelessness Accommodation Programme (SHAP)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 14 May 2024. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Salford City Council - Record of Decision (Cabinet) I Paul Dennett, City Mayor, in exercise of the powers contained within the City Council Constitution do hereby approve: Single Homelessness Accommodation Programme (SHAP) The Reasons are : Delegate authority to the Executive Director of Place in consultation with the Section 151 officer to enter into a grant funding agreement with Homes England under the Single Homelessness Accommodation Programme 2023-28 for £2,052,000 allocated capital grant. Delegate authority to the Executive Director of Place in consultation with the Section 151 officer to enter into a grant funding agreement with Homes England under the Single Homelessness Accommodation Programme 2023-28 for £940,995 allocated revenue grant. Authorise the Shared Legal Service to prepare all necessary documentation and to take all steps which are required to give effect to the above recommendations. Options considered and rejected were: The SHAP proposal was informed by a strategic gap analysis on the youth homelessness pathway in Salford, which informed the target number of dwellings and type of accommodation required. As a result of the gap analysis and development gateway process other proposals were considered across different sites across the city. Assessment of Risk : The principal risk would be in the council failing to develop the SHAP proposals within the timescales of the programme or within the agreed terms of the grant funding agreement. Failure to meet delivery targets within the timescales or to the agreed terms may result in loss of grant. This is mitigated by further financial appraisal and the scheme will require further City Mayor approvals prior to entering into contract for the construction of the homes and drawing down grant. The source of funding is : Funding for the Single Homelessness Accommodation Programme is provided through Homes England in accordance with the Homes England capital funding guide. Legal Advice obtained : Homes England has confirmed that the Council has been awarded Single Homelessness Accommodation Programme (SHAP) 2023-28 capital grant to fund the delivery of the 18 SHAP Dwellings described in this report. Homes England has also confirmed that the Council has been awarded SHAP revenue grant to fund the provision of support services for the vulnerable young people who the Council has agreed will occupy the 18 SHAP Dwellings. The SHAP revenue grant will allow the Council to fund the provision of support services until 31 March 2028. Homes England has advised the Council that no changes can be made to their standard form of SHAP 2023-28 Grant Funding Agreement. The Council is therefore required to accept all the terms and conditions of the SHAP 2023-28 Grant Funding Agreement without any amendments. Separately, Council officers have been advised by Homes England that Homes England will agree to an extension of the completion date for the 18 SHAP Dwellings beyond 31 March 2025, although this will mean a 5% reduction of the amount of SHAP capital grant which the Council will receive from HE. The Council has advised Homes England that the Council proposes to transfer legal ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Cabinet

Recommendations

That,The City Mayor in consultation with Cabinet:

1. Delegate authority to the Executive Director of Place in consultation with the Section 151 officer to enter into a grant funding agreement with Homes England under the Single Homelessness Accommodation Programme 2023- 28 for £2,052,000 allocated capital grant.

2. Delegate authority to the Executive Director of Place in consultation with the Section 151 officer to enter into a grant funding agreement with Homes England under the Single Homelessness Accommodation Programme 2023- 28 for £940,995 allocated revenue grant.

3. Authorise the Shared Legal Service to prepare all necessary documentation and to take all steps which are required to give effect to the above recommendations.

Executive summary

The report details the award of capital and revenue funding by Homes England under the Single Homelessness Accommodation Programme (SHAP), for the delivery of high-quality affordable accommodation and support services for vulnerable young people at risk of or experiencing homelessness.

The award of grant responds to a strategic gap analysis undertaken by the council that has identified key gaps in service provision. Entering grant agreement with Homes England will support the delivery of units in the Walkden and Broughton neighbourhoods and provide additional benefit to the council by providing young vulnerable people with a home and the health, social and economic opportunities that brings.

1 BACKGROUND DOCUMENTS:

KEY DECISION: YES

DETAILS:

Background

The Single Homelessness Accommodation Programme 2023 – 2028 (SHAP) is a Department of Levelling Up Housing and Communities (DLUHC) backed funding programme that aims to address gaps in homelessness pathway provision by funding the delivery of high-quality accommodation with high levels of support. Funding has been directed to local authority areas with high levels of need for accommodation and support for SHAP’s “Target Client Groups”; those with the longest histories of rough sleeping or the most complex needs and vulnerable young people (age 18-25) who are experiencing or are at risk of homelessness or rough sleeping and who require support services to take care of themselves or be protected from harm or exploitation. The focus of the SHAP will be on the provision of longer-term accommodation for individuals who come within the definition of the Target Client Groups.

Councils have played a key role in framing the need for SHAP funding at a local strategic level through co-production of a Strategic Gap Analysis identifying gaps in local housing pathway provision relating to SHAP’s Target Client Groups. Under the programme, the Council and its partners were asked to be a provider of vulnerable young person’s accommodation in line with the findings of the gap analysis.

The capital funding element of the SHAP 2023-25 runs till 31 March 2025 and the final round for bidding was in November 2023. Following a period of engagement with DLUHC, the council, and its local housing company Dérive, developed and submitted a bid under the SHAP informed by findings of the strategic gap analysis.

Bidding under the SHAP is separated into two elements, a capital funding bid to support the development of a number of “SHAP Dwellings” and a revenue funding bid to enable provision of support for the individual members of the Target Client Group who will occupy the SHAP Dwellings, funded until the end of the SHAP on 31 March 2028.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Single Homelessness Accommodation Programme (SHAP)Report 77 KB DownloadRead as text

At this meeting

Whole meeting
3Minutes of the previous meetingOn the agenda
4Single Homelessness Accommodation Programme (SHAP)This decision
5Local Authority Housing Fund (Round 2+3)Approved

Who was there

16 of 29 attended
MA
Muna Abdel AzizCouncil Staff, present
SA
Sharmina AugustCommittee Member, present
BB
Barbara BenthamCommittee Member, present
SB
Sam BettsOfficer, expected
JC
Jim CammellCommittee Member, present
TC
Thomas CurranOfficer, expected
PC
Philip CusackCommittee Member, present
PD
Paul DennettCommittee Member, present
SD
Sarah DixonOfficer, expected
JF
Joanne FarrellOfficer, expected
JH
Jane HamiltonCommittee Member, present
BH
Bill HindsCommittee Member, present

All 29 on the meeting page

On this subject at Salford

Search all
  1. Single Homelessness Accommodation Programme (SHAP)This decision
  2. Award of contract for the construction of Single Homelessness Accommodation Programme (SHAP) accommodation and Affordable homes (Konrad Magdzinski)Approved

More from Salford Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Crisis Resilience Fund 2026/27Salford City Council - Record of Decision I Paul Dennett, City Mayor, in exercise of the powers contained within the ... Noted Open
25 Aug 2026 2026/27 Revenue Budget Monitoring and Capital Budget Monitoring - Quarter 1Salford City Council - Record of Decision (Cabinet) 2026/27 – Revenue Budget Monitoring – Quarter 1 I Paul Dennett, C... Approved Open
25 Aug 2026 Nature, Towns and Cities Programme - Nature City Accreditation and Refresh of the Greenspace StrategySalford City Council - Record of Decision (Cabinet) I Paul Dennett, City Mayor, in exercise of the powers contained w... Approved Open
11 Aug 2026 Proposal to designate a citywide Additional HMO Licensing Scheme for properties that fall within the Definition of Section 257 Houses in Multiple Occupation of the Housing Act 2004Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open
11 Aug 2026 Planned Carriageway Patching Programme - Local Highway Maintenance Fund 2026/27Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies