Hilton Lane Traffic Calming Improvements - Section 106 Contribution Expenditure.

Approved Planning 1 paper

Planning, Transport and Sustainable Development and Regeneration approved this item on Wednesday 9 April 2025. Below is the council's own wording, with the papers it was decided on.

Item3b

Resolved

Salford City Council - Record of Decision I, Councillor Mike McCusker, Lead Member for Planning, Transport & and Sustainable Development, in exercise of the powers contained within the Council Constitution , do hereby approve: The expenditure of £208,373.20 of Section 106 contributions towards delivering a traffic calming / road safety scheme on Hilton Lane. The reasons are : to meet the requirement of the relevant Section 106 Agreement detailed within the report. Options considered and rejected: Not applicable as the Section 106 Agreement detailed within the report requires expenditure on specific individual projects or types of projects. Assessment of risk: Low – The delivery of these highways improvements will satisfy the terms of the Section 106 agreement. The source of funding is : Section 106 contributions of £208,373.20 which have been received from the developments located at: § Hilton Lane (Section 106 Ref : 404 - 19/73971/FUL); Legal Advice obtained: Supplied by Robert Irvine, Shared Legal Service, 28 February 2025 Section 106 contributions can only be expended in accordance with the terms of the planning obligations outlined in the relevant Agreement. If the Council cannot demonstrate that the contribution has been expended in accordance with the Agreement, there is a risk that the contribution may need to be repaid to the developers. The accompanying report explains why officers are of the view that the expenditure set out herein would be in line with the terms of the Agreement. Financial Advice obtained : Supplied by Adam Mozley, Senior Trainee Accountant 13.02.2025 The £208,373.20 Section 106 funding as identified in the report has been received and is available to fund the works. Procurement Advice obtained: Not applicable The following documents have been used to assist the decision process: § Section 106 Agreement, Ref: 404 - 19/73971/FUL Contact Officer: Fiona Fryer Tel No 779 6044 This decision is not subject to consideration by another Lead Member. The appropriate scrutiny panel to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed: Councillor Mike McCusker Dated: 9 April 2025 Lead Member for Planning, Transport & Sustainable Development This decision was published on 11 th April 2025. This decision will come into force at 4.00 p.m. on 22 nd April 2025, unless it is called-in in accordance with the decision-making process rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Planning, Transport and Sustainable Development and Regeneration

Executive summary

It is proposed to utilise a total of £208,373 of secured Section 106 contributions towards improvement works to existing traffic calming measures along Hilton Lane to reduce average vehicle speeds, to create a safer environment.

BACKGROUND DOCUMENTS:

▪ N/A

KEY DECISION: NO

1 DETAILS:

Background

1.1In line with the council’s Planning Obligations Supplementary Planning Document (SPD), adopted in 2015 and refreshed in December 2019, Section 106 contributions were secured from a development on land at Hilton Lane (Section 106 Ref: 404 – planning application 19/73971/FUL).

1.2As required by Policy OB5 of the SPD contributions have been received from this development towards highways. For section 106 ref: 404 the full sum of £450,000 index linked has been received towards highways. The signed section 106 agreement(s) dated 9 March 2020 (s106 ref: 404), require(s) that the highways contribution be directed towards projects as follows: • £240,000 index linked to deliver pedestrian connections and safety improvements at the Hilton Lane/ Newearth Road roundabout • £200,000 index linked to deliver traffic calming/ road safety scheme on Hilton Lane and • £10,000 index linked towards cycle parking facilities at Walkden Train Station

1.3The wording of the agreement is therefore very specific as to the allocation of the highways contribution. This report seeks to allocate funding for the second of these projects; the first is the subject of a parallel approval report and the funding for cycle parking facilities was allocated in March 2022.

2.0Proposed uses of the s106 funding

2.1Ward councillors have been consulted and are very supportive of proposals to utilise up to £208,373.20 of s106 funding secured for highways improvements towards the improvement of the current traffic calming features along Hilton Lane. The additional £8,373.20 over the amount specified in paragraph 1.2 above represents the index linking which was applied to the total due in order to cover inflation between the date of the agreement and the date of payment.

2.2Currently, Hilton Lane has a series of traffic calming measures along its full length, implemented to support the 20-mph speed limit. However, these measures have proven ineffective based on recorded vehicle speeds and complaints from residents. The proposal looks to improve the situation by upgrading the existing cushions and installing new cushions to further control traffic speeds. In addition, the proposal looks to implement additional road narrowings as speed reduction feature and a provision for uncontrolled crossings.

2.3The proposed works will significantly improve safety for vulnerable road users along Hilton Lane, which is a pressing local issue.

3.0Wider benefits of the project

3.1The proposed works will aim to reduce average speed of vehicles going through Hilton Lane, to promote safety for pedestrians, cyclists and other motorists. The proposal also looks at

2 improving pedestrian accessibility especially around schools with the provision of uncontrolled crossing facilities, which promotes active travel.

Recommendation

That the Lead Member for Planning and Sustainable Development approves:

1. The expenditure of up to £208,373.20 of Section 106 contributions towards delivering traffic calming/road safety scheme on Hilton Lane

KEY COUNCIL POLICIES: ▪ Salford City Council Unitary Development Plan 2004-16 (2006); ▪ Planning Obligations Supplementary Planning Document (2015); and ▪ Planning Obligations Supplementary Planning Document (2019).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hilton Lane Traffic Calming Improvements: Section 106 Contribution Expenditure.Report 94 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 3 attended
PC
Philip CusackInvitee, in attendance
JH
Jane HamiltonInvitee, in attendance
MM
Mike McCuskerCommittee Member, present

On this subject at Salford

Search all
  1. Hilton Lane Traffic Calming Improvements - Section 106 Contribution Expenditure.This decision
  2. Hilton Lane Primary School - Section 106 ExpenditureApproved
  3. Hilton Lane / Newearth Road Roundabout Improvements - Section 106 Contribution Expenditure.Approved
  4. Approval to Award the Contract for Hilton Lane Primary School, roof works and external repairsApproved
  5. Land at Hilton LaneDeferred

More from Salford Planning, Transport and Sustainable Development and Regeneration

All decisions
MeetingDecisionOutcome
9 Sep 2026 Traffic Regulation Order 2453 - Chapel Street / Trinity Way / St Stephen Street & Ford Street, Blackfriars & Trinity and Ordsall) - Phase 1.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
9 Sep 2026 City of Salford (Camp Street, Grecian Street, Neptune Gardens, & Trojan Gardens, Broughton) (No Waiting At Any Time) Order 2025.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
12 Aug 2026 Irwell River Park Floating Wetland Habitats - Section 106 Contribution Expenditure.Salford City Council - Record of Decision I, Councillor McCusker, Deputy City Mayor and Lead Member for Planning, Tra... Approved Open
22 Jul 2026 Conservation Area Appraisals and Management Plans - Approval for Consultation, Proposed Boundary Changes, and Addition of a New Conservation Area.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
22 Jul 2026 Update of the Salford City Council Local List of Heritage Assets, to include updates to existing entries, removals from the list and new additions as well as amendments to the selection criteria.Salford City Council - Record of Decision I, Councillor Mike McCusker , Deputy City Mayor and Lead Member for Plannin... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies