Approval to Award the Contract for Hilton Lane Primary School, roof works and external repairs

Approved Committee 1 paper

Procurement Board approved this item on Wednesday 8 June 2022. Below is the council's own wording, with the papers it was decided on.

Item5a

Resolved

Salford City Council - Record of Decision I Councillor Hinds, Lead Member for Finance and Support Services and chairman of the Procurement Board , in exercise of the powers contained within the Council Constitution do hereby approve t he award of the following contract for a project approved under the schools condition grant as detailed below:- Detail required Answers Partial internal refurbishment of the Civic centre, Swinton Hilton Lane Primary School, roof works and external repairs Name of Successful Contractor Schofield & Sons Ltd Supplier Registration Number ( to be supplied by Corporate Procurement) 025459259 Type of organisation ( to be supplied by Corporate Procurement) Private Limited Company Status of Organisation ( to be supplied by Corporate Procurement) SME Contract Value £279,326.00 (£325,000 Full Project) Contract Duration 6 weeks Contract Start Date 25/07/2022 Contract End Date 02/09/2022 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? N/A Contact Officer (Name & number) Les Woolhouse Tel [phone removed] Lead Service Group People Services How the contract was procured? ( to be supplied by procurement) Framework Call-Off (Mini Competition) Framework Details (where applicable) ( procurement body, framework reference & title, start/ end date Minor Building Works Framework Lot 2 Funding Source Capital Programme Ethical Contractor Mayor’s Employment Charter Committed to sign up to the Charter Accredited Living Wage Employer Committed to become accredited The Reasons are : The works have been identified as essential maintenance from the schools asset management plan. This is the second and final phase of roof refurbishment and external repairs. The flat roofs at the rear of the school have exceeded their anticipated life span and require upgrading. The proposed works are for the installation of a cold applied liquid membrane roofing solution with tapered insulation. The external repairs are for the replacement if life expired UPVC and aluminium windows and doors to specified areas. Replacement of damaged cladding to specified areas to prevent water ingress. Options considered and rejected were : None. All procedures are in accordance with normal Contractual Standing Orders Assessment of Risk : High The roof and external areas have exceeded their anticipated life span. Failure to replace could result in costly remedial repairs which would only provide a short term solution. The source of funding is : Schools condition grant 2022/23 Expenditure code: E22004 Legal Advice obtained . Supplied by: The Shared Legal Service – – Contact Officer and telephone number: Tony Hatton – Principal Solicitor tel. 0161 219 6323 When commissioning contracts for the procurement of goods, services, or the execution of works, the Council must comply with the Public Contracts Regulations 2015 (PCR) and its own Contractual Standing Orders (CSO’s), failing which a contract may be subject to legal challenge from an aggrieved provider. The proposed award of the contract follows a tender exercise by mini competition in accordance with the Minor Building Works Framework Agreement Lot 2. The purpose of a framework agreement is to select through a procurement/ ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Executive summary

The purpose of this report is to seek approval for the award of the above mentioned contract.

BACKGROUND DOCUMENTS: Exempt under Paragraph 3 of Schedule 12A of the Local Government Act 1972

‘Tender Submissions and Evaluation Documents’

KEY DECISION: No

DETAILS:

Background

The works identified are the second and final phase of roof refurbishment and external repairs identified on the schools asset management plan.

The flat roofs to the rear have exceeded their anticipated life span and require upgrading. The proposed works are for the installation of a cold applied liquid membrane roofing solution with tapered insulation to achieve U values of 0.18W/m2. All works will be covered by a 20 year guarantee. The external works include the replacement of life expired UPVC and aluminium windows, which will also improve the ventilation to classrooms, assembly hall, office and ancillary areas. Replacement aluminium doors are also required for the assembly hall, external store rooms, boiler house and fuel store.

There are areas around the building where the cladding has deteriorated due to age. This is to be replaced with a Thermowood cladding which will be insulated and prevent water ingress into the building.

2. The Procurement Process

The works for this project have been tendered under the Council’s e-tendering portal in accordance with Contractual Standing Orders. Tenders were let by mini competition under the Minor Building Works Framework Lot 2 Agreement.

Two companies submitted a tender and these have been evaluated in accordance with selection criteria.

The evaluation scores are as follows:-

% Price % Quality % Overall Name of Bidder score score Score Max 70% Max 30% 100%

Schofield & Sons Ltd 70.00 22.00 92.00

Provider B 68.97 18.00 86.97

Following the evaluation process the company that scored the highest in accordance with the selection criteria was Schofield & Sons Ltd with a tender of £279,326.00. Their submission produced a score of 92.00% and represents the most economically advantageous offer to the Council which also supports social value.

3. Social Value

Schofield and Sons Ltd are a Salford based contractor with 85% of their in-house workforce are Salford residents. They are committed to actively employing construction professionals and trades from within the Salford area. They currently employ a year 1NVQ apprentice who lives in Salford.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to Award the Contract for Hilton Lane Primary School, roof works and external repairsReport 436 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 6 attended
PD
Paul DennettCommittee Member, apologies
AH
Anthony HiltonOfficer, present
BH
Bill HindsChair, present
TK
Tracy KellyCommittee Member, present
JM
John Merry CBECommittee Member, apologies
JY
Jack YoudCommittee Member, present

On this subject at Salford

Search all
  1. Approval to Award the Contract for Hilton Lane Primary School, roof works and external repairsThis decision
  2. Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Approved
  3. Approval to Award the Contract for the continued use of the Line of Business System for Planning, Building Control and Local Land and Property Gazetteer (Anthony Stephenson)Approved
  4. Approval to Award the Contract for Statutory Homeless Supported Temporary Accommodation (Jane Barlow)Approved
  5. Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan VinceApproved
  6. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies