Approval of revised indicative budget costs for expansion work, at Ellesmere Park High School and Primrose Hill Primary School

Approved Executive 1 paper

Cabinet approved this item on Tuesday 10 June 2025. Below is the council's own wording, with the papers it was decided on.

Item5b

Resolved

Salford City Council - Record of Decision I , Councillor Tracy Kelly, Statutory Deputy City Mayor, in exercise of the powers contained within the City Council Constitution do hereby approve: The associated indicative budget costs of £3,252,561.00 in respect of the creation of additional capacity at Ellesmere Park High School and Primrose Hill Primary School. The Reasons are : Local authorities have a statutory responsibility to ensure there are enough school places available in their area for every child aged 5 to 16. The creation of additional capacity across above two schools will support the city’s pupil demand position, enabling the young people of the city, access to local school provision . Options considered and rejected were: None Assessment of Risk : The creation of additional pupil capacity will assist the city council in fulfilling its statutory duty in relation to the provision of sufficient school places. The source of funding is : The cost of works will be met with the Basic Need grant allocations available . Legal Advice obtained : Local authorities have a statutory responsibility to ensure there are enough school places available in their area for every child aged 5 to 16 needing one, as set out in section 14 of the Education Act 1996. The Department of Education (DfE) provides Basic Need capital grant funding to local authorities to support them to meet that statutory responsibility. The Basic Need Grant can be used to create new school places in mainstream schools. The Grant helps local authorities meet the growing demand for school places and ensure that all children, including those with SEND, have access to suitable education environments. The funding is un-ringfenced (subject to certain conditions that ensures any funding paid out under this grant is spent efficiently) and it is for local authorities to determine how to best use the funding to meet local priorities. In relation to efficient use of resources DfE guidance states: “The department expects local authorities to conduct a robust evaluation of procurement options for any education capital projects.” In relation to using the Grant to create new places DfE guidance states: “When expanding existing schools, we expect local authorities to create new places at schools (including academies and free schools) with an overall Ofsted rating of good or outstanding, and to notify the department where it is not possible to do so. We also expect local authorities to prioritise schools with strong performance records by considering a range of performance indicators and financial data, when deciding to expand a school. Expansion can offer school leaders the opportunity to reach more local children and to achieve greater financial economies of scale. All schools should be flexible in considering how best they can support the local authority to deliver its sufficiency duty. We expect school leaders and academy trusts to collaborate effectively with local authorities, expanding where feasible when requested to do so by a local authority, or increasing their admission numbers where they have capacity, in order to meet a ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Cabinet

Executive summary

This report provides an update on the progress delivery for the planned expansion building works at both Ellesmere Park High and Primrose Hill Primary Schools as of September 2025. The works being undertaken will allow for the creation of additional school places to support the pupil demand position across these two areas of the city.

Both schemes were initially scheduled to be delivered in September 2024, however complexities around delivery resulted in works being deferred. Work across both schools will now commence on site over the summer with additional school places being available to support pupil demand for September 2025 intake.

Approval in respect of budget costs for both, of the schemes had previously been, sought for which funding remains allocated. There have been further enhancements

1 to the schemes, part of which includes the use of temporary accommodation to support the demand position for September 2025. This has resulted in an increase in the overall budget costs across both schools. The purpose of this report therefore is to seek approval for the additional associated costs in respect of the two projects.

Details of the revised scope of works and indicative budget costs are, contained in section 2 of this report. Details of the previously approved budget costs are also, included at section 2.

BACKGROUND DOCUMENTS:

KEY DECISION: YES

DETAILS:

Background

1.1This report provides an update on the progress delivery for the planned expansion building works at both Ellesmere Park High and Primrose Hill Primary Schools.

1.2Officers have been working, closely with partners to progress the schemes and works across both schools are now due to commence on site over the summer, with additional school places being available to support the demand position for September 2025 intake.

1.3As part of the works, a further review of both projects has been, undertaken by officers and additional works have been, identified. This includes the use of temporary accommodation across both schools to support the demand position for September 2025. This has resulted in an increase in the overall budget costs for both schemes.

1.4Approval in respect of budget costs for both schemes had previously been, sought, for which funding remains allocated.

1.5The purpose of this report therefore is to provide an update on the progress of the planned works and to seek approval for the additional associated budget costs in respect of the revised scope of works.

1.6Details of the revised scope of works, indicative budget costs and available funding stream are, contained in section 2 of this report.

2 2. REVISED SCOPE OF WORKS, INDICATIVE BUDGET COSTS AND FUNDING STREAM

Ellesmere Park High Project

2.1Previous cost approval of £2,847,439.00 was sought (report dated 13 April 2023) to support the expansion works at Ellesmere Park High School, initially planned for delivery September 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval of revised indicative budget costs for expansion work, at Ellesmere Park High School and Primrose Hill Primary SchoolReport 94 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
PD
Paul DennettCommittee Member, apologies
TK
Tracy KellyCommittee Member, present
JY
Jack YoudCommittee Member, apologies
BB
Barbara BenthamCommittee Member, apologies
JC
Jim CammellCommittee Member, present
MM
Mike McCuskerCommittee Member, present
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, present
MB
Michele BarnesInvitee, in attendance
JM
Joshua Mark BrooksInvitee, in attendance
JH
Jane HamiltonInvitee, apologies

All 16 on the meeting page

On this subject at Salford

Search all
  1. Approval of revised indicative budget costs for expansion work, at Ellesmere Park High School and Primrose Hill Primary SchoolThis decision
  2. Request for Approval - Contract Award - MCF Trinity Way/Springfield Lane Junction Improvement Scheme - Anene Chiegboka - Revised report attached.Approved

More from Salford Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Crisis Resilience Fund 2026/27Salford City Council - Record of Decision I Paul Dennett, City Mayor, in exercise of the powers contained within the ... Noted Open
25 Aug 2026 2026/27 Revenue Budget Monitoring and Capital Budget Monitoring - Quarter 1Salford City Council - Record of Decision (Cabinet) 2026/27 – Revenue Budget Monitoring – Quarter 1 I Paul Dennett, C... Approved Open
25 Aug 2026 Nature, Towns and Cities Programme - Nature City Accreditation and Refresh of the Greenspace StrategySalford City Council - Record of Decision (Cabinet) I Paul Dennett, City Mayor, in exercise of the powers contained w... Approved Open
11 Aug 2026 Proposal to designate a citywide Additional HMO Licensing Scheme for properties that fall within the Definition of Section 257 Houses in Multiple Occupation of the Housing Act 2004Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open
11 Aug 2026 Planned Carriageway Patching Programme - Local Highway Maintenance Fund 2026/27Salford City Council - Record of Decision (Cabinet) I, Tracey Kelly, Statutory Deputy City Mayor, in exercise of the ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies