2026/27 CRSTS Highways Core Programme.

Approved Planning 2 papers

AI summaryLead Member approves 2026/27 CRSTS Highways Core Programme worth £3,143,000 for road safety, bridges, walking and cycling schemes across Salford.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved2026/27 CRSTS Highways Core Programme
Money£3,143,000Total CRSTS Highways allocation for 2026/27
What happens nextDelivery in 2026/27Future years' allocations to be approved later
Who it affectsAll Salford wardsCity-wide roads, bridges, walking and cycling

What was decided

The Lead Member approved the 2026/27 CRSTS Highways Core Programme, allocating £3,143,000 across six categories of work. Report P1, P14

Two major local safety schemes were endorsed: a £600k junction improvement at Bury Old Road/Singleton Road and a £425k scheme at A6 Manchester Road/Cleggs Lane/Armitage Avenue, which also draws in £775k of S106 funding from the Logistics North development. Report P18, P19

Indicative allocations for 2027/28 and 2028/29 are included in Appendix A for reference, but approval for those years is not being sought at this stage. Report P2, 2.3

Why

To enable delivery of the projects detailed in the programme. Report P2

Failure to spend capital allocations in line with government guidelines could reduce future settlement levels for both the council and GMCA. Report P44

The proposed schemes are expected to improve road and pedestrian safety, encourage use of cycle routes, and strengthen the council's position in defending third party highway claims under section 58 of the Highways Act 1980. Report P51

What happens next

Schemes are to be delivered during the 2026/27 financial year, funded from the CRSTS capital allocation. Report P60

Expenditure is to be closely monitored so schemes are delivered within allocated resources. Report P61

Any individual project valued at more than £150,000 will require a separate report to Procurement Board; smaller schemes can be awarded directly under Lot 1 Minor Civils of the SCC Technical and Highways Works Framework. Report P56, P66

The money

  • £3,143,000 Total 2026/27 CRSTS Highways allocation to Salford Report 1.3, P14
  • £1,035,000 Local Safety Schemes category Report P14
  • £1,000,000 Structures & Bridges category Report P14
  • £351,000 Highway Maintenance category Report P14
  • £267,000 Schemes to Assist Walking & Cycling category Report P14
  • £90,000 Other Minor Works category Report P14
  • £400,000 Community Committee Schemes (eight committees at £50k each) Report P14, P40
  • £600k Bury Old Road/Singleton Road junction improvement Report P18
  • £425k A6 Manchester Road/Cleggs Lane/Armitage Avenue junction improvement Report P19
  • £775k S106 contribution from Logistics North development, to be used on the A6 scheme Report P19
  • £450k Cross Lane Subway/Roundabout parapet replacement Report P21
  • £250k Pothole Action Fund contribution to planned carriageway maintenance Report P29
  • £150,000 Threshold above which a separate Procurement Board report is needed Report P56

Options considered

  • Chosen: Approve the 2026/27 CRSTS Highways Core Programme. To enable delivery of the listed projects in 2026/27 Report P1
  • Rejected: No alternative options were considered

Implications

  • Legal: The council acts within its powers as highway authority under Part V of the Highways Act 1980; section 58 provides a possible defence to third party claims where a robust inspection and maintenance regime is shown. Report P48, P49, P50, P51
  • Legal: Any Traffic Regulation Orders needed must follow the Road Traffic Regulation Act 1984; dropped crossings do not need a TRO. Report P52, P53
  • Financial: Expenditure will be met from the CRSTS Highways Consolidated Highways capital allocation 2026/27; figures are preliminary and subject to further approvals. Report P60, P62
  • Risk: Failure to spend in line with government guidelines may impact future settlement levels for the council and for GMCA as a whole. Report P44
  • Staffing: There are no HR implications associated with this report. Report P70
  • Climate: Climate change implications will be assessed on a project-by-project basis. Report P72
  • Other: Procurement will use the SCC Technical and Highways Works Framework where suitable, with further competition for schemes over £150k; the service will look for efficiencies and savings as part of procurement activity. Report P66, P67, P68

Who and where

  • All wards in Salford (city-wide) Report P75
  • Road users, pedestrians and cyclists in the vicinity of named schemes including Bury Old Road, A6 Manchester Road, Cross Lane and Broadway Link Road Report P18, P19, P21, P26
  • Members of the public and councillors who have requested dropped crossing improvements Report P37
  • The eight community committees, each receiving £50k of devolved funding Report P40

Timeline

  • 2026/27 financial year: Delivery of the approved CRSTS Highways Core Programme Report P2
  • 2027/28 and 2028/29: Indicative future allocations shown; separate approval to be sought in later years Report P2, 2.3

Plain English for the jargon

  • CRSTS: City Regions Sustainable Transport Funding, a five-year settlement from the Department for Transport to the Greater Manchester Combined Authority
  • DfT: Department for Transport
  • GMCA: Greater Manchester Combined Authority
  • PROW: Public Right of Way
  • S106: Section 106 planning obligation contribution, here from the Logistics North development
  • TRO: Traffic Regulation Order, made under the Road Traffic Regulation Act 1984
  • TCR: Transport for City Regions, the successor settlement to CRSTS
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4g

Resolved

Salford City Council - Record of Decision I, Councillor Mike McCusker, Lead Member for Planning, Transport & Sustainable Development, in exercise of the powers contained within the City Council Constitution , do hereby – Approve the The Reasons are : To enable the delivery of the projects detailed within the programme in the 2025/26 financial year Options considered and rejected were: N/A Assessment of Risk : Failure to spend Capital Allocations on initiatives in line with Government guidelines may impact on future settlement levels, both for the City Council and for GMCA as a whole. The source of funding is : 2026/27 CRSTS Highways Core Legal Advice obtained : Tony Hatton, Principal Solicitor – 12/02/2026 Under Part V of the Highways Act 1980 (“the Act”), the Council acting in its capacity as the highway authority, shall have general and express powers in relation to any highway maintainable at public expense by them, any work for the improvement of the highway other than the work of lighting which is expressly provided for under Section 97 of the Act. Under s41(1) the Act the authority who are for the time being the highway authority for a highway maintainable at the public expense are under a duty subject to subsections (2) and (4) to maintain the highway. Subsection (2) and (4) do not apply to the proposals contained within this report. Under s329 of the Act ‘maintenance’ includes repair. In that regard, there are no legal implications as the Council, as highway authority, is acting within its powers. However, failure to maintain the highway may have adverse implications. The proposals in the report for the programmes, once finalised scheme details within each of the specified categories of work have been submitted, will strengthen the Council’s position in defending 3 rd party highway/tripping claims. Whilst it is legally accepted that it is not possible to maintain the highway completely free of all defects, section 58 of the Highways Act 1980 provides a possible defence to a claim if it can adequately show that there was a sufficiently robust regime in place to inspect and maintain the highway provided it is adequately carried out and the Council had no prior knowledge of the defect before an alleged incident. The proposed schemes will also improve road safety, pedestrian/public safety, and encourage the further use of safer cycle routes. In relation to any proposed Traffic Regulation Orders, these should not give rise to any legal implications provided the works are carried out in accordance with the appropriate statutory requirements set out in the Road Traffic Regulation Act 1984. The proposed dropped crossings can be introduced without delay because no Traffic Regulation Order is required for these. To ensure all users have the ability to safely access and use dropped crossing facilities that the Council has installed, the Council has powers subject to exemptions under the Traffic Management Act 2004 to fine and remove vehicles that are parked at dropped crossings within any special ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Planning, Transport and Sustainable Development and Regeneration

Recommendations

That the Lead Member for Planning & Sustainable Development approves the 2026/27 CRSTS Highways Core Programme.

Executive summary

This report presents the proposed CRSTS Highways Core Programme for 2026/27 for approval, providing details of the funding allocations across six categories. Two future years are also presented in the programme, giving detail of the proposed funding allocations in 2027/28 and 2028/29. Approval is not being sought for the later years at this stage to retain flexibility, but they are indicative of the potential future direction.

BACKGROUND DOCUMENTS:

- 2026/27 CRSTS Programme (Appendix ‘A’ of this report) - Report to Property & Regeneration Board: ‘CRSTS update and Strategic Maintenance Priorities’ 27/03/2023 - CRSTS Funding Settlement Letter for Greater Manchester 01/04/2022

1 KEY DECISION: No

DETAILS:

Background

1.1The Department for Transport (DfT) announced the award of the City Regions Sustainable Transport Funding (CRSTS) to the Greater Manchester Combined Authority (GMCA) on 1st April 2022. This is a five-year settlement from DfT to GMCA for all ten regions of Greater Manchester.

1.2A component of the CRSTS funding is an annual allocation for Highways Maintenance projects. This replaces the annual settlement formerly known as Block 3 received from DfT and consolidates other sources of funding into a single pot.

1.3The amount of funding allocated to Salford City Council in the CRSTS for Highway improvements per financial year is £3.143m, which has been allocated to the projects/programmes identified in this report.

1.4The funding is provided for minor infrastructure improvement projects such as: road safety schemes; structure/bridge improvements; schemes to improve walking & cycling facilities, etc.

1.5The details of the funding beyond 2026/27 are currently unknown and are subject to the provision in the Transport for City Regions (TCR) settlement which replaces CRSTS for the following five years.

Proposals

2.1The programme has been split into the following categories and allocations for 2026/27:

Category Allocation Local Safety Schemes £1,035,000 Structures & Bridges £1,000,000 Highway Maintenance £351,000 Schemes to Assist Walking & Cycling £267,000 Other Minor Works £90,000 Community Committee Schemes £400,000 TOTAL 2026/27 Allocation £3,143,000

2 2.2 Details of the significant project allocations within the above categories are provided below. NB: lower value, self-explanatory items are not shown below but can be seen in the detailed programme which is enclosed in Appendix A. The allocations are representative of the current estimated costs which may change as the projects progress to delivery.

2.3Details of the proposed programme for the following two years are provided as an indication of the potential future direction. This is reflective of strategic planning and current priorities, but may change prior to approval being sought in later years.

2.4Local Safety Schemes

• Bury Old Road/Singleton Road - £600k Delivery of a junction improvement scheme, the development of which has been funded in previous years. The works will introduce controlled pedestrian facilities at the junction, where there are currently none.

• A6 Manchester Road/Cleggs Lane/Armitage Avenue - £425k Delivery of a junction improvement scheme, the development of which has been funded in previous years, similar to the above. The works will improve the pedestrian and cycle facilities at the junction. A S106 contribution of £775k from the Logistics North development is to be utilised.

2.5Structures & Bridges

• Cross Lane Subway/Roundabout Parapet Replacement - £450k Following a review of the condition during a routine inspection, it was determined that a scheme to replace the existing parapets was required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2026/27 CRSTS Highways Core Programme.Report 123 KB DownloadRead as text
PDF
CRSTS Core ProgrammeAppendix A 212 KB Download

At this meeting

Whole meeting

Who was there

1 of 3 attended
JM
Joshua Mark BrooksInvitee, in attendance
BG
Ben GroganInvitee, in attendance
MM
Mike McCuskerCommittee Member, present

On this subject at Salford

Search all
  1. 2026/27 CRSTS Highways Core Programme.This decision
  2. 2025/26 CRSTS Consolidated Highways Programme.Approved
  3. 2024-25 CRSTS Consolidated Highways Programme.Approved

More from Salford Planning, Transport and Sustainable Development and Regeneration

All decisions
MeetingDecisionOutcome
9 Sep 2026 Traffic Regulation Order 2453 - Chapel Street / Trinity Way / St Stephen Street & Ford Street, Blackfriars & Trinity and Ordsall) - Phase 1.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
9 Sep 2026 City of Salford (Camp Street, Grecian Street, Neptune Gardens, & Trojan Gardens, Broughton) (No Waiting At Any Time) Order 2025.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Refused Open
12 Aug 2026 Irwell River Park Floating Wetland Habitats - Section 106 Contribution Expenditure.Salford City Council - Record of Decision I, Councillor McCusker, Deputy City Mayor and Lead Member for Planning, Tra... Approved Open
22 Jul 2026 Conservation Area Appraisals and Management Plans - Approval for Consultation, Proposed Boundary Changes, and Addition of a New Conservation Area.Salford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
22 Jul 2026 Update of the Salford City Council Local List of Heritage Assets, to include updates to existing entries, removals from the list and new additions as well as amendments to the selection criteria.Salford City Council - Record of Decision I, Councillor Mike McCusker , Deputy City Mayor and Lead Member for Plannin... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies