Salford City Council
Procurement Board, Monday 13 April 2026 at 2.00pm

ADDENDUM REPORT - Approval to Award the Contract for Monton Canal Bridge VRS Protection Scheme (Jack McClung)

Approved Committee 1 paper

AI summarySalford City Council's Lead Member for Finance and Support Services has approved awarding a £237,200.00 contract to Coating Services Limited for the Monton Canal Bridge Vehicle Restraint System Protection Scheme, after the original winner withdrew.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOriginal winner withdrew over a contract clause
Money£237,200.00 contract, £326,800.39 schemeFunded from 2025/26 Highways Capital Programme
What happens nextWorks run for 14 weeksCorrected dates: 04/05/2026 to 07/08/2026
Who it affectsThree Salford wardsEccles, Worsley and Westwood Park, Barton and Winton

What was decided

Councillor Youd, as Lead Member for Finance and Support Services and chairman of the Procurement Board, approved awarding the contract for the Monton Canal Bridge Vehicle Restraint System Protection Scheme to Coating Services Limited. Report P1, P2

The award goes to the second placed bidder, Coating Services Limited, because Amalgamated Construction Limited withdrew after declining to accept the contract terms offered by the council. Report P31, P32

Why

The original winning bidder, Amalgamated Construction Limited, withdrew because it would only proceed if a clause limiting its liability was added, which the council judged would have made the competitive tender process unfair. Report P31, P32

Without the scheme, a vehicle collision could cause significant structural damage to the bridge, leading to closure and disruption on Parrin Lane and the wider community of Monton, with no simple diversion available. Report P13, P50

The works form part of the on-going rolling programme of structural repair works within the 2025/26 CRSTS Consolidated Highways Programme, providing trief kerbs to protect the existing bridge structure from vehicular impact. Report P18, P14

What happens next

Coating Services Limited will carry out the main works over 14 weeks, including trief kerb installation, widening of the north footway, installation of bridge expansion joints, resurfacing of about 1,900 m2 of Parrin Lane and footways, and reinstatement of highway lining. Report P2, P14, P15

Traffic management will use two way lights during off peak hours, with night road closures from 22:00 to 05:30 for surfacing works and an approved diversion route. Report P16

The decision is open to call in by the Growth and Prosperity Panel as the appropriate Scrutiny Committee.

The money

  • £ 237,200.00 Contract value awarded to Coating Services Limited Report P2, P21
  • £ 326,800.39 Total scheme value Report P2, P21, P63
  • £152,200.00 CRSTS grant funding from DfT via GMCA Report P19, P63
  • £174,600.39 Unsupported Borrowing allocated to the scheme Report P19, P63
  • £33,152.15 Quantified Risk Assessment, reduced from £50,000.00 to cover higher target cost Report P21, P23
  • £41,250 Budget retained in 2025/26 for initial costs, remainder re-profiled into 2026/27 Report P64
  • £74,460.34 Total social value committed by Coating Services Limited for the project Report P37
  • £ 950.00 In-kind donations to local community-based improvement projects Report P41, P43

Options considered

  • Chosen: Award the contract to Coating Services Limited (second placed bidder). Original winner withdrew over a contract clause that the council could not add without disadvantaging other bidders Report P31, P32
  • Rejected: Not to award the contract. Would leave the bridge exposed to collision damage and the risk of substantial repair costs or closure Report P50

Implications

  • Financial: Total scheme budget of £326,800.39 is funded from the 2025/26 Highways Capital Programme, with £152,200.00 from CRSTS and £174,600.39 from Unsupported Borrowing, and the Senior Accountant judged financial risk as low. Report P52, P63, P65, P66
  • Legal: The Principal Solicitor confirmed the procurement followed a compliant mini-competition under the Technical and Highways Minor Civils Works Framework Lot 4 and met the Public Contracts Regulations 2015 and the Council's Contractual Standing Orders. Report P56, P57, P58, P59
  • Equalities: Officers assessed no adverse equality implications and noted the scheme helps less able bodied and visually impaired people by maintaining the highway structure. Report P47
  • Risk: Risk is rated Low because the council's Engineering and Landscape Department is experienced in such works, though the cost of post-collision repairs would likely be substantial compared with the proposed measures. Report P48, P49, P50
  • Other: Coating Services Limited is a member of the Mayor's Employment Charter, is an Accredited Living Wage Employer, and will deliver social value including employing 3 local direct recruits, spending around £27,000 with local micro and small supply chain partners, and donating £950.00 in kind. Report P36, P37, P38, P40, P41

Who and where

  • Residents and road users in Eccles Ward, Worsley and Westwood Park Ward, and Barton and Winton Ward Report P77
  • Pedestrians, cyclists and motorists crossing Monton Canal Bridge on Parrin Lane Report P13, P14
  • Local supply chain partners expected to receive about £27,000 in spend from the contractor Report P40
  • Community groups including Langworthy Cornerstone and Lower Kersal Young People and Community Group Report P43

Timeline

  • 5th November 2025: Tender documents issued through The Chest under Structures and Bridges Lot 4 of the Technical and Highways Works Framework Report P25
  • 12th December 2025: Revised tender submission date after extension granted to contractors Report P25
  • 9th January 2026: Legal advice provided by the Principal Solicitor Report P54, P55
  • 12th January 2026: Financial advice provided by the Senior Accountant Report P61, P62
  • 26th January 2026: Original budget approved at Procurement Board meeting Report P22
  • March 2026: Procurement advice provided by the Category Manager
  • 13 April 2026: Decision signed by Councillor Youd, Lead Member for Finance and Support Services
  • 04/05/2026: Contract start date as corrected in the addendum report Report P2
  • 07/08/2026: Contract end date as corrected in the addendum report Report P2

Plain English for the jargon

  • VRS: Vehicle Restraint System, the edge protection to be installed on the bridge
  • ITT: Invitation to Tender, the procurement method used
  • Mini-competition: A call-off competition run between providers on an established framework
  • CRSTS: City Region Sustainable Transport Settlement, the grant funding stream from DfT via GMCA
  • PCR 2015: Public Contracts Regulations 2015, the procurement rules the council must follow
  • CSO: Contractual Standing Orders, the council's own procurement rules
  • Trief kerbs: A profiled kerb unit used to shield bridge structures from vehicle impact
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5e

Resolved

Salford City Council – Record of Decision I Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: Detail required Answers Title/ Description of Contracted Service/Supply/Project Monton Canal Bridge VRS Protection Scheme Procurement Reference numbers (DN and CR number supplied by Procurement) DN794586 / S1232/122 Name of Successful Contractor Coating Services Limited Supplier Registration Number (to be supplied by Procurement 3852483 Proclass Classification No. (to be completed by procurement) 391200 Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by Procurement) Non-SME Contract Value (£) £ 237,200.00 Total Scheme value £ £ 326,800.39 Contract Duration 14 Weeks Contract Start Date 02/03/2026 Contract End Date 22/05/2026 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? Deputy Chief Executive (Executive Director of Place) (extension < £150k) Contact Officer (Name & number) Jack McClung - [phone removed] · to Award the Contract forMonton Canal Bridge Vehicle Restraint System (VRS) Protection Scheme, as detailed in the table below: Lead Service Group Place How the contract was procured? (to be supplied by procurement) ITT Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Technical and Highway Works – Lot 4 – Structures & Bridges Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Employment Charter No EC: Committed to sign The Mayor’s Employment Charter Yes EC: Committed to the principles outlined in the Mayor’s Employment charter N/A EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living wage Employer N/A The Main works are Monton Canal Bridge Vehicle Restraint System Protection Scheme. Options considered and rejected were : Not to award the Contract. Assessment of Risk : Low – Salford City Council Engineering and Landscape Department are well versed in delivering works of this nature. The risk of not undertaking the works is that a vehicular collision could cause structural damage to the bridge resulting in a bridge closure and significant impact on the Highway Network, with no simple diversion route available to lessen the impact on the passage of vehicles. Furthermore, the cost for the repair works following vehicle collision are likely to be substantial in comparison to the cost of the vehicular restraint measures proposed. The source of funding is : the 2025/26 Highways Capital Programme. Legal Advice obtained : 9 th January 2026 – received from Tony Hatton, Principal Solicitor. Financial Advice obtained : 12 th January 2026 – Received from Ian Cowburn, Senior Accountant. Procurement Advice obtained: 20 th March 2026 – Received from Heather Stanton, Category Manager. Contact Officer: Jack McClung Telephone number: [phone removed] · This matter is not subject to consideration by another Lead Member. · The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Panel Signed: Cllr J Youd Dated: 13 April 2026. Lead Member FOR DEMOCRATIC SERVICES USE ONLY: * This decision was published ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board recommends Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board approve the award of the Contract for Monton Canal Bridge Vehicle Restraint System (VRS) Protection Scheme, as detailed in the table below:

Monton Canal Bridge Vehicle Restraint System Protection Scheme – Procurement Board Report – Addendum – Award of Contract Detail required Answers Title/Description of Contracted Monton Canal Bridge VRS Protection Service/Supply/Project Scheme Procurement Reference numbers (DN and DN794586 / S1232/122 CR number supplied by Procurement) Name of Successful Contractor Coating Services Limited Supplier Registration Number 3852483 (to be supplied by Procurement Proclass Classification No. 391200 (to be completed by procurement) Type of organisation Private Limited Company (to be supplied by Procurement) Status of Organisation Non-SME (to be supplied by Procurement) Contract Value (£) £ 237,200.00 Total Scheme value (£) £ 326,800.39 Contract Duration 14 Weeks Contract Start Date 04/05/2026 Contract End Date 07/08/2026 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? Deputy Chief Executive (Executive Director of Place) (extension < £150k) Contact Officer (Name & number) Jack McClung - [phone removed] Lead Service Group Place How the contract was procured? ITT (to be supplied by procurement) Framework Details (where applicable) Technical and Highway Works – Lot 4 – (procurement body, framework reference Structures & Bridges & title, start/ end date Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Yes Employment Charter N/A EC: Committed to sign The Mayor’s Employment Charter

EC: Committed to the principles outlined N/A in the Mayor’s Employment charter

Monton Canal Bridge Vehicle Restraint System Protection Scheme – Procurement Board Report – Addendum – Award of Contract Yes EC: Accredited Living Wage Employer

EC: Committed to becoming Accredited N/A Living wage Employer

Executive summary

The purpose of this report is to seek approval for the award of the above-mentioned contract.

BACKGROUND DOCUMENTS:

Bridge asset file held on Pontis (digital asset management system for bridges) and in the archive files within the Councils Bridges and Structures Department.

KEY DECISION:

No – if the value of the decision is between £150,000 and £349,999

DETAILS:

Background

Monton Canal Bridge carries Parrin Lane over the Bridgewater Canal in Monton.

During a routine structural inspection, it was identified that the only means of edge protection on the bridge, was in fact the edge beams of the structure. Whilst these would suitably stop vehicles from falling off the bridge into the watercourse below, should these edge beams suffer impact damage, there could be significant structural damage caused and in turn, loss of functionality of the structure resulting in the need for emergency repairs and in the worst case, replacement of the entire structure. This would cause serious disruption along Parrin Lane and the wider community of Monton.

It is intended that the scheme works will improve the safety of pedestrians (cyclists) and vehicles. The works involved in the scheme are as followed: • Installation of trief kerbs over the bridge • Widening of North Footway • Installation of bridge expansion joints • Resurfacing approximately 1900m2 of Parrin Lane and footways over structure (previously part of proposed SCC Highway Network Management Scheme, taken on by SCC Structures & Bridges team to minimise disruption to the Local Highway Network) • Reinstate Highway lining

Monton Canal Bridge Vehicle Restraint System Protection Scheme – Procurement Board Report – Addendum – Award of Contract • General minor civils works

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ADDENDUM REPORT: Approval to Award the Contract for Monton Canal Bridge VRS Protection Scheme (Jack McClung)Addendum 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 9 attended
BB
Barbara BenthamInvitee, in attendance
PD
Paul DennettCommittee Member, present
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
MM
Mike McCuskerInvitee, in attendance
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. ADDENDUM REPORT - Approval to Award the Contract for Monton Canal Bridge VRS Protection Scheme (Jack McClung)This decision
  2. ADDENDUM REPORT - Request approval to extend the contract for Community Protection/ Refuse Collection software (Place) from 01/04/2026 to 31/03/2028 (Matt Wylie)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies