Procurement Board, Monday 11 May 2026 at 2.00pm

Cleggs Lane/ A6 Junction Improvement Scheme Approval to award the tender (Nicola Smithies)

Approved Committee 2 papers

AI summarySalford City Council awards Rosgal Ltd a £837,521.29 contract for junction improvement works at Cleggs Lane and A6 Manchester Road, running from 18/05/2026 to 04/12/2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCleggs Lane / A6 junction scheme
Money£837,521.29Funded from Capital Programme
What happens nextWorks start 18/05/2026Contract ends 04/12/2026
Who it affectsJunction users and pedestriansSafety concerns from local representatives

What was decided

The City Mayor accepted the Procurement Board recommendation to award the contract for the Cleggs Lane / A6 Manchester Road Junction Improvement Scheme to Rosgal Ltd.

The contract runs for 7 months from 18/05/2026 to 04/12/2026, with no optional extension periods.

The contract was procured through the Bolton Council 2024/28 Highways Framework Contract, Lot 1, using a PSR Competitive Process.

Why

The junction is a site of concern due to a high number of recorded collisions and a current lack of cycling facilities, with existing narrow pedestrian refuges and substandard cycle provision creating difficulties, particularly for vulnerable users.

Between August 2019 and August 2024, seven collisions were reported at the site, all of slight severity.

Representations about the junction have been received from the local MP, ward members and the public, mostly focused on safety.

What happens next

The contractor will deliver the works between 18/05/2026 and 04/12/2026, with any required traffic orders to be submitted to the council's streetworks officer. Report P13

Rosgal Ltd will carry out the works in line with the issued highways drawings and specification listed in the drawing notes. Report P12, P20

The council considers the risk to delivery as low, based on similar junction improvement projects previously delivered successfully.

The money

  • £837,521.29 Contract value for the junction improvement scheme, funded from the Capital Programme

Options considered

  • Chosen: Do Minimum (chosen): provide appropriate crossing facilities. Offers appropriate crossing facilities and value for money
  • Rejected: Do Medium and Do Maximum: increase junction capacity while providing crossing facilities. Increases time delays and adds cost with more works and service diversions
  • Rejected: Do nothing. Will not solve the current or future problems with crossing and cycling provision

Implications

  • Financial: The £837,521.29 contract is funded from the Capital Programme.
  • Legal: Legal advice was provided by Daniel Howard, Principal Lawyer, Legal Services, on 20 April 2026.
  • Risk: Risk is assessed as low; similar junction improvement projects have been delivered successfully and no significant risks are identified.
  • Equalities: The scheme is intended to address difficulties for vulnerable user groups navigating the existing narrow pedestrian refuges and footways.
  • Other: Rosgal Ltd has signed the Mayor's Employment Charter and is an Accredited Living Wage Employer.

Who and where

  • Pedestrians, including vulnerable users, at the Cleggs Lane / A6 Manchester Road junction
  • Cyclists, who currently face substandard cycle facilities
  • Road users at and around the junction during the 7 month works period
  • The local MP, ward members and residents who raised safety concerns about the junction

Timeline

  • August 2019 to August 2024: Seven reported collisions at the site, all slight severity
  • 02/02/2026: Drawing issued for tender (revision P01) Report P45
  • 20 April 2026: Legal advice provided by Daniel Howard, Principal Lawyer
  • 18/05/2026: Contract start date
  • 04/12/2026: Contract end date

Plain English for the jargon

  • GMRAPS: Greater Manchester Road Activities Permit Scheme, the mandatory road permitting scheme for all districts within Greater Manchester
  • PSR Competitive Process: The procurement route used, as recorded in the decision
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5a

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: · approve the award of Contract forthe Cleggs Lane/ A6 Junction Improvement Scheme as detailed in the table below: Detail required Answers Title/ Description of Contracted Service/Supply/Project Cleggs Lane / A6 Manchester Road Junction Improvement Scheme Procurement Reference numbers (DN and CR number supplied by Procurement) DN807134 / S1906 Name of Successful Contractor Rosgal Ltd Supplier Registration Number (to be supplied by Procurement 3731189 Proclass Classification No. (to be completed by procurement) 391410 Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by Procurement) Non-SME Contract Value (£) £ £837,521.29 Total contract value £ (including extensions) N/A Contract Duration 7 months Contract Start Date 18/05/2026 Contract End Date 04/12/2026 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Nicola Smithies - [phone removed] Lead Service Group Place How the contract was procured? (to be supplied by procurement) PSR Competitive Process Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Bolton Council 2024/28 Highways Framework Contract, Lot 1 Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Employment Charter Yes EC: Committed to sign The Mayor’s Employment Charter N/A EC: Committed to the principles outlined in the Mayor’s Employment charter N/A EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living wage Employer N/A ? The Reasons are : The Cleggs Lane/ A6 Manchester Road is a site of concern due to a high number of recorded collisions and current lack of cycling facilities. The existing crossing facilities comprise narrow pedestrian refuges and footways which creates difficulties for pedestrians, particularly vulnerable user groups to navigate. The existing junction also has substandard cycle facilities. Representation regarding the junction have been received from the local MP, ward members and the public, mostly concerned with safety issues. Between August 2019 – August 2024 there have been seven reported collisions, all of which were of slight severity. Options considered and rejected were : Doing nothing will not solve the current or future problems with crossing/cycling provision. Increasing the capacity of the junction while providing crossing facilities (Do Medium and Do Maximum options) increases time delays and adds cost with more works and service diversions. The current proposal (Do Minimum) provides for appropriate crossing facilities while offering value for money. Assessment of Risk : Low: Similar junction improvement projects have been successfully delivered previously. There are no significant risks associated with the delivery of the project. The source of funding is : See financial comments below. Legal Advice obtained : Supplied by: Daniel Howard, Principal Lawyer, Legal Services Date provided: 20 April 2026 When commissioning contracts for the procurement of goods, services, or the execution of works, the Council must comply with the applicable procurement legislation and ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Cle STOP S

2 MH

08 This drawing is copyright to Salford City Council. It shall not be used without permission for any

A5 purpose. Reproduction is only permitted by prior arrangement. Do not scale from this drawing. All N BU discrepancies to be related back to the originator for verification prior to commencing the works. COMMERCIAL IN CONFIDENCE

BUS BUS ST LP ©Corwcna o gn p hd iyta rb g t2sa h 0 ist2 reO 6drnancS eu ve rA yC0000851257

SAFETY, HEALTH AND STOP OP

BUS ST OP ENVIRONMENTAL INFORMATION Bus Stop Ramps. For bus stop platform details In addition to the hazards/risks normally associated with the types of work refer to Kerbs, Footways and Paved areas drawing detailed on this drawing, note the following 010610-SCC-HKF-XX-DR-CH-0001 SHE001 STAIR WAY 1 SHE002 HIGH VOLTAGE CABLE 11 - 33KV CABLE A6 SP

STOP S SP

Ma LP

nc It is assumed that all works will be carried out by a competent contractor

BU he LP working, where appropriate, to an approved method statement ste General Notes: rR oa TAC SV

d W SHE002 FLAGST ONES 1. All dimensions to be checked before commencement of work on es TARMA C site. t Vie 2. All dimensions in metres unless otherwise stated. FL BUS ST wp 3. All work to be in accordance with the Specification for Highway AG ST OP G ort ON ES 3 works and associated appendices. MH TAC 4. Contractor to propose, and gain approval for suitable traffic / pedestrian management. The Contractors’ attention is drawn to the mandatory road permitting scheme operating for all districts G 1 within Greater Manchester. The Contractor shall comply fully BLOCK GV with the Greater Manchester Road Activities Permit Scheme PAVING GV GV (GMRAPS) requirements to ensure that the impact of the scheme on wider road network can be managed effectively MH TARMA 5. The Contractor shall be responsible for preparing and submitting C FL AG applications for all TTROs required by their Traffic Management ST ON ES G SP SP T

LRE E A L PPA R R SP proposals to Salford City Council Streetworks officer. The cost of submitting the Orders shall be met by the Contractor. This TAC RC A C CCLLEE EPEKKPEEEE A SP includes any other associated third-party costs, such as TfGM

ne TAC traffic signal monitoring.

La GV 6. This drawing is to be read in conjunction with the issued Highways KEE drawings and specification, any discrepancies, errors or omissions

gs K to be brought to the attention of the Designer:

leg · 010610-SCC-HDG-XX-DR-CH-0001 Drainage

2C TAC TAC · 010610-SCC-HDG-XX-DR-CH-0002 Ducting & Ironworks

08 T · 010610-SCC-HLG-XX-DR-CH-0001 Proposed Street Lighting

A5 LP G · 010610-SCC-HSC-XX-DR-CH-0001 Site Clearance · 010610-SCC-HKF-XX-DR-CH-0001 Kerbs and Footways PB LP 2 LP · 010610-SCC-HKF-XX-DR-CH-0001 Kerb Heights T MH FLAGST ONES · 010610-SCC-HMK-XX-DR-CH-0001 Road Markings FL AG ST G TARMA C · 010610-SCC-HPV-XX-DR-CH-0001 Proposed Pavement ON ES BL OC K Construction PA VI NG · 010610-SCC-HPV-XX-DR-CH-0002 Proposed High Friction G 3 Surfacing G SV · 010610-SCC-HSN-XX-DR-CH-0001 Traffic Signs TARMA SV C SV TH T BL LP FH KEY OC GV K PA VI NG Scheme Extents SHE002 T KO N Proposed Alignment

T Proposed Carriageway Surfacing G T

ne TL FH T TAC TAC

La P SV G Proposed High Friction Surfacing

gs SV SHE002 SHE002 TH T

leg 2C TL

SV TAC MH STOP S Proposed Footway Surfacing

08 T SHE002 SV

A5 TL N TAC P BU Proposed Controlled crossing P

BUS TL LP LP TAC G T BUS ST Proposed Uncontrolled crossing STOP OP SV SV BUS ST OP T Vie SV

wp T TP MH On Carriageway Cycle lane S

ort XI TA

LP T 1 TAC P Proposed Hazard Warning Paving SP

BLOCK PAVING P SP T T G TAC Unadopted Highway TARMA S

C LP XI TA

TAC G Rediweld Greenwich Wand Orca 2500mm long x LP G 175mm wide with two 800mm high x 80mm TAC SV GV TAC SV diameter rebound pole cones (wands) installed as T TL P per manufacturers specification SHE001 TARMA C

SV TAC LP TL WO G Vie w po NOTES rt 1 TAC T P 1 NEW BUS PLATFORM. EXISTING SHELTER TO BE UPGRADED. TAC SV FLAGST

Viewport 3 LP TAC G ONES e

1 nu

WO TL ve

TAC G FH eA

P G TARMA tag

C T

T mi

GV Ar 2 08

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
010610-SCC-HGN-XX-DR-CH-0001_D2_P01 (4)Report 836 KB DownloadRead as text
PDF
Cleggs Lane/ A6 Junction Improvement Scheme Approval to award the tender (Nicola Smithies)Report 195 KB Download

At this meeting

Whole meeting
3To approve, as a correct record, the minutes of the meeting held on Monday 27 April 2026On the agenda
5aCleggs Lane/ A6 Junction Improvement Scheme Approval to award the tender (Nicola Smithies)This decision
7Exclusion of the publicOn the agenda

Who was there

5 of 7 attended
BB
Barbara BenthamInvitee, in attendance
PD
Paul DennettCommittee Member, present
AH
Anthony HiltonOfficer, present, as expected, virtual
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerInvitee, in attendance
JM
John Merry CBECommittee Member, present

On this subject at Salford

Search all
  1. Cleggs Lane/ A6 Junction Improvement Scheme Approval to award the tender (Nicola Smithies)This decision
  2. Cleggs Lane/Armitage Avenue and Manchester Road A6 Junction Improvements - S106 Spending ApprovalApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open