Salford City Council
Procurement Board, Monday 13 July 2026 at 2.00pm

Approval to go out to tender/ competition for S2007 – Floating Wetlands Habitats (Andrew Chatterjee/ Opu Anwar)

Approved Committee 1 paper

AI summarySalford City Council approves open tender for floating wetland habitats on the River Irwell at Ordsall, with a £248,000 budget from the Environment Agency and Section 106 funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor S2007 Floating Wetlands Habitats contract
Money£248,000 total available budgetEnvironment Agency grant plus Section 106 match
What happens nextTender to be openly advertisedOn Find a Tender Service and The Chest
Who it affectsOrdsall ward, River IrwellQuays ward, floating wetland on River Irwell

What was decided

Councillor Cusack accepted the Procurement Board recommendation to go out to open tender for S2007 Floating Wetlands Habitats, procured under the Council's Contract Procedure Rules. Report P1

The tender will run on a design and build basis, letting bidders propose their own technical approaches, materials and delivery methods. Report P13, P14

The decision is not a Key Decision and is open to call-in by the Growth and Prosperity Scrutiny Panel until 4.00 p.m. on 20 July 2026. Report P7

Why

The project delivers a key ecological part of the Irwell River Park Connectivity and Movement Strategy, aiming to create wetland habitats on an 8km stretch of the River Irwell. Report P3, P9

Officers judged open tender as the best way to test a specialised market, drive innovation and secure value for money under the Procurement Act 2023. Report P4, P13, P28

Doing nothing was rejected because it would risk losing secured external funding, reduce future funding chances and allow continued ecological decline. Report P19

What happens next

Formal approval of the Section 106 funding must be obtained before the Council commits to a contract with the successful bidder. Report P22

The tender will be openly advertised on the Find a Tender Service and The Chest, with the most advantageous supplier selected. Report P28

If the Ordsall demonstrator succeeds, the Environment Agency may provide further funding in 2027/28 and 2028/29 to extend the scheme to the city centre, Meadows and Anaconda areas. Report P3

The money

  • £248,000 Total available budget for the floating wetlands project Report P21
  • £78,000 Environment Agency Water Environment Improvement Framework (WEIF) grant Report P21, P22
  • approximately £170,000 Section 106 match funding, agreed in principle Report P21
  • £178,000 S106 funding stated in finance officer comments, subject to formal approval Report P22

Options considered

  • Rejected: Not proceeding with the project. Would risk loss of secured external funding, reduce future funding opportunities and allow continued ecological decline Report P19
  • Chosen: Open tender for design and build. Tests a specialised market, encourages innovation and meets Procurement Act 2023 obligations Report P4, P13, P14, P28

Implications

  • Financial: Total budget of £248,000 made up of £78,000 Environment Agency grant and S106 match funding, which still needs formal approval before contract award. Report P21, P22
  • Legal: Procurement must comply with the Procurement Act 2023 and the Council's Contractual Standing Orders; open tender reduces the risk of legal challenge. Report P24, P25, P26
  • Risk: Risk assessed as medium: not proceeding would risk loss of secured external funding and continued ecological decline. Report P19
  • Climate: Climate change team expects new wetland habitats to support biodiversity, absorb pollutants, contribute to carbon capture and improve flood resilience. Report P31, P32
  • Equalities: Equality Impact Assessment recorded as N/A. Report P16, P17
  • Staffing: No HR implications recorded. Report P29

Who and where

  • Residents and visitors to Ordsall Riverside, Quays ward Report P3, P32, P36
  • Biodiversity and aquatic species along the River Irwell Report P9, P31
  • Specialist suppliers of floating wetland systems Report P4, P13, P28
  • Environment Agency as co-funder and potential future funder Report P3, P21

Timeline

  • 13th August 2025: Earlier Part 2 report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development Report P6
  • 20/05/26: Legal advice provided by Daniel Howard
  • 20/05/26: Financial advice provided by Ian Cowburn
  • 21/05/26: Procurement advice provided by Daniel Cunliffe
  • 03/06/2026: Finance contact officer (Ian Cowburn) supplied funding details Report P22
  • July 2026: Part 2 report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development
  • 13 July 2026: Decision published and signed by Councillor Cusack
  • 4.00 p.m. on 20 July 2026: Decision comes into force unless called in
  • 27/28 and 28/29: Potential further Environment Agency funding years if demonstrator scheme succeeds Report P3

Plain English for the jargon

  • WEIF: Water Environment Improvement Framework, the Environment Agency grant programme funding the project
  • Section 106 funding: Developer contributions used by the Council for local infrastructure or environmental projects, here agreed in principle but not yet formally approved
  • LECA: Light Expanded Clay Aggregate, a planting substrate used to fill the floating wetland modules
  • HDPE: High Density Polyethylene, the plastic used in the modular floating island units
  • FTS: Find a Tender Service, the UK public procurement advertising portal
  • The Chest: North West procurement portal used by Salford City Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5d

Resolved

Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the Procurement Board, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: · to go out to tender/ competition for S2007 – [OA1] [AC2] Floating Wetlands Habitats, to be procured in accordance with the Council’s Contract Procedure Rules. The Reasons are : to seek design and construction solutions for floating wetlands through a tender process. Options considered and rejected were: not proceeding with the project however this would not be beneficial to the Irwell River Park project. Assessment of Risk : Medium: Failure to proceed would risk loss of secured external funding and reduce future funding opportunities, as well as continued ecological decline. Legal Advice obtained : Daniel Howard, 20/05/26. Financial Advice obtained : Ian Cowburn, 20/05/26. Procurement Advice obtained: Daniel Cunliffe, 21/05/26. HR Advice obtained: N/A. Climate Change Implications obtained – Climate change team. The following documents have been used to assist the decision process: · Report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development (Part 2) on 13 th August 2025. · Report of the Strategic Director Place to the Lead Member for Planning, Transport and Sustainable Development (Part 2) on 8 th July 2026. Contact Officer: Andrew Chatterjee/ Opu Anwar Contact e-mail: [email protected] · This matter is not subject to consideration by another Lead Member. · The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed: Cllr Cusack Dated: 13 July 2026. Lead Member FOR DEMOCRATIC SERVICES USE ONLY: · This decision was published on 13 July 2026. · *This decision will come in force at 4.00 p.m. on 20 July 2026 unless it is called-in in accordance with the Decision Making Process Rules. class=WordSection2> [OA1] What does this refer to? Does it need to be in? [AC2] its just an internal procurement code
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board recommends S2007 – Floating Wetlands Habitats to be procured in accordance with the Council’s Contract Procedure Rules through open tender.

Executive summary

The purpose of this report is to request approval to go out to tender for the delivery of the abovementioned scheme

The project will deliver a key ecological part of the Irwell River Park Connectivity & Movement Strategy which aims to transform an 8km stretch of the River Irwell into a vibrant, accessible, ecologically rich urban river corridor. It focuses on creating new wetland habitats using floating ecosystems at key locations along the river. The first location, chosen with co-funder Environment Agency (EA), is the Ordsall Riverside where the river is widest and deepest. If this demonstrator scheme proves successful, there is potential for additional funding from the EA in 27/28 and 28/29 to continue the scheme in the city centre, and Meadows & Anaconda areas.

Siting, design, manufacture and installation of floating wetlands is a very specialised therefore it is proposed to go to open tender to test the market to find the best supplier.

BACKGROUND DOCUMENTS:

Report of the Strategic Director of Place to the Lead Member Planning, Transport and Sustainable Development - 13th August 2025

Sample A – going out to tender KEY DECISION: No

DETAILS:

This project seeks to deliver floating wetland habitats along the River Irwell at Ordsall, enhancing biodiversity, creating amenity value/ feature of interest and improving water quality. The scheme involves design, supply and installation of modular floating ecosystems using specialist contractors.

The proposed floating wetlands consist of modular, high-buoyancy floating island units designed to create an approximate 100m (long x 3m wide stretch of riverbank habitat, adaptable to site conditions and urban constraints. The exact size of the habitats will depend on the site conditions. Each island uses interlocking High Density Polyethylene (HDPE) and stainless-steel modules filled with a planting substrate of Light Expanded Clay Aggregate (LECA) mixed with woodchip or compost to support native aquatic vegetation and enhance ecological complexity.

Protective features include wire mesh to prevent grazing by birds and detachable stainless-steel posts, while hydraulic considerations require confirmation of water depth and flood levels to determine anchoring—either weighted wall anchors for low- risk conditions or pile anchors adjusted to fluctuating levels where flood risk is significant. The system is designed for durability, recyclability, adjustable buoyancy, and flexible configuration to suit evolving environmental and spatial requirements.

KEY COUNCIL POLICIES: • Irwell River Park – Connectivity & Movement Strategy: creation of new wetland habitats • Corporate Plan (2024-28): this will contribute to the council’s vision for a "fairer, greener, healthier and more inclusive Salford for all" • Climate Change Strategy • Biodiversity and Green Infrastructure priorities. • Greater Manchester 5-Year Environment Plan 2025-2030

INNOVATE/ BEST VALUE: The procurement of floating wetland habitats will be undertaken through an open tender process to ensure transparency, competition, and alignment with the Council’s obligations under the Procurement Act 2023, thereby securing best value. By inviting a broad range of suppliers to bid, the Council will maximise market engagement and encourage innovative solutions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to go out to tender/ competition for S2007: Floating Wetlands Habitats (Andrew Chatterjee/ Opu Anwar)Report 88 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
PC
Philip CusackChair, present
PD
Paul DennettCommittee Member, apologies due to council business
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, apologies
JC
Jim CammellCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, apologies
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present

On this subject at Salford

Search all
  1. Approval to go out to tender/ competition for S2007 – Floating Wetlands Habitats (Andrew Chatterjee/ Opu Anwar)This decision
  2. Approval to go out to tender for a Management Information System for Regulatory Services, Vehicle Management Services, Waste Management Services and the Customer Contact Centre (Tim Cook)Approved
  3. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  4. Approval to go out to tender/ competition for Ordsall Neighbourhood Scheme (Anene Chiegboka)Approved
  5. Approval to go out to competition for Adult Social Care Business Delivery Partners (Matt Drogan)Approved
  6. Approval to Award the Contract for Internal and External Refurbishment of Height Youth Centre (Tracy Squirrell)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies