Request to extend the contract - Solar PV (Hayley Nixon)

Approved Committee 1 paper

AI summarySalford's City Mayor has approved a £422,000 contract extension with NPS Solar Ltd to add roof-mounted solar panels at up to three more sites, lifting total contract value to £1,267,900.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRoof-mounted solar PV installation at up to three more sites
Money£1,267,900Total contract value including extensions; £422,000 extension
What happens next03/08/2026 to 30/10/2026Extension period; subject to Strategic Review of Property
Who it affectsUp to 3 additional Salford sitesAdds up to 230kWh renewable energy generation

What was decided

The City Mayor approved an extension of the contract for design and installation of roof mounted Solar PV with NPS Solar Ltd by £422,000, increasing total contract value from £845,900 to £1,267,900. Report P8

The extension covers the period from 03/08/2026 to 30/10/2026, on an open book basis, and is subject to confirmation that the three proposed additional sites have a viable future following the Council's Strategic Review of Property, anticipated February 2027. Report P2

The additional sites are Hope Library, Westwood Community Centre, and a third site to be confirmed, with the extension adding up to 230kWh of renewable energy generation to the Council's existing 5MW estate. Report P18, P59

Why

The extension supports Salford's contribution to Greater Manchester's target of becoming a carbon-neutral city region by 2038 and increases local renewable energy generation and supply flexibility. Report P3, P16, P18

NPS Solar is already mobilised and installing across the existing programme; extending avoids additional mobilisation costs, ensures continuity of delivery, and allows the same equipment to be used across all sites for consistent monitoring and maintenance. Report P23, P37

Additional grant funding of £206,523 from the GM Mayoral Renewables Fund and approval of 26/27 Invest to Save budget created the opportunity to extend the programme and install panels at more sites. Report P7, P23

What happens next

Roof and structural surveys will be undertaken to de-risk the additional sites and identify any site constraints before installation proceeds. Report P36

Confirmation that the three proposed additional sites have a viable future is required following the Council's Strategic Review of Property, anticipated February 2027.

The contractor will deliver the additional installations during the extension period 03/08/2026 to 30/10/2026, with £691,856 of Invest to Save funding allocated to the three additional schemes. Report P2, P40

The money

  • £422,000 Contract extension value, increasing total contract from £845,900 to £1,267,900 Report P8
  • £1,267,900 Total contract value including extensions Report P8
  • £845,900 Original contract value before extension Report P8
  • £750,000 Original Invest to Save funding approved in 2025/26 capital programme Report P5
  • £95,900 Original Mayoral Renewal Fund Grant from GMCA Report P5
  • £206,523 Additional funding from GM Mayoral Renewables Fund, fully spent by 31 March 2026 Report P7, P23
  • £302,423 Total grant funding from GM Mayoral Renewables Fund Report P23, P39
  • £965,477 Total Invest to Save funding for the scheme Report P39
  • £1,461,724.15 Total Invest to Save funding allocated to the Zero Carbon Renewable Energy project in 2026-27 Report P40
  • £691,856 Invest to Save funding used to fund the three additional solar PV installations Report P40
  • £430,119.89 Original social value offer from NPS Solar Report P26, P27
  • £151,535.98 Social value progress to date on original contract Report P27
  • £68,170,65 Additional social value from the contract extension Report P30

Options considered

  • Chosen: Extend existing contract with NPS Solar Ltd by £422,000. Contractor already mobilised; avoids additional mobilisation costs, ensures continuity, allows consistent equipment and monitoring across all sites, and minimises delays. Report P23, P37
  • Rejected: Go out to tender for a new contractor. Would mean additional mobilisation costs and delays to installation of additional renewable energy assets and associated budget and carbon savings. Report P23, P37

Implications

  • Financial: The £422,000 extension is funded from approved Invest to Save budget from 25/26 and 26/27, drawn from the £1,461,724.15 allocated to the Zero Carbon Renewable Energy project in 2026-27. Report P9, P40
  • Legal: The variation is permitted under Contractual Standing Orders and Regulation 72 of the Public Contracts Regulations 2015; it is not material and the price increase is within limits. Report P44
  • Legal: Procurement team confirms the extension is in line with Regulation 72 of the Public Contract Regulations 2023 and the Council's governance processes. Report P47
  • Climate: Project supports the GM 5 Year Environment Plan 2025-2030 and Salford's carbon neutral by 2038 target, adding up to 230kWh of renewable energy to the estate and reducing carbon emissions. Report P18, P50, P52
  • Equalities: Equality Impact Assessment: N/A. Report P34
  • Risk: Programme is low risk; roof and structural surveys will de-risk sites by identifying whether they can proceed and highlighting any constraints. A risk register and mitigation measures are in place. Report P35, P36
  • Staffing: HR implications: N/A. Report P48
  • Other: Additional social value of £68,170,65 from the extension includes an apprenticeship, supply chain spend in Salford M50 postcode, volunteering for Salford Foundation, donations to Schools Eco Refill Shops, and use of zero emission vehicles. Report P28, P29, P30

Who and where

  • NPS Solar Ltd (contractor, SME, Private Limited Company, registration 5513604) Report P22
  • Salford Community Leisure buildings and Council estate Report P1, P18
  • All wards of Salford (Walkden South; Kersal and Broughton Park; Higher Irlam and Peel Green; Weaste and Seedley; Boothstown and Ellenbrook; Barton and Winton; Pendleton and Charlestown; Broughton; Swinton and Wardley; Claremont; Worsley and Westwood Park) Report P56
  • Local supply chain in Salford M50 postcode Report P27, P29
  • Salford Foundation (community partner benefiting from staff volunteering) Report P27, P29

Timeline

  • July 2025: Tender documents advertised via GMCA Go Neutral Smart Energy Framework Lot 1 Report P20
  • 13 October 2025: Procurement Board report on approval to award the contract to NPS Solar Ltd Report P11, P21
  • 14/10/2025: Contract start date
  • 31 March 2026: Deadline for spending £206,523 GM Mayoral Renewables Fund grant; funding fully defrayed by this date Report P7
  • 03/08/2026: Extension period start date Report P2
  • 30/10/2026: Extension period end date Report P2
  • February 2027: Anticipated outcome of Council's Strategic Review of Property determining viability of three additional sites
  • 2030: GM target of at least 375MW increased local renewable energy generation Report P50
  • 2038: Greater Manchester carbon-neutral city region target Report P3, P16

Plain English for the jargon

  • Solar PV: Solar Photovoltaic, technology that converts sunlight into electricity using panels
  • SCC: Salford City Council
  • GMCA: Greater Manchester Combined Authority
  • CSO: Contractual Standing Orders, the Council's rules for procuring contracts
  • TOMs: Themes, Outcomes and Measures, the framework used to assess social value
  • Invest to Save: Council funding mechanism where future savings repay the upfront investment
  • PCR 2015: Public Contracts Regulations 2015, the procurement rules applicable to this variation
  • kWh: Kilowatt hour, a unit of energy
  • MW: Megawatt, a unit of power equal to one million watts
  • SME: Small and Medium-sized Enterprise
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5b

Resolved

Salford City Council – Record of Decision I Paul Dennett , City Mayor , in exercise of the powers contained within the City Council Constitution do hereby approve: · an Extension of Contract for Design and Installation of roof mounted Solar PV on estate and Salford Community Leisure buildings 2025/26 Programme (on an ‘open book’ basis and subject to confirmation that the three proposed additional sites have a viable future, as per the outcome of the Council’s Strategic Review of Property, anticipated February 2027) , as detailed in the table below: Detail required Answers Title/Description of Contracted Service/Supply/Project Design and installation of roof mounted Solar PV Procurement Reference Number (DN and CR, supplied by Procurement) DN562301 Name of Successful Contractor NPS Solar Ltd Supplier Registration Number (to be supplied by Lead officer) 5513604 Supplier Identifier Reference (Central Digital Platform) above awards above £30,000 (inc VAT) N/A Proclass Classification No. (to be completed by procurement) 102300 Type of organisation (to be supplied by Lead Officer) Private Limited Company Status of Organisation (to be supplied by Lead Officer) SME Contract Value (£) £422,000 per annum Total Contract Value including extensions (£) £1,267,900 Total project Contract Duration 6 months Contract Start Date 14/10/2025 Contract End Date Optional Extension Period 1 Optional Extension Period 2 Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Paula Connor-Bennett Lead Service Group Place Procurement Legislation PSR Funding Source Combination of Above (please detail below) Ethical Contractor (EC): Mayor’s Employment Charter Yes EC: Committed to sign up to the Mayor’s Employment Charter Yes EC: Committed to the principles outlined in the Mayor’s Employment charter Yes EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living Wage Employer Yes The Reasons are : The purpose of this report is to seek to request an extension to the current contract for the design and installation of roof mounted Solar PV at estate and Salford Community Leisure buildings 2025/26 Programme. There is provision within the current contract to extend the agreement for a further period from ?03/08/2026? to ?30/10/2026?. Salford City Council (SCC) is looking to install roof mounted solar PV at an additional three sites across the city to increase local renewable energy generation and increase the flexibility of local energy supply as part of its contribution towards Greater Manchester’s target of becoming a carbon-neutral city region by 2038. Options considered and rejected were: The only other option that would be available would be to go out to tender however he current contractor is already mobilised and operating across the existing sites. Extending the contract twill avoid additional mobilisation costs and will ensure the continuity of delivery. Assessment of Risk : The programme?has?a risk register in place and mitigation measures. ? The programme is?low risk?as the roof and structural surveys that are to be undertaken will de-risk the sites by?identifying?whether they are able to?proceed?as planned and highlight any site constraints. ?? The current contractor is already mobilised ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Executive summary

The purpose of this report is to seek to request an extension to the current contract for the design and installation of roof mounted Solar PV at estate and Salford Community Leisure buildings 2025/26 Programme.

There is provision within the current contract to extend the agreement for a further period from 03/08/2026 to 30/10/2026

Salford City Council (SCC) is looking to install roof mounted solar PV at an additional three sites across the city to increase local renewable energy generation and increase the flexibility of local energy supply as part of its contribution towards Greater Manchester’s target of becoming a carbon-neutral city region by 2038.

A mini competition exercise was previously undertaken for the procurement of a contractor to undertake structural and roof surveys and the design and install of solar PV on nine sites utilising GMCA’s Go Neutral Smart Energy Framework using Lot 1 – Building Mounted Solar PV. NPS Solar Ltd was appointed.

The original financial provision that was in place to take the solar PV forward consisted of £750,000 Invest to Save, which was already approved in the 2025/26 capital programme, plus £95,900 of Mayoral Renewal Fund Grant funding from the GMCA. Structural and

Sample C – Exception to CSO’S roof surveys were undertaken in order to get firm quotes for the installation of the roof mounted sites and take a decision on which were installed. The final costs of each site took into account the costs associated with each site, available budget and payback period of the Invest to Save funding. The outcome of these discussions informed which sites went to the build stage.

During the original programme, the Council secured an additional £206,523 through the GM Mayoral Renewables Fund. This funding had to be fully spent by 31 March 2026 and was successfully defrayed by that date. The remaining 25/26 Invest To Save budget was carried forward to 26/27.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Request to extend the contract: Solar PV (Hayley Nixon)Report 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
PC
Philip CusackChair, present
PD
Paul DennettCommittee Member, apologies due to council business
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, apologies
JC
Jim CammellCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, absent
AH
Anthony HiltonOfficer, present
CH
Chris HowlClerk, present

On this subject at Salford

Search all
  1. Request to extend the contract - Solar PV (Hayley Nixon)This decision
  2. ADDENDUM REPORT - Request approval to extend the contract for Community Protection/ Refuse Collection software (Place) from 01/04/2026 to 31/03/2028 (Matt Wylie)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies