Procurement Board, Monday 14 September 2026 at 2.00pm

Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan Vince

Approved Committee 1 paper

AI summarySalford awards £40m contract to Seddon Construction to build 144 low-energy affordable homes at Robert Hall St, Ordsall, with the award contingent on funding approval and the council noting high risk if delayed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£39,999,285Contract sum, with total scheme costs of £46,250,141
What happens nextFunding approval needed
Who it affectsOrdsall ward

What was decided

Award the contract for construction of affordable homes at Robert Hall St, Ordsall to Seddon Construction via the Innovation Chain North framework

Confirm the award is subject to approval of funding by Property and Regeneration Briefing and confirmation of external funding packages

Why

Seddon has experience building council affordable homes to high environmental standards, worked with the design team to ensure deliverability and cost savings, and the contract sum reflects high specification and brownfield site abnormal costs Report P2, P21

The contract sum was assessed by the council's cost consultants as value for money, and the ICN framework provides the latest prices, rates and building regulations Report P21, P17

The scheme will deliver 144 low-energy affordable homes in an area dominated by private development, with social value including £30k for community projects via Ordsall Forum and local employment commitments Report P22, P28, P30

What happens next

Property and Regeneration Briefing to approve the funding mix, associated risks and capital expenditure for the scheme Report P41, P43

Contract to commence on 5 October 2026, with completion by 9 July 2030

The money

  • £39,999,285 Total contract sum with Seddon Construction Report P43
  • £46,250,141 Total scheme costs Report P43
  • £16,080,000 Homes England AHP funding Report P45
  • £3,960,000 GMCA Good Growth Fund Report P45
  • £1,576,656 Brownfield Land Release funding Report P45
  • £24,333,970 Capital resource required Report P45
  • £220,747 Right to Buy receipts Report P45
  • £78,768 RDEL funding Report P45
  • £30,000 Budget for community projects allocated through Ordsall Forum Report P30

Options considered

  • Chosen: Award contract to Seddon Construction via Innovation Chain North framework. Seddon's experience with council affordable homes, early contractor involvement provided informed contract sum assessed as value for money by cost consultants, and ICN framework provides current market rates Report P2, P18, P21
  • Rejected: Do not award contract. Not considered; delay would significantly impact housing delivery programme, affect Affordable Housing Delivery for the City, potentially impact funding streams including Brownfield Land Release obligations, and may require redesign for new Future Homes Building Regulations Report P38

Implications

  • Financial: Total scheme costs are £46,250,141; funding mix includes Homes England AHP £16,080,000, GMCA Good Growth Fund £3,960,000, Brownfield Land Release £1,576,656, Right to Buy receipts £220,747, RDEL £78,768, with £24,333,970 capital resource required Report P43, P45
  • Financial: Scheme included in approved 2026/27 Housing Strategy Capital Programme; expenditure beyond 2026/27 included in future capital programme iterations Report P45
  • Risk: Risk rated High: delay to appointment would impact housing delivery programme, affect Affordable Housing Delivery, impact funding streams including Brownfield Land Release obligations, and may require redesign for new Future Homes Building Regulations Report P37, P38
  • Legal: Direct award under Innovation Chain North framework, Lot L1, complies with Public Contract Regulations 2015 and Council's Contractual Standing Orders Report P47, P48
  • Climate: All 144 homes designed as low energy with high thermal efficiency, Mechanical Heat Recovery systems and options for PV Cells; homes meet M4(2) accessible design standards and Nationally Described Space Standards Report P24, P25
  • Other: Social value commitments include £30k for community projects via Ordsall Forum, 160 hours volunteering, local job creation, training, support at local schools, and commitment to local supply chain spend and Build Salford Report P28, P29, P30

Who and where

  • Salford residents in need of affordable housing Report P22
  • Ordsall ward community, including via community project funding through Ordsall Forum Report P30
  • Seddon Construction as contractor Report P1

Timeline

  • 13 October 2025: Procurement Board approved PCSA with Seddon Construction Report P5
  • 5 October 2026: Contract start date
  • 9 July 2030: Contract end date

Plain English for the jargon

  • PCSA: Pre-Construction Services Agreement - contract to perform services before the main building contract
  • ICN: Innovation Chain North - a specialist framework for delivery of affordable housing schemes covering Greater Manchester and surrounding areas
  • AHP: Affordable Homes Programme - Homes England funding stream
  • RDEL: Revenue Deferred Element of Funding
  • M4(2): Building regulation standard for accessible and adaptable dwellings
  • NDSS: Nationally Described Space Standards - minimum space requirements for new dwellings
  • PV Cells: Photovoltaic cells for solar energy generation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5c

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: · approve and award the contract for the construction of affordable homes at Robert Hall St Ordsall, as detailed in the table below, and · subject to the approval of funding by Property and Regeneration Briefing and the confirmation of external funding packages. Answers Title/ Description of Contracted Service/Supply/Project Construction of affordable homes Procurement Reference numbers (DN and CR number supplied by Procurement) CR S1351-02 Name of Successful Contractor Seddon Construction Supplier Registration Number 03578140 Supplier Identifier Reference (Central Digital Platform FTS) for awards above £30,000 (inc VAT) FTS is PRRH-8298-MPBM Proclass Classification No. (to be completed by procurement) [To be completed by Procurement] Type of organisation Private Limited Company Status of Organisation Choose an item. Contract Value (£) £ per annum Total contract value £ (including extensions) £ 39,999,285 total project value Contract Duration 36 months Contract Start Date 05/10/2026 Contract End Date 09/07/2030 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Choose an item Contact Officer (Name & number) Dylan Vince 0161 793 2476 The reasons are: The affordable housing scheme viability and allocation of capital funding is considered in a separate City Mayor approval. The procurement of Seddon construction will see the delivery of much needed affordable housing in Ordsall and the report identifies Seddon as the most appropriate contractor to complete the works following appointment through the Innovation Chain North Framework and independent assessment of costs and value for money. The contract includes a social value offer with emphasis on local community projects and employment. Lead Service Group Place How the contract was procured? (to be supplied by procurement) Direct Award/ Call off Procurement Legislation PA2023 Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Innovation Chain North Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Employment Charter Yes EC: Committed to sign The Mayor’s Employment Charter Choose an item. EC: Committed to the principles outlined in the Mayor’s Employment charter Yes EC: Accredited Living Wage Employer Yes Assessment of Risk: High Should this appointment not proceed or be delayed it will significantly impact and delay the council’s housing delivery programme and impacting overall Affordable Housing Delivery for the City, a key priority. Innovate/ Best Value – identify the relevant corporate priorities specific to Salford: · A good home for all. · Good growth. · Tackling poverty and equality. · Creating places where people want to live. The source of funding and financial advice obtained: Adam Mozley, Senior Accountant, 13.08.2026 The financial comment are subject to approval of a report being presented to Property and Regeneration on 14 September 2026. That report seeks approval of the funding mix, associated risks and the capital expenditure required for the scheme. Therefore, any decision to award the contract should be regarded as contingent upon those approvals being secured. The report is requesting contract ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Executive summary

The purpose of this report is to seek approval for the award of the above mentioned contract. Seddon Construction has been procured via the Innovation Chain North framework to progress the scheme and were appointed under a PCSA to produce detailed costing and preparation for the main build contract. A phased delivery approach has been agreed, and the award of contract will deliver 144 affordable homes on site A2.

Seddon have successfully constructed a number of council affordable housing schemes and have experience of building homes to the councils high environmental standards. Seddon have worked with the design team to ensure construction deliverability and cost savings were built into the design process. This provided a fully informed contract sum. The contract sum reflects the high specification of the low energy homes, high abnormal costs associated with this and the brownfield nature of the site and has been assessed by the councils cost consultants as value for money.

The scheme viability and allocation of capital funding is considered in a separate City Mayor decision in his Property & Regeneration briefing to enable the award of contract.

BACKGROUND DOCUMENTS:

Procurement Board approval to enter PCSA with Seddon Construction 13th October 2025.

award of contract KEY DECISION:

Yes

DETAILS:

Background

Robert Hall Street and West Park Street (A1 & A2) have been identified and agreed as the next priority delivery sites under the council’s affordable housing delivery programme. The programme responds to the shortage of affordable housing in the city and this scheme has been designed to respond to local housing need. Planning consent was approved in 2024 for the development of 274 new homes, including 112 affordable rented homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan VinceReport 122 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 15 attended
PC
Philip CusackChair, present
PD
Paul DennettCommittee Member, apologies due to council business
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, apologies
BB
Barbara BenthamCommittee Member, apologies
JC
Jim CammellCommittee Member, apologies
HR
Hannah Robinson-SmithCommittee Member, absent
CH
Chris HowlSecretary, present
SR
Samuel RussellCouncil Staff, apologies
PH
Paul HutchingsCouncil Staff, present
CD
Cunliffe, DanielCouncil Staff, present, as expected, virtual

All 15 on the meeting page

On this subject at Salford

Search all
  1. Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan VinceThis decision
  2. Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Approved
  3. Approval to Award the Contract for the continued use of the Line of Business System for Planning, Building Control and Local Land and Property Gazetteer (Anthony Stephenson)Approved
  4. Approval to Award the Contract for Statutory Homeless Supported Temporary Accommodation (Jane Barlow)Approved
  5. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  6. Approval to Award the Contract for consultancy fees for development from RIBA 3 up to RIBA 4, for the Pendleton Wellbeing Hub (Tracy Squirrell/ Adam Vandan)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open