Item69
Resolved
RESOLVED: That (1) the actions of the Strategic Director for Regeneration and Environmental Services in accepting the lowest quotations for the provision of temporary accommodation at Thomas Gray Primary School at a total cost of £189,312.78 be endorsed; (2) approval be given to the waiving of the relevant procedure rules requiring a formal contract and the Technical Services Department be authorised to place individual orders for the supply, delivery, erection and removal of the temporary accommodation (£102,362.78) and for the estimated 47 week hire cost (£86,950); and (3) it be noted that the Chair of the Scrutiny and Review Committee (Performance and Corporate Services) has given his consent, under Rule 17 of the Scrutiny Procedure Rules, for the resolution not to be subject to call-in on the basis that it is necessary to undertake the works as soon as possible, to ensure that the school can accept its full quota of pupils in September 2008.