Resolved
RESOLVED: That (1) the success of Lydiate Parish Council in attracting Big Lottery grant for the construction of the Lydiate Village Centre be noted; (2) approval be given to Lydiate Parish Council's request for Sefton Council to manage the construction of the Village Centre, with Capita Symonds acting as Project Manager, and undertaking the necessary tendering process for the appointment and management of a contractor, subject to Lydiate Parish Council agreeing to reimburse all external costs, e.g. management costs charged by Capita Symonds; (3) approval be given to the Parish Council's request for Sefton officers from relevant Departments to participate in the Lydiate Village Centre Steering Group to support the successful delivery of the project; (4) a legal agreement be developed to facilitate the issues in (2) and (3) above; and (5) regular progress reports on the project be submitted.