Resolved
RESOLVED: That (1) the allocation of £397,916 in the Children’s Services Capital Programme for the scheme at Valewood Primary School, as detailed in the report, be approved and funding be provided from the Sure Start Children’s Centre funding allocation (£272,916) and the Extended Schools funding Provision (£125,000); (2) subject to checking and to the total scheme cost not exceeding the Capital Programme Budget Provision, acceptance of the lowest tender received from Melwood Construction from Huyton in the sum of £260,713 be approved; and (3) subject to (1) and (2) above the Legal Director be requested to enter into a formal contract with the successful tenderer.
Word for word from the decision Sefton published for this meeting.