St Philips CE Primary School, Litherland - Proposed Extensions and Alterations

Approved Executive 1 paper

Cabinet approved this item on Wednesday 25 November 2009. Below is the council's own wording, with the papers it was decided on.

Item211

Resolved

That (1) approval be given to the allocation of £228,939.30 in the Children's Services Capital programme for this scheme, funded entirely from the Primary Capital budget; (2) subject to audit approval of the contractor's latest financial statement of accounts the lowest tender submitted by Lyjon Co. Ltd. of Ellesmere Port and adjusted by the agreed Addendum to the sum of £177,921 be accepted; and (3) the Legal Director be requested to enter into a formal contract with the successful tenderer.
Word for word from the decision Sefton published for this meeting. Source: modgov.sefton.gov.uk

Follow this further

Built from Sefton's papers

What the report saysPro

Report to Cabinet, 5 pages

REPORT TO: Cabinet th DATE: 25 November 2009

SUBJECT: Proposed Extensions and Alterations St Philips CE Primary School, Litherland

WARDS AFFECTED: Litherland and Ford

REPORT OF: Alan Moore Strategic Director for Regeneration and Environmental Services

CONTACT OFFICER: David Kay Architecture and Buildings manager Tel No. 0151 934 4527

EXEMPT/ No CONFIDENTIAL:

PURPOSE/SUMMARY:

This report is to advise Members of tenders received in respect of the proposals to provide extensions and alterations at St Philips CE Primary School, Litherland

REASON WHY DECISION REQUIRED: To enable acceptance of tenders and to thereby allow the timetable for implementation and expenditure to be met.

RECOMMENDATION(S):

It is recommended that:

(i) Cabinet approves the allocation of £228,939.30 in the Children’s Services Capital programme for this scheme, funded entirely from the Primary Capital budget.

(ii) Subject to (i) above and audit approval of the contractor’s latest financial statement of accounts Cabinet approves acceptance of the lowest tender received, adjusted by the agreed Addendum to £177,921.00

(iii) Subject to (i) and ii) above the Legal Director be requested to enter into a formal contract with the successful tenderer.

KEY DECISION: Yes

FORWARD PLAN: Yes

IMPLEMENTATION DATE: Immediately following expiry of the call in period ALTERNATIVE OPTIONS:

All alternative options have been considered and have been discounted.

IMPLICATIONS:

Budget/Policy Framework: The Primary Capital Strategy for Change funding allocation for 2009/10 of £3,618,029 is included in the Children’s Services Capital Programme.

Funding is included within the total allocation to address the proposals for St Philips C of E Primary School, Litherland. th Financial Tenders for the works were received on 30 September 2009. Details of the tenders received are outlined within paragraph 1.2.

The total scheme cost can be met from within the total funding available and the lowest tender received can therefore be considered for acceptance.

2009/ 2010/ 2011/ 2012/ 2010 2011 2012 2013 CAPITAL EXPENDITURE £ £ £ £ Gross Increase in Capital Expenditure

Funded by:

Sefton Capital Resources Specific Capital Resources

REVENUE IMPLICATIONS Gross Increase in Revenue Expenditure Funded by:

Sefton funded Resources

Funded from External Resources

Does the External Funding have an expiry N/A date? Y/N

How will the service be funded post expiry? N/A Legal: Not appropriate

Risk Assessment: Not appropriate

Asset Management: Not Applicable

CONSULTATION UNDERTAKEN / VIEWS

The Children’s Services Department have been consulted and any comments have been taken into account in preparing this report.

FD 219 - The Finance and Information Services Director has been consulted and has no comments on this report.

CORPORATE OBJECTIVE MONITORING:

Corporate Positive Neutral Negative Objective Impact Impact Impact

1 Creating a Learning Community √ 2 Creating Safe Communities √ 3 Jobs and Prosperity √ 4 Improving Health and Well-Being √ 5 Environmental Sustainability √ 6 Creating Inclusive Communities √ 7 Improving the Quality of Council Services and √ Strengthening local Democracy 8 Children and Young People √

LIST OF BACKGROUND PAPERS RELIED UPON IN THE PREPARATION OF THIS REPORT

Children’s Services Capital Programme 1.0 BACKGROUND

1.1The Primary Capital Strategy for Change funding allocation for 2009/10 of £3,618,029 is included in the Children’s Services Capital Programme.

1.2Funding is included within the total allocation to address the proposals for St Philips C of E Primary School, Litherland.

1.3The proposals at St Philips include for an extension to the existing building which, together with internal refurbishment works, will provide a new meeting room and improved office, storage and toilet facilities. The existing hall will benefit from roof light installation providing better natural illumination.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
St Philips CE Primary School, Litherland: Proposed Extensions and AlterationsReport 5 pages DownloadRead as text

At this meeting

Whole meeting
200MinutesDecided 202Safer and Stronger Communities Partnership Capital AllocationApproved 203Revenue Budget Monitoring 2009/10Noted 204Local Land ChargesNoted 205Primary Capital Programme - Additional SchemesApproved 206Building Schools for the Future - Outcome of Readiness to Deliver Re-SubmissionNoted 207Building Schools for the Future - Proposed Delegation of Decision Making Powers to The Project BoardNoted 208Building Schools for the Future - Appointment of Project Director and Project ManagerApproved 209The Development of Low Carbon Economy in Response to Climate ChangeDecided 210Climate Change and Inland Flooding in SeftonNoted
211St Philips CE Primary School, Litherland - Proposed Extensions and AlterationsThis decision
212Christchurch CE Primary School, Bootle - Proposed Extensions and AlterationsApproved 213Governance Review – Area ManagementNoted 214Annual Monitoring Report 2009Approved 215Core Strategy - Green Space and Recreation Study (PPG17 Study) and Playing Pitch StrategyApproved 216Sefton Business Village Partnership ActivitiesNoted 217Southport Park and Ride Services - Temporary Closure of Kew Park and Ride SiteDecided 218Merseyside Landlord Accreditation SchemeApproved 219Exclusion of Press and PublicDecided 220Transformation Programme Update - Strategic Budget ReviewPrivate 221Housing Market Renewal Programme - Housing Development Opportunity - Klondyke NeighbourhoodPrivate 222Commercial Waste Service ChargesPrivate 223112 Monfa Road, Klondyke - Repayment of Home Repair Assistance GrantsPrivate

More from Sefton Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Previous MeetingDecision Made: That the Minutes of the meeting held on 23 July 2026 be confirmed as a correct record. Decided Open
3 Sep 2026 Review of Adult Social Care Charging PolicyThe recommendations in the report had been developed following a review of Adult Social Care charging arrangements, e... Approved Open
3 Sep 2026 Approval of Legal Documentation for Academy Conversions – Voluntary ConversionsThe Archdiocese of Liverpool had determined that all Catholic schools in Sefton would become part of the Pope Francis... Agreed Open
3 Sep 2026 Procurement of Supported Lodgings Accommodation for Young People Aged 16+The proposed procurement would secure a compliant, regulated and more financially sustainable Supported Lodgings arra... Refused Open
3 Sep 2026 Fleet Replacement Street CleansingThe proposal to purchase a new fleet of 13 Small Mechanical Sweepers for the Street Cleansing Service would provide a... Refused Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies