That (1) approval be given to the allocation of £228,939.30 in the Children's Services Capital programme for this scheme, funded entirely from the Primary Capital budget; (2) subject to audit approval of the contractor's latest financial statement of accounts the lowest tender submitted by Lyjon Co. Ltd. of Ellesmere Port and adjusted by the agreed Addendum to the sum of £177,921 be accepted; and (3) the Legal Director be requested to enter into a formal contract with the successful tenderer.
Word for word from the decision Sefton published for this meeting.Source: modgov.sefton.gov.uk
SUBJECT: Proposed Extensions and Alterations St Philips CE Primary School, Litherland
WARDS AFFECTED: Litherland and Ford
REPORT OF: Alan Moore Strategic Director for Regeneration and Environmental Services
CONTACT OFFICER: David Kay Architecture and Buildings manager Tel No. 0151 934 4527
EXEMPT/ No CONFIDENTIAL:
PURPOSE/SUMMARY:
This report is to advise Members of tenders received in respect of the proposals to provide extensions and alterations at St Philips CE Primary School, Litherland
REASON WHY DECISION REQUIRED: To enable acceptance of tenders and to thereby allow the timetable for implementation and expenditure to be met.
RECOMMENDATION(S):
It is recommended that:
(i) Cabinet approves the allocation of £228,939.30 in the Children’s Services Capital programme for this scheme, funded entirely from the Primary Capital budget.
(ii) Subject to (i) above and audit approval of the contractor’s latest financial statement of accounts Cabinet approves acceptance of the lowest tender received, adjusted by the agreed Addendum to £177,921.00
(iii) Subject to (i) and ii) above the Legal Director be requested to enter into a formal contract with the successful tenderer.
KEY DECISION: Yes
FORWARD PLAN: Yes
IMPLEMENTATION DATE: Immediately following expiry of the call in period ALTERNATIVE OPTIONS:
All alternative options have been considered and have been discounted.
IMPLICATIONS:
Budget/Policy Framework: The Primary Capital Strategy for Change funding allocation for 2009/10 of £3,618,029 is included in the Children’s Services Capital Programme.
Funding is included within the total allocation to address the proposals for St Philips C of E Primary School, Litherland. th Financial Tenders for the works were received on 30 September 2009. Details of the tenders received are outlined within paragraph 1.2.
The total scheme cost can be met from within the total funding available and the lowest tender received can therefore be considered for acceptance.
2009/ 2010/ 2011/ 2012/ 2010 2011 2012 2013 CAPITAL EXPENDITURE £ £ £ £ Gross Increase in Capital Expenditure
Funded by:
Sefton Capital Resources Specific Capital Resources
REVENUE IMPLICATIONS Gross Increase in Revenue Expenditure Funded by:
Sefton funded Resources
Funded from External Resources
Does the External Funding have an expiry N/A date? Y/N
How will the service be funded post expiry? N/A Legal: Not appropriate
Risk Assessment: Not appropriate
Asset Management: Not Applicable
CONSULTATION UNDERTAKEN / VIEWS
The Children’s Services Department have been consulted and any comments have been taken into account in preparing this report.
FD 219 - The Finance and Information Services Director has been consulted and has no comments on this report.
1 Creating a Learning Community √ 2 Creating Safe Communities √ 3 Jobs and Prosperity √ 4 Improving Health and Well-Being √ 5 Environmental Sustainability √ 6 Creating Inclusive Communities √ 7 Improving the Quality of Council Services and √ Strengthening local Democracy 8 Children and Young People √
LIST OF BACKGROUND PAPERS RELIED UPON IN THE PREPARATION OF THIS REPORT
Children’s Services Capital Programme 1.0 BACKGROUND
1.1The Primary Capital Strategy for Change funding allocation for 2009/10 of £3,618,029 is included in the Children’s Services Capital Programme.
1.2Funding is included within the total allocation to address the proposals for St Philips C of E Primary School, Litherland.
1.3The proposals at St Philips include for an extension to the existing building which, together with internal refurbishment works, will provide a new meeting room and improved office, storage and toilet facilities. The existing hall will benefit from roof light installation providing better natural illumination.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Fleet Replacement Street CleansingThe proposal to purchase a new fleet of 13 Small Mechanical Sweepers for the Street Cleansing Service would provide a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.