Item268
Resolved
RESOLVED: That (1) the progress made on the renewal of the highway and drainage maintenance contracts be noted; (2) approval be given to the extension of the contracts referred to within the report for a period not exceeding six months, to provide continuity for maintenance works until the new contractual arrangements are in place; and (3) approval be given to the waiving of Contract Procedure Rule No. 3 with regard to Invitation to Tender to allow the extension of the contracts.
Word for word from the decision Sefton published for this meeting.
Source: modgov.sefton.gov.uk