CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Sefton Metropolitan Borough Council
Cabinet, Thursday 8 December 2011 at 10.00am

Capital Programme Update

Noted Executive 1 paper

Cabinet noted this item on Thursday 8 December 2011. Below is the council's own wording, with the papers it was decided on.

Item68

Resolved

RESOLVED: That (1) the progress made in relation to the delivery of committed capital schemes and particularly the potential for under- and over-spends related to those schemes, be noted; (2) a Cabinet Sub-Committee comprising of Councillors Booth, Fairclough, Moncur, Parry, Porter and Robertson be requested to consider which of the uncommitted capital schemes identified in the report should be approved for continuation or abandonment within the Capital Programme and submit its recommendations to the Cabinet and Council; (3) any underspends achieved within the committed Capital Programme, together with any approved funding associated with the abandonment of any uncommitted schemes referred to in Resolution 2 above, be in the first instance allocated to off-set any net overspends currently identified within the Capital Programme; (4) for any uncommitted scheme that the Council agree to continue within the Capital Programme as referred to in Resolution 2 above, the appropriate Officers be requested to re-evaluate the running costs and funding sources and report the findings back to the Cabinet before a final decision is made to progress any such scheme; (5) the Council be requested to give approval to the inclusion of the following ‘invest to save’ capital schemes in the Capital Programme 2012/13: · Convert traffic bollards to LED fittings - £109k · Convert traffic signs to LED fittings - £140k; · Adaptations to Foster Carers’ Residencies - Pilot Scheme - £200k; and (6) approval be given to the submission of a bid to the Heritage Lottery Fund for a contribution of £4.079m toward the cost of Phase II of the regeneration of Kings Gardens, Southport.
Word for word from the decision Sefton published for this meeting. Source: modgov.sefton.gov.uk

Follow this further

Built from Sefton's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Review reportReport Copy on its way

At this meeting

Whole meeting

Who was there

8 of 26 attended
PD
Cllr Peter DowdChair, present, as expected
MB
Cllr Mike BoothMember, present, as expected
IB
Cllr Iain Brodie - BrowneMember, apologies
JF
Cllr John FaircloughMember, present, as expected
IM
Cllr Ian MaherMember, apologies
IM
Cllr Ian MoncurMember, present, as expected
MP
Cllr Mrs Paula ParryMember, present, as expected
BP
Cllr Brenda PorterMember, present, as expected
TR
Cllr Tony RobertsonMember, present, as expected
SS
Cllr Simon ShawMember, present, as expected
MC
Margaret CarneyOfficer, expected
BM
Bill MilburnOfficer, expected

All 26 on the meeting page

On this subject at Sefton

Search all
  1. Capital Programme UpdateThis decision
  2. High Needs Capital Programme 2023 - 2024Refused
  3. Bootle Strand Re-purposing Programme – Memorandum of Understanding with the Department for Levelling Up, Housing and Communities for Capital Levelling Up FundingDecided
  4. Capital Programme and Capital Allocations 2012/13Approved
  5. Capital Programme and Capital Allocations 2012/13Noted
  6. Capital Programme 2011/12 and Capital Allocations 2012/13Approved

More from Sefton Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Previous MeetingDecision Made: That the Minutes of the meeting held on 23 July 2026 be confirmed as a correct record. Decided Open
3 Sep 2026 Review of Adult Social Care Charging PolicyThe recommendations in the report had been developed following a review of Adult Social Care charging arrangements, e... Approved Open
3 Sep 2026 Approval of Legal Documentation for Academy Conversions – Voluntary ConversionsThe Archdiocese of Liverpool had determined that all Catholic schools in Sefton would become part of the Pope Francis... Agreed Open
3 Sep 2026 Procurement of Supported Lodgings Accommodation for Young People Aged 16+The proposed procurement would secure a compliant, regulated and more financially sustainable Supported Lodgings arra... Refused Open
3 Sep 2026 Fleet Replacement Street CleansingThe proposal to purchase a new fleet of 13 Small Mechanical Sweepers for the Street Cleansing Service would provide a... Refused Open