Without the provision of a Transport Technical Services Support supplier, there would be insufficient resource to deliver the schemes, initiatives and policy development within the Transport Capital Programme. This would impact on the funding the Council was likely to secure in the future. Alternative Options Considered and Rejected: The provision of all the specialist skills and capabilities through an in-house team would require substantial additional recruitment which was not practicable within current budget constraints and recruitment challenges. Support for individual schemes could be procured individually and independently through separate procurement processes. This had been rejected because it would require officer time and resources for each procurement. In some situations, the timescales imposed for submitting proposals and funding bids meant that a stand-alone procurement process was either not feasible or would substantially detract from the time available for completing the submission. This approach would also mean that there was much less potential to develop strong working relationships with an individual service provider and for them to develop local knowledge.
Word for word from the decision Sefton published for this meeting.Source: modgov.sefton.gov.uk
To seek Cabinet approval to invite tenders through the appropriate procurement route for the provision of transport technical support services to assist in the preparation of business cases, funding bids and the development and management of transport investment projects.
Recommendation(s):
That Cabinet:
(1) Approves the tender process to procure the provision of Transport Technical Support Services, to be published on The Chest using an Open Tender process, as outlined in the report.
(2) Authorises the contract period of 4 years from 1 January 2026 to 31st December 2029 with an option to extend on a year-by-year basis to 31 December 2032 subject to performance.
(3) Gives delegated authority to the Head of Highways and Public Protection to award the Contract resulting from the procurement and any extensions, subject to consultation with Cabinet Member Housing and Highways. 1. The Rationale and Evidence for the Recommendations
1.1The Transportation Capital Programme (TCP) identifies a significant range of projects and initiatives utilising funding from various sources provided by the Liverpool City Region Combined Authority (LCRCA). Whilst funding contributions have been received from the Active Travel and Levelling Up/Town Funds, the majority of the funding is derived from the City Region Sustainable Transport Settlement (CRSTS). This is the 5-year programme of capital transport investment covering the period from 2022 to 2027. This programme has included greater annual levels of investment than prior to the settlement period. Initial indications from the Department for Transport (DfT) are that the settlement for the next settlement period (CRSTS2) are likely to be higher, although the settlement figure is unlikely to be confirmed until the summer 2025.
1.2The TCP includes some major schemes including the Maritime Corridor, Southport Eastern Access, Les Transformation de Southport and Active Travel investment on the A59. They are intended to support the Council’s Growth Programme, promote Active Travel and highway safety. In addition the programme supports the development and delivery of smaller public realm and safety schemes, school neighbourhood development work, the development of a Local Cycling and Walking Infrastructure plan, Carbon Assessment Work and EV infrastructure roll out. Forward Planning work to shape the schemes likely to form part of the CRSTS2 are also in development. The schemes and initiatives are all at various stages of development, but all will require detailed appraisal, development, design and supervision if they are to be funded and delivered.
1.3The Council does not currently have the capacity, and in some areas of specialist work, the capability, to undertake all the elements of work involved in developing and delivering this programme of strategic transport investment and technical support. It is clear that with a significant number of projects, all necessitating development and delivery within both the current programme and the next CRSTS2 programme, there is significant pressure on staff within the Strategic Transport Planning and Investment and Highway Design teams. The pressure on these teams in likely to be exacerbated by an anticipated increase in private development through the planning system following changes to the National Planning Policy Framework 2024. The Design Team are responsible for the technical review process to support the Highways Development Control Teams as well as delivering capital schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Fleet Replacement Street CleansingThe proposal to purchase a new fleet of 13 Small Mechanical Sweepers for the Street Cleansing Service would provide a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.