Sevenoaks Joint Transportation Board noted this item on Thursday 19 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
To: Sevenoaks Joint Transportation Board
By: Tim Read, Head of Transportation
Date: 19th June 2014
Subject: Member Highway Fund 2013/14
Classification: Information only or decision
Member Highway Fund programme update for Sevenoaks District.
The following list of schemes comprise of those which are outstanding from the previous financial year and new schemes for the current financial year which have been approved, programmed or complete. This information is up to date as of the 3 June 2014.
More detail on the schemes below can be found online on the Kent Member Highway Fund database.
Roger Gough – Darent Valley
Scheme Reference Cost Status Horton Kirby – Vehicle Activate Sign 90100429 3500 Handed Over for 12/13 Delivery Goldsel Rd/Green Court Rd, 13-MHF-SE-19 3390 Handed Over for Crockenhill – wooden fencing and Delivery lining works Swanley Village Gateways – 13-MHF-SE-32 4919 Design Complete, total Improvements to signing and lining cost of the scheme is on approach to the village £7482, requires an addition contribution of £2563 from 2014/2015 CMG Shoreham Village Gateways - 13-MHF-SE-32 4765 Design complete, Improvements to signing and lining consultation the Parish on approach to the village is on-going Badgers Mount Village Gateways – 13-MHF-SE-41 776 Design Complete, Provision of three village gates on all consultation with local approaches to the village residents is on-going, requires additional funds to bring this scheme to completion Margaret Crabtree – Sevenoaks Central Scheme Reference Cost Status Wickenden Road – Dropped Kerbs 13-MHF-SE-18 875 Complete Buckhurst Lane, Sevenoaks – 13-MHF-SE-12 1237 Handed Over for Dropped kerbs Delivery Brittains Lane. Sevenoaks – 13-MHF-SE-52 5488 Design on-going, may Signing and lining improvements require additional funds within the vicinity of the school from 2014/2015 CMG (towards its junction with Oak Lane) allocation Bayham Road, Sevenoaks – School 13-MHF-SE-38 1660 Consultation on-going Keep Clear Markings to the rear of St to be complete by 16 John’s Primary School June 2014
Nick Chard – Sevenoaks East
Scheme Reference Cost Status High Street Seal – Highway Mirror 13-MHF-SE-9 1000 Complete Childsbridge Road, Seal – Footway, 13-MHF-SE-23 6650 Programmed for signing and lining works Delivery late July 2014 Shoreham Road, Otford – 13-MHF-SE-37 £8000 Vehicle activate sign – Installation of a vehicle activated sign handed over delivery, and other signing and lining Additional signing and improvements. This scheme is lining improvements – inclusive of a £3000 contribution from currently awaiting The Otford Society transfer of funds to KCC from Otford Society
David Brazier – Sevenoaks North East
Scheme Reference Cost Status A20 London Road, West 13-MHF-SE-13 380 Complete Kingsdown – Bollards Church Road, New Ash Green – 13-MHF-SE-3 1700 Complete Signing and Lining Oak Farm Lane, Fairseat – 20mph 13-MHF-SE-6 3350 Complete Speed Limit Milestone Acadmey, New Ash 13-MHF-SE-42 10520 Design on-going and in Green - alterations to existing car conjunction with the parking arrangements Academy
Clive Pearman – Sevenoaks South
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Member Highway Fund 2013/14Report | 43 KB | DownloadRead as text |
Follow Sevenoaks Joint Transportation Board at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Mar 2026 | MinutesThat the minutes of the meeting held 14 October 2025 be approved and signed by the Chairman as a correct record. | Approved | Open |
| 17 Mar 2026 | Petition - Crossing at Bessels GreenThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... | Decided | Open |
| 17 Mar 2026 | Petition - Commuter Parking, Cherry AvenueThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... | Decided | Open |
| 17 Mar 2026 | Sevenoaks 20mph Zone - 1 Year UpdateThat the report be noted. | Noted | Open |
| 17 Mar 2026 | Active Travel UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.