To: Sevenoaks Joint Transportation Board
By: KCC Highways and Transportation
Date: 19th June 2014
Subject: Highway Works Programme 2013/14
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2014
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2014
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage – see Appendix B
Traffic Signals – see Appendix C
Conclusion
1. This report is for Members information.
Contact Officers:
The following contact officers can be contacted on 03000 41 81 81
Carol Valentine Highway Manager (West) Julian Cook Sevenoaks District Manager Sue Kinsella Street Lighting Manager Neil Tree Carriageway Surface Treatment Russell Boorman Resurfacing Manager Mar Gillett Major Projects Planning Manager Wendy Bousted Footway Improvement Team Leader Katie Lewis Drainage Manager Toby Butler Intelligent Transport Systems Manager Tony Ambrose Structures Manager Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Surface Treatments - Contact Officer Neil Tree
Micro Asphalt Schemes Road Name Parish Extent of Works Current Status
From A225 Dartford Road St. Botolph's Road Sevenoaks Road to A225 Dartford Road Completed (Service Road) Road From its junction with Clarkes Birchin Cross Road Shoreham Green Road to its junction with Completed Romney Street From its junction with Chelsfield Lane Shoreham Shacklands Road to its Completed junction with Shoreham Lane From its junction with B2026 Spout Lane Westerham Completed Main Road to Coakham Farm From stream o/s Little Browns Honeypot Lane Edenbridge Farm to east side of double Completed bends From its junction with Cow Buckhurst Lane Cowden Lane to its junction with Completed Cowden Pound Road From its junction with B2026 Station Road Cowden Hartfield Road to its junction Completed with Cow Lane
Surface Dressing Schemes – Contact Officer [name removed] Name Parish Extent of Works Current Status
From the change of surface Works programmed to Church Road Ash-Cum-Ridley south of Manor jct to its start Spring/Summer junction with Ash Road 2014
From North of Scudders Hill Works programmed to Valley Road Fawkham junction to its junction with start Spring/Summer Sun Hill 2014
From its junction with St. Works programmed to Tonbridge Road Sevenoaks Julians Road to its junction start Spring/Summer with Weald Road 2014
From the High Friction Works programmed to Surfacing at Sundridge start Spring/Summer Main Road Sundridge Crossroads to the dual 2014 carriageway From Tates Orchard to its Works programmed to Ash Road Hartley junction with Chapel Wood start Spring/Summer Road 2014
From its junction witth Works programmed to Moorden Lane Leigh Penshurst Road to its junction start Spring/Summer with B2027 Tonbridge Road 2014
From its junction with High Works programmed to Heaverham Road Kemsing Street to its junction with St start Spring/Summer Clere 2014
From its junction with London Works programmed to Watercroft Road Halstead Road to its junction with start Spring/Summer Station Road 2014
From its junction with Oak Works programmed to London Road Shoreham Tree Farm to its junction with start Spring/Summer Polhill 2014
From its junction with Works programmed to Stonehouse Lane Halstead Sevenoaks Road to Halstead start Spring/Summer Place School 2014
From Halstead Place School Works programmed to Church Road Halstead to its junction with Shoreham start Spring/Summer Road 2014
From its junction with Works programmed to London Road West Kingsdown Hazelden Close to its junction start Spring/Summer with Stansted Lane 2014
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Works Programme ReportReport | 60 KB | DownloadRead as text |
Follow Sevenoaks Joint Transportation Board at Sevenoaks and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Mar 2026 | MinutesThat the minutes of the meeting held 14 October 2025 be approved and signed by the Chairman as a correct record. | Approved | Open |
| 17 Mar 2026 | Petition - Crossing at Bessels GreenThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... | Decided | Open |
| 17 Mar 2026 | Petition - Commuter Parking, Cherry AvenueThat the concerns raised by the petition be evaluated by Officers and a report brought back to a future meeting of th... | Decided | Open |
| 17 Mar 2026 | Sevenoaks 20mph Zone - 1 Year UpdateThat the report be noted. | Noted | Open |
| 17 Mar 2026 | Active Travel UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.