Resolved
View the decision text for item 10.
Transport, Regeneration and Climate Policy Committee decided this item on Wednesday 8 February 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 10.
Agenda Item 11
Officer Decision Report Author/Lead Officer of Report: David Whitley, Transport Schemes Manager
Tel: 0114 205 3804
Report to: Transport, Regeneration and Climate Policy Committee
Date of Decision: 8h February 2023
Subject: East Bank Road Active Travel Project: Approval to proceed through design and delivery.
Has an Equality Impact Assessment (EIA) been undertaken? Yes No
If YES, what EIA reference number has it been given? (1278)
Has appropriate consultation taken place? Yes No
Has a Climate Impact Assessment (CIA) been undertaken? Yes No
Does the report contain confidential or exempt information? Yes No
If YES, give details as to whether the exemption applies to the full report / part of the report and/or appendices and complete below:-
“The (report/appendix) is not for publication because it contains exempt information under Paragraph (insert relevant paragraph number) of Schedule 12A of the Local Government Act 1972 (as amended).”
Purpose of Report: The purpose of this report is to provide the context for a recommendation to progress with the development of the East Bank Road Active Travel Project, subject to agreement from the DfT to a revised project end date. The scheme has an estimated cost of £1.89 million wholly funded by the Department for Transport (DfT), from Tranche 3 of the Active Travel Fund (ATF) via a capital grant. The funding will be used to design and deliver the East Bank Road Active Travel Project, including community consultation.
The East Bank Road Active Travel Project is part of the South Yorkshire Mayoral Combined Authority (SYMCA) Active Travel Implementation Plan (ATIP) and will become a critical extension to the communities just south of the City Centre, connecting with and beyond the Sheaf Valley Cycle Route, to the Grey to Green project, wider Transforming Cities Fund programme, and the City’s transformational Connecting Sheffield Programme.
Recommendations: It is recommended that the Transport, Regeneration and Climate Committee:
Policy Committee Report Page 157 April 2022 • Approve the continuation of scheme development detail in consultation with internal and external stakeholders funded from the scheme development within the Road Safety Fund until confirmation of funding deadline for the ATF3 programme.
• Subject to agreement from the DfT to a revised project end date, approve the submission of the project through the Councils Capital approval process (managed through Strategy and Resources committee) as well as the SYMCA assurance process to access the funding
Background Papers: • Appendix A: Project Concept Design; • Appendix B: Equality Impact Assessment; • Appendix C: Climate Impact Assessment; and • Appendix D: Project Mandate.
Lead Officer to complete:-
1 I have consulted the relevant departments Finance: Damien Watkinson in respect of any relevant implications indicated on the Statutory and Council Legal: Richard Cannon Policy Checklist, and comments have been incorporated / additional forms Equalities & Consultation: Ed Sexton, 24th completed / EIA completed, where January 2023 required. Climate: Jessica Rick, 23rd January 2023
Legal, financial/commercial and equalities implications must be included within the report and the name of the officer consulted must be included above.
2 SLB member who approved Kate Martin, Executive Director, City Futures submission:
3 Relevant Policy Committee Transport, Regeneration and Climate Policy Committee 4 I confirm that all necessary approval has been obtained in respect of the implications indicated on the Statutory and Council Policy Checklist and that the report has been approved for submission to the Decision Maker by the SLB member indicated at 2. In addition, any additional forms have been completed and signed off as required at 1. Lead Officer Name: Job Title: David Whitley Transport Schemes Manager
Date: 8th February 2023
1. PROPOSAL
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
East Bank Road Active Travel Project: Approval to proceed through design and deliveryReport | 210 KB | DownloadRead as text |
PDF |
Item 11: 2.3 Appendix B: ATF EBR Equality Impact AssessmentAppendix | 202 KB | Download |
PDF |
Item 11: 2.4 Appendix C: ATF EBR Climate Impact AssessmentAppendix | 91 KB | Download |
PDF |
Item 11: 2.5 Appendix D: ATF EBR Project MandateAppendix | 131 KB | Download |
PDF |
Item 11 . 2.2 Appendix A: ATF EBR Concept DesignAppendix | 615 KB | Download |
Follow Transport, Regeneration and Climate Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | 2026/27 Quarter 1 Budget MonitoringView the decision text for item 8. | Decided | Open |
| 16 Sep 2026 | Solar on Schools Phase 1 - Commissioning of a Contract for the Operation and Maintenance of Solar PV Installations and entering into Power Purchase AgreementsView the decision text for item 9. | Decided | Open |
| 16 Sep 2026 | Improving Neighbourhood Junctions TrialView the decision text for item 10. | Decided | Open |
| 15 Jul 2026 | 2025/26 Final Budget Outturn Report (Quarter 4)View the decision text for item 8. | Decided | Open |
| 15 Jul 2026 | Local and Neighbourhood Transport Complementary Programme 26/27 Delivery UpdateView the decision text for item 9. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.