Resolved
View the decision text for item 9.
Transport, Regeneration and Climate Policy Committee decided this item on Wednesday 8 February 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 9.
The report provides information to the Transport, Regeneration and Climate Change Policy Committee (TRCPC) on the proposals for £135m for schemes in Sheffield, outlined as part of the £570m allocated to South Yorkshire Mayoral Combined Authority (SYMCA) following the City Region Sustainable Transport Settlement (CRSTS) submission.
The report will confirm the schemes that have been prioritised for investment and provide indicative proposals as well as alignment with policy objectives and strategic fit, outcome expectations, funding, risk and deliverability.
The CRSTS programme of works is large and complex and aims to provide a stepped change in sustainable travel by delivery of targeted interventions.
Due to inflation and construction price fluctuations arising from wider economic conditions it should be noted that the current programme will be subject to potential change. Should this be required, the TRCPC will be presented with appropriate update reports.
The outline CRSTS programme was approved as part of the bid submission process though the SYMCA Governance procedure, with the main schemes in Sheffield identified below;
• Active Travel - £20m for high quality cycle and walking networks, including a northern community package (including Northern General Hospital link) (£15m), cross city centre links (£5m)
Policy Committee Report Page 143 April 2022 • Public Transport – £39m for A61 Chesterfield Road (£11m), Upper Don Valley area (£15m) and Northern Communities to City Centre (£13m).
• LaNTCP Block – £18m to continue our ‘business as usual’ smaller scale transport schemes and support the transport elements of the Local Area Committee plans.
• Mass Transit renewal (Supertram Contribution) - £51m for the most immediate renewals of the tram network.
• Transforming Cities Fund scheme completion – £7m, a specific allocation was included in the CRSTS submission for the completion of Transforming Cities Fund (TCF) schemes; £5m of this funding is required for the Housing Zone North (HZN) project providing an activetravel route linking Kelham/Neepsend to the City centre. The programmes have a shared goal to stimulate the economy by improving sustainable transport infrastructure; balancing finances within both programmes will maximise the benefits which can be achieved by both.
More detail of the schemes is included in section 1.9.
To:
1. Approve the continuation of CRSTS scheme development detail in consultation with internal and external stakeholders,
2. Approve the current scheme allocations in section 1.9 in the programme (including £10.1m to enable the Chesterfield Road corridor to progress immediately through the SCC capital approval process)
3. Note that the £50,847,458 allocation for the tram renewal project will be delivered by SYMCA, with the value of the contribution having been agreed through the SYMCA governance process as part of the bid submission)
4. Note that SYMCA have been working with the DfT to see how to help manage CRSTS at a programme level, however, mechanisms for managing allocations between schemes are yet to be determined, including any local flexibility for this. It is proposed that any amendments to the CRSTS programme will be made through updates to this committee and SYMCA as appropriate.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Introduction to Sheffield's City Region Sustainable Transport Settlement (CRSTS)Report | 232 KB | DownloadRead as text |
Follow Transport, Regeneration and Climate Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | 2026/27 Quarter 1 Budget MonitoringView the decision text for item 8. | Decided | Open |
| 16 Sep 2026 | Solar on Schools Phase 1 - Commissioning of a Contract for the Operation and Maintenance of Solar PV Installations and entering into Power Purchase AgreementsView the decision text for item 9. | Decided | Open |
| 16 Sep 2026 | Improving Neighbourhood Junctions TrialView the decision text for item 10. | Decided | Open |
| 15 Jul 2026 | 2025/26 Final Budget Outturn Report (Quarter 4)View the decision text for item 8. | Decided | Open |
| 15 Jul 2026 | Local and Neighbourhood Transport Complementary Programme 26/27 Delivery UpdateView the decision text for item 9. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.