Resolved
View the decision text for item 82.
Transport, Regeneration and Climate Policy Committee decided this item on Wednesday 26 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 82.
Agenda Item 11
Policy Committee Decision Report
Title of Report: Summerfield Street CPO Date of Decision: 26/03/2025 Report To: Transport Regeneration and Climate Report Of: Kate Martin Executive Director Report Author: Paul Sullivan Principal Transport Planner
Executive Summary: To deliver the Nether Edge to City Centre and Broomhall active travel route, third party land is required. Negotiations on securing two plots of land have stalled. To progress negotiations, this report asks that an ‘in principle’ decision be made to endorse the use of powers conferred by the Highways Act 1980 to make a Compulsory Purchase Order to acquire the two plots. In the event that this ‘in principle’ decision does not progress negotiations then authority is delegated to the Executive Director, City Futures for a decision to use those powers to make a Compulsory Purchase Order for the purpose of acquiring the two plots. The plots are required to construct and maintain the proposed Highway Improvement - namely the active travel route between Cemetery Road and Broomhall which forms a section of the spur of the Nether Edge to City Centre Active Travel Transforming Cities scheme.
Page 303 Council Plan outcomes: The scheme as a whole contributes to the following council plan out comes Great neighbourhoods that people are happy to call home A city on the move – growing, connected and sustainable Policy Committee remit: This report is to be considered by the Transport Regeneration and Climate Policy Committee as its remit includes. Regeneration and Development, including. • Heart of the City 2 • City Centre and Central Area major developments • Development and Regeneration Partnerships • Housing Growth • Strategic Development • Investment, Climate Change and Sustainable City • Planning policy • Flood protection • Building Standards and Public Safety • Strategic Transport Sustainability and Infrastructure Within its remit the Committee: • Takes decisions on any reserved matter. • Champions heritage. • Is responsible for regular monitoring of data including performance and financial information and for monitoring the performance of services. • Is responsible for working within the budget framework agreed by Council, including taking timely action to address any overspend within services. • Is responsible for delivery against the Corporate Plan and any associated Annual Plans and reporting performance to Strategy and Resources Policy Committee: Does the report contain confidential or exempt information? NO
Page 304 Recommendations: Transport, Regeneration and Climate Committee is recommended to: 1. In principle, approve the use of the Compulsory Purchase Order (CPO) process to deliver the spur route along Summerfield Street on the basis that there is a compelling case in the public interest for the acquisition of the land to enable the delivery of the Nether Edge Active travel route. 2. Delegate authority to the Executive Director, City Futures for a decision whether to make a CPO to acquire the aforementioned land.
Financial Implications: Included Legal Implications: Included Approved by Richard Cannon Equality and Engagement Implications: EIA number: 3049 -EIA for the scheme
Climate Change Implications: N/A
Background Papers: N/A
Appendices: Appendix A Scheme drawing indicating land required
Page 305 1. Background to the issue
1.1In 2019 Sheffield City Council was awarded funding from the Transforming Cities Fund to deliver a programme of active travel and public transport improvements. Nether Edge was one six schemes identified to be progressed.
1.2The scheme has public support - 622 people responded to the initial consultation with 78% in support of the overall proposals.
1.3The scheme is currently close to completion of detailed design. Contractors are programmed to be on site August 2025. The period for construction is 22 months.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Summerfield Street CPO plansAppendix A | 252 KB | Download |
PDF |
Summerfield Street Compulsory Purchase OrderDecisions | 209 KB | DownloadRead as text |
Follow Transport, Regeneration and Climate Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | 2026/27 Quarter 1 Budget MonitoringView the decision text for item 8. | Decided | Open |
| 16 Sep 2026 | Solar on Schools Phase 1 - Commissioning of a Contract for the Operation and Maintenance of Solar PV Installations and entering into Power Purchase AgreementsView the decision text for item 9. | Decided | Open |
| 16 Sep 2026 | Improving Neighbourhood Junctions TrialView the decision text for item 10. | Decided | Open |
| 15 Jul 2026 | 2025/26 Final Budget Outturn Report (Quarter 4)View the decision text for item 8. | Decided | Open |
| 15 Jul 2026 | Local and Neighbourhood Transport Complementary Programme 26/27 Delivery UpdateView the decision text for item 9. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.