CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Sheffield City Council
Transport, Regeneration and Climate Policy Committee, Wednesday 26 March 2025 at 2.00pm

Wharncliffe Side Flood Storage Area, potential Compulsory Purchase Order

Decided Committee 2 papers

Transport, Regeneration and Climate Policy Committee decided this item on Wednesday 26 March 2025. Below is the council's own wording, with the papers it was decided on.

Item84

Resolved

View the decision text for item 84.
Word for word from the decision Sheffield published for this meeting. Source: democracy.sheffield.gov.uk

Follow this further

Built from Sheffield's papers

What the report saysPro

Report to Transport, Regeneration and Climate Policy Committee

Agenda Item 13

Policy Committee Decision Report

Title of Report: Wharncliffe Side Flood Storage Area, potential CPO Date of Decision: 26th March 2025 Report To: Transport, Regeneration and Climate Policy Committee Report Of: Kate Martin, Executive Director, City Futures Report Author: James Mead, Flood & Water Service Manager

Executive Summary: To inform committee of the current position regarding flood alleviation proposals for the River Don and to seek endorsement from this committee that, in principle and should it be necessary, it would be appropriate for the Environment Agency to make a CPO in respect of land at Wharncliffe Side for use as a flood storage area.

Page 335 Council Plan outcomes: A city on the move – growing, connected and sustainable

Policy Committee remit: This report is to be considered by the Transport Regeneration and Climate Policy Committee as its remit includes Regeneration and Development, including. • Flood protection Does the report contain confidential or exempt information? [No]

Page 336 Recommendations: Transport, Regeneration and Climate Policy Committee is recommended to: (a) In principle, endorse the use of the Compulsory Purchase Order (CPO) process by the Environment Agency on the basis that there is a compelling case in the public interest for the acquisition of land at Wharncliffe Side for use as a flood storage area.

Financial Implications: [Yes] [Approved by: Damian Watkinson]

Legal Implications: [Yes] [Approved by: David Sellars / Richard Cannon]

Equality and Engagement Implications: [Yes] [Carried out at Programme level and previously presented]

Climate Change Implications: [Yes] [Carried out at Programme level and previously presented]

Background Papers: None

Appendices: Appendix A: Location of proposed flood storage area

Page 337 1. PROPOSAL

1.1The creation of a flood storage area at Wharncliffe Side is essential for the delivery of proposals to better protect areas of the city between Kelham Island and Neepsend/Owlerton from flooding from the river Don. This is an area of the city that was significantly impacted by flooding in 2007 and which has subsequently come close to flooding in 2012, 2019, 2021 and 2023. The effects of climate change suggest that this risk will only increase over time.

1.2A flood storage area is an area of land where, during periods of prolonged/intensive rainfall and high river levels, water can be diverted out of a river and safely stored until river levels fall, at which time the stored water can be safely released back into the river.

1.3The proposed location of this flood storage area is shown on the plan/map included as Appendix A. It should be noted that the site lies just within the boundary of Barnsley MBC and that they have been informed at officer level of this proposal (specifically their Flood Risk Co-ordinator and their Head of Highways & Engineering). They have not raised any objections to this proposal.

1.4Whilst the City Council is not legally responsible for managing flood risk from the river Don, as the Lead Local Flood Authority we are committed to working in partnership with the Environment Agency to address all key sources of flood risk within Sheffield.

2. HOW DOES THIS DECISION CONTRIBUTE ?

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 532 KB Download
PDF
Wharncliffe Side Flood Storage Area, potential Compulsory Purchase OrderReport 193 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
BM
Councillor Ben MiskellChair, present
AD
Councillor Alexi DimondDeputy Chair, present
AS
Councillor Andrew Sangar (MBE)Group Spokesperson, present
CG
Councillor Craig Gamble PughCommittee Member, present
IH
Councillor Ian HornerCommittee Member, present
RM
Councillor Ruth MersereauCommittee Member, present
JR
Councillor Janet RidlerCommittee Member, present
RS
Councillor Richard ShawCommittee Member, present
JW
Councillor John WrightCommittee Member, present

More from Sheffield Transport, Regeneration and Climate Policy Committee

All decisions
MeetingDecisionOutcome
16 Sep 2026 2026/27 Quarter 1 Budget MonitoringView the decision text for item 8. Decided Open
16 Sep 2026 Solar on Schools Phase 1 - Commissioning of a Contract for the Operation and Maintenance of Solar PV Installations and entering into Power Purchase AgreementsView the decision text for item 9. Decided Open
16 Sep 2026 Improving Neighbourhood Junctions TrialView the decision text for item 10. Decided Open
15 Jul 2026 2025/26 Final Budget Outturn Report (Quarter 4)View the decision text for item 8. Decided Open
15 Jul 2026 Local and Neighbourhood Transport Complementary Programme 26/27 Delivery UpdateView the decision text for item 9. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies