Agenda Item 11
Policy Committee Decision Report
Title of Report: Traffic volume, speed, active travel, and parking surveys Commissioning Decision Date of Decision: 28th January 2026 Report To: Transport, Regeneration and Climate Policy Committee Report Of: Kate Martin, Executive Director, City Futures Report Author: Paul Sullivan, Principal Transport Planner, City Transport Executive Summary: This report seeks approval to establish a framework contract for the provision of traffic surveys including, motor vehicles, cycling, pedestrian and parking surveys. And in order to do this progress a competitive tender to establish a select number of suppliers for the services detailed in the report Suppliers will be selected following a competitive procurement process and placed on the framework.
Page 249 Council Plan outcomes: City on the Move, Great Neighbourhoods that people are happy to call home. Policy Committee remit: This report is to be considered by the Transport, Regeneration and Climate Policy Committee as its remit includes functions arising from the Council’s roles as Highways Authority and Road Traffic Authority, including transport and parking matters, where these relate to the capital programme Does the report contain confidential or exempt information? No Recommendations: The Transport, Regeneration and Climate Policy Committee is recommended to: 1. Approve the commissioning of a traffic volume, speed, active travel and parking surveying contract for 4-years with an estimated value of approximately £1.5m* across the contract term.
Financial Implications: Yes. Approved by Adrian Hart Legal Implications: Yes. Approved by: Renaldo Da Costa Equality and Inclusion Implications: There are no equality and inclusion implications arising from this report. Climate Change Implications: There are no climate implications resulting from this report. Background Papers: None
Appendices: None
Page 250 1. Background to the issue
1.1Since 2019, there has been a significant increase in funding for local authority transport schemes. Alongside this, new design standards and business case requirements have emerged, necessitating considerable investment in data collection to understand existing travel behaviours and traffic patterns. Motorised traffic volumes are a key determinant in designing appropriate infrastructure for walking, cycling and wheeling, while speed surveys are essential to inform decisions on pedestrian crossings and speed limit changes.
1.2Over the period Feb 23- Feb 25, the Transport Planning team has commissioned approximately £560,000 worth of survey work through multiple contracts with a small number of suppliers. These surveys have supported the development of various transport schemes. (Figures correct March 2025)
1.3The cumulative cost of these individual survey commissions has triggered multiple quote requests. As the total expenditure exceeds the threshold set by the Procurement Act 2023, the Council is currently non-compliant and exposed to potential procurement challenge.
1.4The volume and complexity of this work has placed significant pressure on resources across four departments: Transport Planning, Procurement, Finance, and Information Management.
1.5Suppliers are also impacted, as each quote request requires substantial input, including quality assurance documentation, data protection assessments (DPIAs), health and safety compliance.
2. Proposal.
2.1To ensure legal compliance and reduce the demand on internal resources, it is proposed that a four-year framework contract be established. This would involve a one-off competitive tender exercise in early 2026, resulting in the appointment of successful suppliers to the framework. Individual schemes requiring survey work would then be procured via mini competitions under this framework.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Traffic volume, speed, active travel, and parking surveys Commissioning DecisionDecisions | 157 KB | DownloadRead as text |
Follow Transport, Regeneration and Climate Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | 2026/27 Quarter 1 Budget MonitoringView the decision text for item 8. | Decided | Open |
| 16 Sep 2026 | Solar on Schools Phase 1 - Commissioning of a Contract for the Operation and Maintenance of Solar PV Installations and entering into Power Purchase AgreementsView the decision text for item 9. | Decided | Open |
| 16 Sep 2026 | Improving Neighbourhood Junctions TrialView the decision text for item 10. | Decided | Open |
| 15 Jul 2026 | 2025/26 Final Budget Outturn Report (Quarter 4)View the decision text for item 8. | Decided | Open |
| 15 Jul 2026 | Local and Neighbourhood Transport Complementary Programme 26/27 Delivery UpdateView the decision text for item 9. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.