Resolved
View the decision text for item 55.
AI summarySheffield City Council's Transport, Regeneration and Climate Policy Committee approved legal agreements to identify the full cost of relocating a business to enable a new access road at the Parkwood regeneration site, using Levelling Up Fund money.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
View the decision text for item 55.
Agenda Item 12
Transport Regeneration and Climate Committee Decision Report
Title of Report: Parkwood- Approval to establish costs for a relocation scheme to facilitate a new access road Date of Decision: 28th January 2026 Report To: Transport Regeneration and Climate Committee Report Of: Kate Martin, Executive Director City Futures Report Author: David Ambrose - Senior Land & Property Surveyor Executive Summary: The regeneration of Parkwood requires a new road to be created, and land currently owned by a business is required to facilitate this. Negotiations have taken place with the owner of this business (the Business) who has agreed in principle to sell their land to the Council in return for their relocation to a new site being funded by the Council however, full costs are needed regarding the proposal. This report seeks approval to enter into a legal agreement with the owner of a potential relocation site (the Owner) to take the proposed site off the market for up to two years and to enable them to design a new industrial unit to tender stage and cost the development. Approval is also sought to enter into an agreement with the Business to indemnify the Business for costs associated in working up a budget for the relocation of the business
Page 255 Lastly, approval is sought to continue negotiations with both the Business and the Owner to agree and draft documentation for the proposed Scheme (see later definition) subject to further committee approval on the Scheme. The budget for the costs associated with these agreements has been approved by Finance and Performance Committee on the 15th December 2025
Council Plan outcomes: Great neighbourhoods that people are happy to call home A creative and prosperous city full of culture, learning, and innovation People live in caring, engaged communities that value diversity and support wellbeing. A city on the move – growing, connected and sustainable
Policy Committee remit: • This report is to be considered by Transport Regeneration and Climate Committee as its remit includes Regeneration and Development, including: • Heart of the City 2 • City Centre and Central Area major developments • Development and Regeneration Partnerships • Housing Growth • Strategic Development
Does the report contain confidential or exempt information? Yes
Page 256 Recommendations: 1. That approval be given to enter into an agreement with the Owner of a potential relocation site and the Business proposed to be relocated on the terms set out below and in Appendix A: A. With the Owner to: - Take the relocation site off the market for up to two years and pay holding costs for the site whilst the Council are in negotiations with the Owner about a potential acquisition of the site; - Pay the Owner’s costs of developing and submitting a planning permission for the building on the relocation site to be in the joint names of the parties - Pay the Owner’s costs for their design team to work up the designs for the new industrial unit to be built on the relocation site up to full tender stage; and - Include a provision committing the Owner to the broad principles of the Scheme.
B. With the Business to: - Pay the Business’ reasonable and proper costs and expenses incurred in working with the Owner on the new building design and in working up detailed costs and obtaining quotations for the relocation of the business into the new industrial unit; and - Include a provision committing the Business to the broad principles of the Scheme.
C. With both parties to agree that in the period during which the Owner and Business are developing the detailed design of the new industrial unit and calculating full costs, for the Council to work with the Owner and Business to negotiate and agree in principle the legal documentation for the Scheme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Parkwood: Approval to establish costs for a relocation scheme to facilitate a new access roadReport | 205 KB | DownloadRead as text |
Follow Transport, Regeneration and Climate Policy Committee at Sheffield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | 2026/27 Quarter 1 Budget MonitoringView the decision text for item 8. | Decided | Open |
| 16 Sep 2026 | Solar on Schools Phase 1 - Commissioning of a Contract for the Operation and Maintenance of Solar PV Installations and entering into Power Purchase AgreementsView the decision text for item 9. | Decided | Open |
| 16 Sep 2026 | Improving Neighbourhood Junctions TrialView the decision text for item 10. | Decided | Open |
| 15 Jul 2026 | 2025/26 Final Budget Outturn Report (Quarter 4)View the decision text for item 8. | Decided | Open |
| 15 Jul 2026 | Local and Neighbourhood Transport Complementary Programme 26/27 Delivery UpdateView the decision text for item 9. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.