Audit Committee noted this item on Thursday 15 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the contents of the report be noted.
This report provides a further update on the existing and emerging assurance and management controls and risk management arrangements within the council. It includes the work undertaken to develop strong governance around commissioning, and also provides an update on the Commissioning Support Unit.
The report gives assurance on the robustness of governance arrangements for all commissioning activity arising from the Council’s 2014-2017 business plan and financial strategy.
With the business plan coming to an end in 2017 the Council is developing the Corporate Plan 2016/17 – 2018/19. The Corporate Plan and Financial Strategy are linked; the Corporate Plan will set out how the Financial Strategy will be delivered and the council’s high-level outcomes and medium term outcomes and objectives (next 12 to 18 months) achieved at a strategic level. The medium term outcomes and objectives will be reviewed every 12 months alongside the Financial Strategy starting in the spring 2018. The medium term outcomes and objectives will be underpinned by more complete Strategic Action Plans which will also be reviewed every 12 months.
The Corporate Plan provides the direction that the Council is taking, informing the shape and design of services directly delivered by the Council or commissioned from others. This direction therefore runs through the Council and shapes the work being delivered at directorate, service area and team levels, as well as providing the basis for staff work planning and appraisals.
The Council is also developing how it uses information and evidence of what works and what is needed to identify targeted priorities and ensure that plans, strategies and actions are based on intelligence and will achieve the expected impact.
A. Members are asked to consider and endorse with appropriate comment the contents of this report.
1 Report
3. Risk Assessment and Opportunities Appraisal
The Corporate Plan is an essential component of the Council’s Strategic Planning, Governance Assurance Framework and the Opportunity Risk Management Strategy. The plans need to link up, and together support and provide direction for the Council to achieve its outcomes and objectives, including delivering a balanced budget. Failure to do so and fully implement the changes required will put the Corporate Plan at risk.
Regular performance reporting against delivery of the Council’s outcomes and objectives established in the Corporate Plan, including through Strategic Risk Reporting will in turn provide assurance to Members and Officers that the Council is achieving against its plan and that strategic risks are being monitored and managed, or on an exception basis activity for improvement is identified. This in turn will provide reflection on and assurance as to the strength of the governance environment.
All Committee reports to Members will continue to report on opportunities and the associated risks and these in turn should be linked to the delivery of the Council’s outcomes as set out in the Corporate Plan.
The delivery of actions within the Financial Strategy that need to be delivered over the next three years are monitored on a monthly basis and reported to the Council's Senior Management Team. To ensure consistency and robustness of the approach, any figures reported in relation to the achievement or non-achievement of savings will be directly reflected within the Council's revenue monitoring reports.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft Commissioning Governance StructureAppendix 1 | 31 KB | Download |
PDF |
SC Commissioning Approach Review: v2Appendix 2 | 669 KB | Download |
PDF |
Commissioning Strategy Supporting Docs V2Appendix 3 | 48 KB | Download |
PDF |
Management Report on Programme Controls and RisksReport | 384 KB | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. | Approved | Open |
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.