That planning permission be granted as per the Officer’s recommendation subject to the Conditions and legal obligations as set out in Appendix 1 of the report subject to the removal of the original requirement for provision of a permissive footpath in the restored quarry area.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1This report seeks an amendment to a legal agreement recommended in connection with an application for a small southerly extension to Gonsal Quarry, Condover and submission of an updated restoration plan. The application was reported to the committee on 17th June 2013 when Members resolved to approve the application subject to a legal agreement and in accordance with the officer recommendation.
1.2The legal agreement covers the following matters:
1) Extended aftercare for 10 years; 2) Convening a steering group to oversee habitat management; 3) A vehicle routing agreement to avoid approaching from or leaving in a southerly direction; 4) A highway maintenance payment of 9 pence per tonne. Central Planning Committee – 16 March 2017 Item 6 – Gonsal Quarry, Condover
2. AMENDMENT TO LEGAL AGREEMENT
2.1At the committee meeting Members also heard from a representative of Condover Parish Council who requested that an additional clause was imposed on the legal agreement in order to deliver a circular permissive footpath route within the restored quarry site. This request was considered at the time to meet relevant legal tests and was accepted by the committee. An additional legal clause was added to cover this matter. Unfortunately however the applicant has not been able to reach agreement with the landowner. Hence it has not been possible to complete the agreement and issue the permission.
2.2In order to progress matters the applicant has been in discussion with the Parish Council and an alternative scheme delivering equivalent benefits has been agreed with the Parish Council. This involves gifting an area of woodland to the immediate south of Condover to the Parish Council and payment of £10,000 towards a project to develop facilities at Condover Village Sports Ground.
2.3These alternative voluntary provisions would not meet relevant legal tests. Accordingly, the developer and the Parish Council have been advised that this would need to be progressed separately from the planning legal agreement. Shropshire Council would not be a party to any such agreement. The developer has confirmed that these matters would be progressed separately.
2.4The officer report to the July 2013 committee concludes that the other recommended legal clauses relating to habitat management and highway matters are appropriate and sufficient to deliver a sustainable development. The permissive footpath would have delivered social benefits enhancing the overall sustainability of the proposals but was not considered essential by officers to deliver a sustainable development. Officers would maintain this position.
2.5Notwithstanding this, the developer has confirmed that the woodland transfer and sports ground payment would be progressed by means of a separate agreement with the Parish Council. The developer has a strong incentive to complete an agreement on this matter with the Parish Council in the context of the ongoing quarrying operations. In this respect it should be noted that a further extension to the quarry has been allocated in the SAMDev plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.