That in accordance with the Officer recommendation planning be granted subject to the conditions and legal obligations set out in Appendix 1, and additional conditions seeking agreement of the applicant to limit the size of lorries using the site and avoiding the despatch of vehicles from the quarry during peak drop-off and pick-up times for Condover School ( 30 minute intervals).
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Recommendation:- Grant Permission subject to the conditions and legal obligations set out in Appendix 1. Southern Planning Committee – 5 October Salop Sand & Gravel Supply Co Ltd Gonsal 2021 Quarry Condover Shrewsbury Shropshire
REPORT
1.0THE PROPOSAL
1.1The Planning Application is for proposed sand and gravel extraction beneath existing lagoons, a proposed southern extension and progressive restoration at Gonsal Quarry.
1.2A similar application (20/03173/MAW) which was refused by the committee in March this year. The only changes are that the annual output has been reduced from 150,000 tpa to 110,000 tpa and an associated application for a satellite depot at Norton Farm north of Condover is not now being proceeded with. The previous application was refused for the following reason:
‘The application conflicts with the development guidelines accompanying SAMDev Policy MD5b in that the requirement for a new access to the A49 avoiding Condover village has not been met. Consequently, the proposals would result in an unacceptable continuation of large quarry HGV movements through Condover Village and Conservation Area and a corresponding adverse impact on local amenities. The applicant’s mitigation proposals are considered insufficient to outweigh this negative impact. (SAMDev Policy MD2, MD5b, MD13, MD13)’
1.3An appeal against this and refusal of the associated application for a satellite depot (Ref 20/03173/MAW) is scheduled to be heard at an Inquiry commencing on 5th December. However, the applicant has confirmed that this will be withdrawn if the current application is approved.
1.4The proposals involve phased extraction of sand and gravel at a rate of 110,000 tonnes per annum over a period of 6 years, a reduction in activity previously accommodated on the local road network, together with progressive restoration to agriculture and nature conservation uses.
1.5The existing permitted quarry access and routing arrangements to the north through Condover would remain the same. No additional plant or machinery required.
1.6The quarry would operate as existing between the hours of 0730 to 1700 Monday to Plan 2 – Block Phasing Southern Planning Committee – 5 October Salop Sand & Gravel Supply Co Ltd Gonsal 2021 Quarry Condover Shrewsbury Shropshire
Friday and between the hours of 0730 and 1630 on Saturdays (maintenance work only. No operations are proposed for Sundays or Bank / Public Holidays.
Figure 2 – Working Plan
1.7A restoration scheme for the whole quarry site has been submitted and is a continuation of the restoration scheme in place for the northern extent of the quarry. It would involve a mix of agriculture and habitat creation, including dry and wet woodland, conservation grassland, shallow water bodies, marsh and acid grassland, and areas left for natural regeneration. Of the total 23.15ha site 2.26ha would remain undisturbed, 2.15ha would be restored to agriculture and the remainder would be restored to wildlife uses (see plan 3).
1.8Enviromental Statement: An Environmental Statement accompanies the application under Schedule 2 of the EIA Regulations including transport, hydrology and ecological assessments. These matters are considered in section 6 below.
2.0SITE LOCATION / DESCRIPTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.