Resolved
To accept the position as set out in the report.
Audit Committee decided this item on Thursday 16 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
To accept the position as set out in the report.
Committee and Date Item
Audit Committee –16th September 2021
RISK MANAGEMENT ANNUAL REPORT 2020/2021 Responsible Officer e-mail: [email protected] Tel: 01743 252073
1. Synopsis 1.1 This report provides an overview of the activity of Risk, Insurance & Resilience Team during 2020/2021 and a synopsis of the current risk exposure of the authority in relation to Strategic, Operational and Project risks. It also identifies some key activity for 2021/2022.
2. Executive Summary 2.1 This report sets out the challenges and achievements accomplished by the Risk, Insurance & Resilience Team during 2020/2021. The team includes business continuity management and emergency planning and as a result we have experienced an unprecedented workload due to significant weather events and the recovery to and response from Covid- 19.
2.2The team continues to strive to ensure that Shropshire Council embeds Opportunity Risk Management practices throughout all service areas.
3. Recommendations 3.1 Members are asked to accept the position as set out in the report.
REPORT
4. Risk Assessment and Opportunities Appraisal 4.1 The management of risk is a key process which underpins the successful achievement of our priorities and outcomes. It forms part of the Annual Governance Statement and the Risk, Insurance & Resilience Team ensures that processes and protocols are established and embedded which support effective decision making.
4.2Insurance is an effective method of risk transfer and a balance of self- insurance and third-party insurance is used based on our risk appetite.
5. Financial Implications 5.1 Failure to effectively and strategically manage the risks associated with developing a sustainable budget will potentially leave the Council exposed to external challenge and financial ramifications. Audit Committee: 16th September 2021 – Risk Management Annual Report 2020/2021
6. Climate Change Appraisal 6.1. The information contained within this report does not impact negatively on our climate change agenda.
6.2Climate Change is one of the Council’s strategic risks. It is subject to regular review alongside all other strategic risks with clearly identified controls and additional controls for mitigation.
7. Background 7.1. The Audit Team undertook a risk management audit for 2020-2021 and we are pleased to confirm that the final report again identified the assurance level as “Good”.
7.2The Opportunity Risk Management Strategy, which supports our rapidly changing environment, is reviewed on an annual basis and endorsed by the Chief Executive. The council needs to ensure that it is taking advantage of every opportunity possible and the strategy is therefore outcome based and focuses on the achievement of our key priorities, objectives and benefits realisation.
8. Additional Information – Risk Management 8.1. Strategic Risk Management 8.1.1 Throughout 2020/2021 our strategic risks were reviewed on a quarterly basis ensuring that the level of risk exposure was monitored closely in our rapidly challenging and changing environment. The outcome of each review is reported to Executive Directors and Informal Cabinet.
8.1.2 The Risk Profile & Action Plans for managing our strategic risks are embedded in the Risk Management SharePoint system. This allows the risks to be updated as frequently as required. The risk profile and action plans detail the direction of travel for each strategic risk over the year, a target risk score for the year end and clearly articulate the current controls in place and the additional controls required to mitigate and manage our strategic risk exposure effectively. Any slippage on outstanding actions is also identified and challenged
8.1.3 During the year a detailed review is undertaken with Executive Directors to ensure that our current strategic risks are still relevant, defined appropriately and accurately assessed and scored. Due to the Covid-19 response, this detailed review has been postponed to October this year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Second line assurance: Risk Annual Report 2020/21 incorporating Strategic Risks UpdateReport | 9 pages | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. | Approved | Open |
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.