That contrary to Officer recommendation planning permission be granted and that delegated authority be given to officers to apply conditions as necessary including: · A condition requiring any soil dug out on the site to remain on the site and be used for landscaping purposes · An advisory around the site being at capacity regarding the number of building s on the site
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Responsible Officer: Tracy Darke, Assistant Director of Economy & Place
Summary of Application
Application Number: 22/03529/FUL Parish: Much Wenlock
Proposal: Erection of 2No holiday lets partially dug into ground, with new pond, associated landscaping and habitat creation, 3No EV charging points, new E-Bike storage, and 18.4 Kw Solar Array, with Ground source heat pump (re-submission)
Site Address: Proposed Holiday Let Accommodation SW Of Westwood House Stretton Westwood Much Wenlock Shropshire
1.Despite the sustainability credentials of the design, in respect of the incorporation in the design of renewable energy sources and drainage arrangements, and the benefits to the visitor economy which weigh in favour of the development they are insufficient to justify a departure from the Development Plan policy which directs new build holiday lets which do not conform to the legal definition of a caravan to sustainable locations i.e. the settlements Market Towns, Key Centres, Community Hubs and Clusters. The principle of the erection of new build holiday lets in this location is contrary to SAMDev policy MD11.
REPORT
1.0THE PROPOSAL
1.1This application is a resubmission of planning application 22/00071/FUL and seeks planning permission for the erection of 2 dwellings to be used for holiday let purposes on land (rough grassland) adjacent the existing holiday letting units and building complex.
1.2The previous application was refused on the following grounds:
1. Despite the sustainability credentials of the design, in respect of the incorporation in the design of renewable energy sources and drainage arrangements, and the benefits to the visitor economy which weigh in favour of the development, these are insufficient to justify a departure from the Development Plan policy which directs new build holiday lets which do not conform to the to the legal definition of a caravan to sustainable locations i.e. the settlements Market Towns, Key Centres, Community Hubs and Clusters. The principle of the erection of new build holiday lets in this location is contrary to SAMDev policy MD11.
2. Insufficient information has been submitted with the application to allow the full potential impact of the development on existing trees to be fully and properly assessed. Whilst it is acknowledged that more trees are proposed to be planted as part of the proposed landscaping scheme than are proposed to be removed, insufficient information has been submitted to ensure that the tree(s) to be removed are not of such special value that would merit their retention and redesign of the scheme. Consequently, it is considered that the proposal fails to meet with the requirements of Core Strategy policy CS17, SAMDev policy MD12 and the National Planning Policy Framework NPPF) Part 15.
1.3The supporting information states that the aims of the development are to create two new ‘Zero Carbon’ holiday lets, and includes the formation of a new pond, and the re-wilding of the surrounding area, in order to provide a sustainable, low - Proposed Holiday Let Accommodation SW Of Westwood House
impact development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.