Audit Committee, Tuesday 14 February 2023 at 10.00am

Minutes of the previous meeting held on the 24 November 2022

Approved Finance 1 paper

Audit Committee approved this item on Tuesday 14 February 2023. Below is the council's own wording, with the papers it was decided on.

Item59

Resolved

That the Minutes of the meeting of the Audit Committee held on the 24 November 2022 be approved as a true record and signed by the Chairman, subject to the above. Matters arising: The Interim Audit Service Manager confirmed that it had been agreed to delay the management report from the dog warden that had been due to be received at this meeting as the officer providing the update had been off sick and had not been able to affect the changes needed. In the meantime, however she had been provided with updates to show the actions being taken in that area so she was able to confirm that work was being done and that the officer would attend the next meeting to give an update. Minute 44 A. First line assurance: IT Services, improvements to the control environment following various Audit Reports 2022/23 The Executive Director of Resources (Section 151 Officer) read an update from the Head of Automation and Technology who confirmed that it was possible to use the existing technology to enable voicemail for all officers who have external calling enabled however this function was currently turned off by default. It was now being recommended to turn it on by default instead and this was being taken forward. In response to a query about Skype, which has the ability for messages to be left, it was confirmed that this service was being decommissioned by Microsoft however there were other methods of low or no cost messaging available. In relation to the outstanding recommendations in relation to IT that needed to be resolved, the External Auditor explained that this information would come as part of the Audit Findings report which had been delayed as the outstanding information was still awaited.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit Committee

Committee and Date

Audit Committee

14 February 2023

MINUTES OF THE AUDIT COMMITTEE MEETING HELD ON 24 NOVEMBER 2022 10.00AM – 12.55PM

Responsible Officer: Michelle Dulson Email: [email protected] Tel: 01743 257719

Present Councillor Brian Williams (Chairman) Councillors Simon Harris (Vice Chairman), Nigel Lumby, Roger Evans and Rosemary Dartnall

39 Apologies for Absence / Notification of Substitutes

No apologies were received.

40 Disclosable Pecuniary Interests

Members were reminded that they must not participate in the discussion or voting on any matter in which they have a Disclosable Pecuniary Interest and should leave the room prior to the commencement of the debate.

41 Minutes of the previous meeting held on the 15 September 2022

A brief discussion ensued in relation to the format of the Minutes and it was agreed by the Assistant Director Legal and Governance to discuss this outside of the meeting.

RESOLVED:

That the Minutes of the meeting of the Audit Committee held on the 15 September 2022 be approved as a true record and signed by the Chairman, subject to the above.

42 Public Questions

There were no questions from members of the public.

43 Member Questions Minutes of Audit Committee held on 24 November 2022

There were no questions from Members.

44 A. First line assurance: IT Services, improvements to the control environment following various Audit Reports 2022/23

The Committee received the report of the Head of Automation and Technology – copy attached to the signed Minutes – which provided an update on the actions taken or planned to address the recommendations arising from various audit reports

The Head of Automation and Technology took members through the paper and responded to a number of queries. It was noted that some dates in the action plan had not been met and did not have new target dates attached to them, also, some actions were marked as green even though the dates were into the following year. Assurance was sought that the extended dates were nothing to be concerned about. In response the Head of Automation and Technology explained that those actions marked green were being managed effectively or were progressing on target so even though some of the dates had passed it was because the risk was being managed effectively or that they were no longer deemed to be a potential risk for escalation.

Referring to paragraphs 9.7 and 9.10 on page 25 of the report, it was noted that effective controls were in place for the management of the Council’s telecommunications contract and for the ICT Business Support function. A query was raised as to whether these controls were being audited, whether they were operating satisfactorily and did not pose any risks for the authority. In response, the Head of Automation and Technology explained that they posed no risks to the authority and were regularly monitored both internally and with suppliers to ensure those contracts were being managed effectively and to ensure the Council were getting the most effective solutions and prices from its suppliers. Alternative sources of procurement were also considered.

In response to a query around the security of legacy systems and third- party contractor access, the Head of Automation and Technology stated that nothing was completely safe as there would always be an element of risk, however, as supplier chain attacks were increasing and to ensure the Council’s suppliers were robust, they were looking more closely at the suppliers’ security mechanisms and procedures. They also identified those accounts that had not been used for periods of time and reviewed them to ensure that they were either disabled or removed completely so that access did not continue. He confirmed that the risk was being effectively managed and that as the legacy systems dropped away, they would become less of a risk.

In response to a query around the security implications of telephony contracts ‘rolling’ beyond their contract end dates, the Head of

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Minutes of the previous meeting held on the 24 November 2022Minutes 196 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
KW
Katie WilliamsOfficer, present
SH
Simon HarrisVice Chairman, present
NL
Nigel LumbyCommittee Member, present
BW
Brian WilliamsChairman, present
RE
Roger EvansCommittee Member, present
GP
Grant PattersonOfficer, present
MW
Mary WrenOfficer, present
JB
Julia BuckleySubstitute, in attendance
RD
Rosemary DartnallCommittee Member, present

On this subject at Shropshire

Search all
  1. Minutes of the previous meeting held on the 24 November 2022This decision
  2. Minutes of the previous meetingApproved
  3. Minutes of the previous meeting held on the 25 June 2026Approved
  4. Minutes of the previous meetingApproved
  5. Minutes of the previous meetings held on the 5 February 2026 and 14 May 2026Approved
  6. Minutes of the previous meetingApproved

More from Shropshire Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2025 Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. Approved Open
16 Jul 2025 Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... Approved Open
16 Jul 2025 Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. Noted Open
16 Jul 2025 Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... Agreed Open
16 Jul 2025 Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies