Resolved
That the Joint Committee a) approve the WME Risk Management Strategy attached at Appendix A b) accept the position as set out in the report.
West Mercia Energy Joint Committee approved this item on Friday 22 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Joint Committee a) approve the WME Risk Management Strategy attached at Appendix A b) accept the position as set out in the report.
1.1The Joint Committee annually reviews the WME Risk Management Strategy and at each meeting receive details regarding the key risks identified.
The Joint Committee are recommended to:
2.1approve the WME Risk Management Strategy attached at Appendix A;
2.2accept the position as set out in this report.
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1The recommendations contained in this report are compatible with the provisions of the Human Rights Act 1998.
3.2There are no direct environmental, equalities or climate change consequences arising from this report.
3.3Given the subject matter of this report, the assessment of risk forms a fundamental part of the risk strategy.
4.1The financial implications of each risk are considered when the impact of the risk is assessed. 5. Background
5.1The current WME Risk Management Strategy was approved by the Joint Committee on 21st March 2023 a copy of which is attached in Appendix A. The WME management team have conducted their annual review of the Strategy document and no changes are being proposed.
5.2The risk register is kept under constant review and is formally reviewed by the management of WME twice a year and the current risk register comprises of eighty four highlighted risks.
5.3The majority of the risks within the risk register are operational with controls in place which mitigate the impact of the risks to an acceptable risk level.
5.4The Strategy states that the Joint Committee are to receive details of all medium and high risks at each meeting The table below identifies the six current high and medium risks and the two risks which has been downgraded since the last meeting.
Risk Rank Ref Risk L I Rank Owner Change
Current High and Medium Risks Market conditions pre-pricing leading Julie 1 5 3 Medium No Change to less competitive prices Wassall Breach of trading risk levels due to significant within year spikes in Julie 2 2 5 High No Change market prices or supplier Wassall reforecasting of volumes Central government policy or Nigel 3 1 5 Medium No Change Regulative initiative Evans Unexpected consequences of a change of supplier e.g. diminishing levels of Julie 4 3 4 Medium No Change service, transfer delays and/or Wassall potential financial implications 5 Bad debts / delayed payment Jo Pugh 3 4 Medium No Change Dealing with suppliers whose ownership, structure, investments or Nigel 6 5 2 Medium No Change general business activities are not Evans deemed satisfactory by customers.
Reduced Risk Poor performance by a key supplier Reduced risk leading to customer service issues Julie 1 2 2 Low from Medium including a) billing issues, b) Wassall to Low information - pricing/budgets, Reduced risk Nigel 2 Loss of key staff 2 3 Low from Medium Evans to Low
L – lik elihood of the risk I – impact of the risk
2 5.5 In light of market conditions over the past quarter Risk Ref 1 remains at a medium level. Whilst volatility levels have decreased, Risk Ref 2 remains at a medium level and continues to be monitored closely.
5.6Risk Ref 3 remains at a medium level to cover any central government policy or initiative which would adversely affect our business. We have recently seen some impact of ‘light mandation’ within the NHS sector.
5.7Risk Ref 4 relates to the risks associated with a change of supplier and with a new electricity supply arrangement commencing formally from 1st April 2024, this risk remains at a medium level. There is a detailed transition plan in place to mitigate the risks here but as we haven’t had a major move in supplier since 2016 the likelihood level remains higher than from 12 months ago.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 10 Appendix A: RiskMgtStrategyMarch24Appendix | 651 KB | Download |
PDF |
Risk Management UpdateReport | 574 KB | DownloadRead as text |
Follow West Mercia Energy Joint Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Sep 2026 | Statement of Accounts 2025/26 and Annual Governance Statement 2025/26That the finalised Statement of Accounts 2025/26 be signed by the Chairman and the Treasurer. That the Annual Governa... | Noted | Open |
| 25 Sep 2026 | External Audit - Audit findings report 2025/26That the contents of the audit findings report presented by WR Partners be considered and endorsed. | Decided | Open |
| 25 Sep 2026 | Distribution of SurplusThat the retention of accumulated surplus of £1.594 million be approved. That the distribution of accumulated surplus... | Approved | Open |
| 25 Sep 2026 | Risk Management UpdateThat the medium risks presented be considered and endorsed. | Decided | Open |
| 25 Sep 2026 | Anti-Slavery and Human Trafficking PolicyThat the WME Anti-Slavery and Human Trafficking Policy be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.