Resolved
That the Joint Committee a) approve the draft audit plan for 2023/24 as presented by WR Partners attached at Appendix 1 b) approve the commissioning of WR Partners to undertake the audit in accordance with the audit plan.
West Mercia Energy Joint Committee approved this item on Friday 22 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Joint Committee a) approve the draft audit plan for 2023/24 as presented by WR Partners attached at Appendix 1 b) approve the commissioning of WR Partners to undertake the audit in accordance with the audit plan.
1.1It has been previously agreed for the Joint Committee to continue with an external audit to provide the Joint Committee the necessary continued assurance regarding stewardship of funds.
1.2This report provides the Joint Committee with the proposed external audit plan for 2023/24 for consideration and approval.
It is recommended that the Joint Committee:
2.1approve the draft audit plan for 2023/24 as presented by WR Partners attached at Appendix 1
2.2approve the commissioning of WR Partners to undertake the audit in accordance with the audit plan.
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1The recommendations contained in this report are compatible with the provisions of the Human Rights Act 1998.
3.2There are no direct environmental, equalities or climate change consequences arising from this report.
3.3WR Partners’ audit work is conducted in accordance with the International Standards on Auditing (ISAs) (UK). 3.4 The risks associated with not conducting an external audit including an audit opinion were considered when the decision was made in September 2015 to continue with an external audit. It was accepted by the Joint Committee that without an annual external audit process not only would the Joint Committee lose the assurance regarding stewardship of funds but also the other Local Authorities/public entities with which WME trades.
4.1The fee for the 2023/24 audit is £15,100, a £700 (4.9%) rise against the fee for 2022/23 of £14,400.
5.1At the September 2015 Joint Committee, members were advised of the changes to the statutory audit requirements for Joint Committees effective from 1 April 2015. At this Joint Committee, it was agreed to continue with an annual external audit to provide the Joint Committee the necessary continued assurance regarding stewardship of funds.
5.2Following the expiry of the previous three year tender period, a procurement exercise was conducted in late 2023 with three audit firms invited to tender with the winning tenderer being the previous auditors WR Partners.
5.3WR Partners will conduct their main audit work on the WME accounts for 2023/24 in July and will bring their report to the September Joint Committee.
5.4The attached WR Partners Service Plan sets out the scope of the audit to be undertaken, identifies risks and audit responses to these and outlines materiality levels.
List of Background Papers (This MUST be completed for all reports, but does not include items containing exempt or confidential information)
Joint Committee 28 September 2015 – Local Audit and Accountability Act 2014
Member Councillor G Butler of Shropshire Council (Chair of the Joint Committee)
Appendices Appendix 1 – WR Partners Audit Service Plan for West Mercia Energy (year ended 31 March 2024)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit Plan 2023/24Report | 132 KB | DownloadRead as text |
PDF |
Item 6: Appendix 1: West Mercia Energy Audit Service Plan 2024Appendix | 366 KB | Download |
Follow West Mercia Energy Joint Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Sep 2026 | Statement of Accounts 2025/26 and Annual Governance Statement 2025/26That the finalised Statement of Accounts 2025/26 be signed by the Chairman and the Treasurer. That the Annual Governa... | Noted | Open |
| 25 Sep 2026 | External Audit - Audit findings report 2025/26That the contents of the audit findings report presented by WR Partners be considered and endorsed. | Decided | Open |
| 25 Sep 2026 | Distribution of SurplusThat the retention of accumulated surplus of £1.594 million be approved. That the distribution of accumulated surplus... | Approved | Open |
| 25 Sep 2026 | Risk Management UpdateThat the medium risks presented be considered and endorsed. | Decided | Open |
| 25 Sep 2026 | Anti-Slavery and Human Trafficking PolicyThat the WME Anti-Slavery and Human Trafficking Policy be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.