That Council: 1. Note the results of the public consultation and approve both the business case for the project, as set out in this paper and in Appendix 6, and that the design and development of the Shrewsbury Sports Village Transformation be included in the Capital Programme with an initial budget for the design and planning stages of £2.248 million. The project to be funded from Public Works Loan Board (PWLB) and Community Infrastructure Levy (CIL) and any available grants and capital receipts which may be available during the project. 2. Agree that to further contribute the council’s net zero targets, that the design and planning stages include assessing the feasibility and cost of both making the whole of the sports village complex all electric and installing overhead photovoltaic cells on the car park. 3. Delegate authority to the Executive Director of Place, in consultation with the Portfolio Holder for Culture & Digital, to procure, negotiate and agree the terms of any agreements/contracts necessary for the delivery of the design and planning stages of the project including, but not limited to: · Commissioning the UK Leisure Framework to support the procurement strategy. · Selection of a prime design and build contractor and other suppliers. · Site surveys and investigations and relevant reports. · Detailed designs and planning application. · Contract preparation for the build stages. 4. Agree that a report is brought back to Cabinet and Full Council after the design stages; following the determination of the planning application and once the project has established the full build costs. This subsequent report will seek a decision on whether to approve the full project budget and to proceed with the build stage.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Cabinet Member (Portfolio Holder): Rob Macey, Portfolio Holder for Culture & Digital
1. Synopsis 1.1 This report presents the results of the recent public consultation on proposals to transform the Shrewsbury Sports Village (“SSV”) with new swimming and fitness facilities. Approval is sought to accept the project into the capital programme and grant authority to proceed with the detailed design and planning stages.
2. Executive Summary 2.1 The proposed approach will maintain the current facilities at the SSV but add new facilities to create a multi-feature centre which is more appealing to a wider demographic, is more accessible, will attract greater revenue to be financially sustainable and be an energy efficient, all electric modern building.
2.2The scope of the proposal would include: Council 26.09.2024 - Shrewsbury Sports Village Transformation
25 metre x 8 lane pool – suitable for competitions, galas, and general swimming (as recommended by Swim England for county level competitions), but with easy access steps to encourage maximum useability.
17 x 10 metre studio teaching pool with easy access steps and moveable floor to provide flexibility for learners and other water sports and to include a children’s water party module.
Seating and space in the main pool hall sufficient to hold county level competitions including at least 250 Spectators and 250 Competitors.
A changing village plus two group changing rooms.
‘Poolpod’ access lifts to both pools for wheelchair users, disability access toilets and changing rooms, and a Changing Places facility.
A new reception area and lobby with café overlooking the studio pool with new children’s soft play area adjacent to café, to encourage family use.
A new 130 station fitness-suite, new dance studio and new 30 station cycle spin studio.
Multi-purpose studio with access to existing kitchen - divisible into 2 areas for group activities and events.
Refurbishment of the existing dry changing facilities.
Subject to the results of a full transport study – replace lost car parking spaces
The new facility would be designed and built to sustainable building principles and would aim to achieve the Building Research Establishment Environmental Assessment Methodology (BREEAM) excellent standard. It would be all electric making use of make use of new photovoltaic cells and air source heat pumps to minimise the carbon footprint. The project would include landscape enhancements and demolition of the former caretaker’s house.
The proposals would maintain all other internal and external facilities on the SSV site including: the main sports hall with 8 badminton courts, 16 football pitches and football changing, Football Academy offices, in-door bowls hall, cycle track and 8 Netball courts.
2.3At the Cabinet meeting on 11 th September 2024, Councillor Julian Dean requested a number of additional requirements to support the council’s programme to achieve net zero. This included to make the whole of the sports village complex all electric, and also to look at installing overhead photo-voltaic cells over the car parks. The Cabinet agreed these were worthwhile proposals and will be added to the scope of the project and so the design stage will include them and assess their feasibility, electrical grid capacity and costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
41Shrewsbury Sports Village Transformation Proposals - Results of Public Consultation and Authority to Proceed with Detailed Design and PlanningThis decision
Shrewsbury Sports Village Transformation Proposals - Results of Public Consultation and Authority to Proceed with Detailed Design and PlanningThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.