That Council agrees to;? ? 1. Authorise the Executive Director of Place in consultation with the Portfolio Holder for Housing & Assets to? ? I. Declare the Guildhall as the administrative base for the Council and implement the phased move and the relocation of its services in the financial year 2024/25.?? II. Rationalise and consolidate the immediate use of the Shirehall building to ground floor and first floor and other essential spaces only to house the data centre, formal meeting spaces, critical storage and remaining tenants until the ultimate building closure in the financial year 2025/26.? III. Update the disposal process accordingly to reflect the accelerated decant of the building.? ? 2. Agree the budget of £1.2 million previously identified to facilitate the accelerated exit from the Shirehall including the cost of decommissioning the Shirehall building, to ultimately achieve a revenue saving of £593k per annum once the move is fully completed and the Shirehall is decommissioned.? Full saving achieved by financial year 25/26.?
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Cabinet Member (Portfolio Holder): Cllr Dean Carroll
1. Synopsis To seek approval to the accelerated phased move from the Shirehall to Guildhall in Shrewsbury to form the future Council headquarters.
2. Executive Summary 2.1 This report to Council is made subsequent to the previous reports dated 24 th February 2022, 14th December 2023 and 29 February 2024 which made the following recommendations;
24th February 2022:-
i. Further to recommendation 3.1, declare the Shirehall building and associated environs within the site boundary marked in red in appendix I, surplus to requirements.
ii. Delegate responsibility to the Executive Director of Place, in consultation with the Portfolio Holder for Physical Infrastructure, to agree and implement the disposal and marketing strategy as the recommended option for the Shirehall site; agree terms and conditions of sale, all subject to approval at Full Council.
14th December 2023:- Shirehall Decommissioning & Disposal Strategy:- 26 September 2024 Relocation of Council Headquarters – Shirehall to Guildhall
Authorise the Executive Director of Place in consultation with the Portfolio Holder for Housing & Assets to
iii. Commence decommissioning of the Shirehall,
29 February 2024, agreement of the Council’s Financial Strategy, Medium Term Financial Strategy, extract from Appendix 1:-
iv. RC040 Reduce Cost – Dispose of Shirehall quicker and relocate services
2.2The relocation of the Council’s headquarters as per previous decision making has been accelerated further to the decisions set out in 2.1. The former Guildhall building is the Council’s preferred venue and is currently being vacated by the University of Chester in the relocation of their University Centre Shrewsbury. This is seen as an important move whilst further work is ongoing concerning the potential full business case for a planned Multi-Agency Hub (MAH) being developed as part of the Shrewsbury Town Centre Redevelopment.
2.3In line with the previous delegation from Council in December 2023, the Executive Director of Place has already instigated the process of vacating the Shirehall, and this report now proposes to accelerate this process to the preferred venue of the Guildhall.
2.4To progress a phased move of the Council, its democratic function and associated services to the new venue Guildhall, Shrewsbury.
3. Recommendations That Council agrees to;
3.1Authorise the Executive Director of Place in consultation with the Portfolio Holder for Housing & Assets to
I. Declare the Guildhall as the administrative base for the Council and implement the phased move and the relocation of its services in the financial year 2024/25. II. Rationalise and consolidate the immediate use of the Shirehall building to ground floor and first floor and other essential spaces only to house the data centre, formal meeting spaces, critical storage and remaining tenants until the ultimate building closure in the financial year 2025/26. III. Update the disposal process accordingly to reflect the accelerated decant of the building.
3.2Agree the budget of £1.2 million previously identified to facilitate the accelerated exit from the Shirehall including the cost of decommissioning the Shirehall building, to ultimately achieve a revenue saving of £593k per annum once the move is fully completed and the Shirehall is decommissioned. Full saving achieved by financial year 25/26. Please see further detail in section 5.3
Contact: Steve Law 01743 281017 2 26 September 2024 Relocation of Council Headquarters – Shirehall to Guildhall
Report 4. Risk Assessment and Opportunities Appraisal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.