Audit Committee, Thursday 6 February 2025 at 10.00am

Third line assurance: Internal Audit Plan 2025/26

Noted Finance 1 paper

Audit Committee noted this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.

Item98

Resolved

To note the contents of the report and to support the following resolution: That whilst recognising the Head of Policy and Governance’s reassurance, they were concerned about the further loss of an auditor. This compounded their reservations at recent meetings about the audit team’s ability to provide sufficient audit function and provide more than the ‘limited assurance’ that they were getting used to. The vacancy level within the team was unacceptable, and whilst recognising that there was a moratorium on recruiting, they considered that senior officers should recognise the seriousness of the situation and requested a report from the senior team for the next committee meeting. The purpose of this motion was to support the audit team and process, and to reassure the Audit Committee.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit Committee

Executive summary

2.1This report provides Members with the proposed approach for the risk based Internal Audit Plan for 2025/26. Significant organisational restructure is currently underway with a full consultation with those affected progressing. This is likely to have implications for the Councils existing strategic and operational risks, the extent of which will not be known until the new structure is finalised. It is therefore proposed that a full plan will be bought back to the Audit Committee in July for approval once the new Council structure has been determined and confirmed.

Recommendations

3.1The Committee is asked to accept the position as set out in the report.

Contact: [email protected] 1 Audit Committee 6th February 2025; Draft Internal Audit Annual Plan 2025/26

Report 4. Risk Assessment and Opportunities Appraisal

4.1Under the Audit Committee’s terms of reference, reviewing the risk-based audit plan, including internal audit resource requirements, the approach to using other sources of assurance and any other work upon which reliance is placed, is an important responsibility.

4.2The recommendations contained in this report are compatible with the provisions of the Human Rights Act 1998. There are no direct environmental, equalities, consultation or climate change consequences of this proposal.

4.3The Internal Audit Annual Plan satisfies both the Public Sector Internal Audit Standards (PSIAS) and the Accounts and Audit Regulations 2015 part 2. The latter sets out the requirements on all relevant authorities in relation to internal control, including requirements in respect of accounting records, internal audit and review of the system of internal control. Specifically:

‘A relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.’

Financial implications

5.1The Internal Audit plan is delivered within approved budgets. The work of Internal Audit contributes to improving the efficiency, effectiveness and economic management of the wider Council and its associated budgets.

6. Climate Change Appraisal

6.1This report does not directly make decisions on energy and fuel consumption; renewable energy generation; carbon offsetting or mitigation; or on climate change adaption. However, the work of the Audit Team will look at these aspects relevant to the governance, risk management and control environment of the Council. The majority of audit work will continue to be carried out remotely thereby reducing fuel consumption.

7. Background 7.1. The provision of a risk based Internal Audit Plan consistent with the Council’s goals is an essential part of ensuring probity and soundness of the Council’s internal controls, risk exposure and governance framework. The audit plan is usually presented to Audit Committee in advance of the start of the financial year, however, due to imminent and significant changes to the Councils structure and

Contact: [email protected] 2 Audit Committee 6th February 2025; Draft Internal Audit Annual Plan 2025/26

operating model a full plan will not be developed until the relevant consultations have concluded and confirmed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Third line assurance: Internal Audit Plan 2025/26Report 241 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
JA
Jim ArnoldCo-Optee non-voting, present
KW
Katie WilliamsOfficer, present
SH
Simon HarrisVice Chairman, apologies, sent representative
BW
Brian WilliamsChairman, present
RE
Roger EvansCommittee Member, present
KH
Kate HallidayCommittee Member, present
RD
Rosemary DartnallSubstitute, in attendance
AS
Avtar S SohalGuest, in attendance, virtual
NL
Nigel LumbySubstitute, present

On this subject at Shropshire

Search all
  1. Third line assurance: Internal Audit Plan 2025/26This decision
  2. Third line assurance: Annual Assurance report of the Audit and Governance Committee to Council 2025/26Decided
  3. Third line assurance: External Audit, Shropshire Council and Shropshire County Pension Fund Audit PlansNoted
  4. Third line assurance: Internal Audit Performance ReportDecided
  5. Third line assurance: Report of the Internal Audit Review of Risk ManagementNoted
  6. Third line assurance: Internal Audit Performance Report and Revised Annual Audit Plan 2025/26Decided

More from Shropshire Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2025 Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. Approved Open
16 Jul 2025 Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... Approved Open
16 Jul 2025 Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. Noted Open
16 Jul 2025 Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... Agreed Open
16 Jul 2025 Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. Approved Open