That Council approve an increase in budget of the pyrolysis project by around £1.3m from £2m as outlined in the council paper, approved by full Council on 21st September 2023,to £3.3 million. 2. That Council delegate authority to the Service Director Strategy in consultation with the Portfolio Holder for Transport and Economic Growth, to negotiate and agree the terms of any and all agreements necessary for the implementation and ongoing operation of the project. 3. That the Council will not utilise biomass from household green waste or food waste unless this is explicitly approved by the Service Director for Strategy in consultation with the Portfolio Holder for Transport & Economic Growth.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Cabinet Member (Portfolio Holder): Cllr Rob Wilson (Transport and Economic Growth))
1. Synopsis
This report seeks approval for additional funds for the procurement, installation, and operation of a biochar plant which will process woody residual biomass into biochar, renewable energy, and associated carbon credits. Additional funds are to cover site remediation, draining and clearance of legacy tanks from the old Ludlow Anaerobic Digestion (AD) plant. The additional works also include increased construction and machinery costs plus additional demand for external technical expertise.
2. Executive Summary 2.1. The Shropshire Plan’s Healthy Environment priority highlights the importance of investment and joint working to tackle climate change and maintain, protect, and enhance our outstanding natural environment.
2.2Pyrolysis is the thermal breakdown of materials (in our case plant matter) in the absence of oxygen. The heat drives off gases and oil and what is left is mostly carbon in the form of char. If this char is burnt again as fuel, it’s known as Charcoal. If it’s kept as char and used in other ways, it is often called biochar; sometimes also activated charcoal. The primary difference from charcoal is the higher temperatures used and typically smaller particle size of the charred material.
2.3Biochar can remain in soils or materials for hundreds, and even thousands of years without degrading. Biochar is typically between 60% and 80% pure carbon. We measure carbon emissions in weight of ‘Carbon Dioxide equivalent’. From pure carbon this requires multiplication by 3.67 to add the weight of the two
Contact: Richard Macdonald [email protected] 1 Council 17 July 2025 Pyrolysis Second Site Increase in Budget
oxygen atoms. This means that 1 tonne of biochar effectively stores over 3 tonnes of Carbon Dioxide.
2.4The Council is already a leader in biochar production, with a joint venture (JV) in operation with Woodtek at their base location in Welshpool demonstrating the commercial return such plants can generate. Our success is being followed by this fully council-owned biochar plant in Ludlow.
2.5The previously approved paper can be found here: Council Paper - Pyrolysis.
2.6Planning permission has been approved and the project is well advanced, however, additional funding is needed due to unforeseen and costly remediation and building works on the proposed site. While this brings an additional expense, the business case remains sound, and the anticipated benefits remain achievable.
3. Recommendations 3.1. Approve an increase in budget of the pyrolysis project by around £1.3m from £2m as outlined in the council paper, approved by full Council on 21st September 2023, to £3.3 million.
3.2Delegate authority to the Service Director Strategy in consultation with the Portfolio Holder for Transport and Economic Growth, to negotiate and agree the terms of any and all agreements necessary for the implementation and ongoing operation of the project.
Report 4. Risk Assessment and Opportunities Appraisal
4.1Risk Assessment (updated risks from 2023 paper plus new risks)
I. [New]. Not Increasing Budget: there is a risk that increased budget is not secured, compromising the ability to remediate the current site in Ludlow to house the biochar plant. An alternative site would be needed, the legacy issues with the Ludlow plant would remain an outstanding liability, abortive costs would need to be covered, and the significant environmental and financial benefits would not be realised. Risk rating: High.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.