That Council agrees the withdrawal of the draft Local Plan (2016-2038) from the Examination in accordance with Section 27 of the Town and Country Planning (Local Planning) (England) Regulations 2012. 2. That in the light of the additional risk of speculative development, coupled with the large number of new councillors, council asks for urgent advice and guidance for all councillors on how to best represent residents concerns and demands as large scale planning applications are mooted, received and processed, with a view to helping both members and officers to get the best outcomes possible for existing residents and our environment
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
2.1Following Council approval, the draft Local Plan was submitted to the Secretary of State in September 2021, with Planning Inspectors appointed to examine the Plan shortly afterwards. The examination in public (EiP) on the draft Plan has in effect been active since then.
2.2Following a lengthy and often challenging examination process, in January 2025 the Inspectors wrote to the Council setting out their significant soundness concerns and invited the Council to prepare a project plan setting out how these would be addressed in a six month timeframe.
2.3In line with the request of the Inspectors, the Council prepared a project plan and, with Cabinet approval, submitted this to the examining Inspectors in February 2025. The Inspectors then issued ID48 (appendix 1 to this report) in February 2025, setting out that they did not consider the extent of the additional work
Contact: Eddie West – [email protected] 1 17th July 2025 - Withdrawal of Local Plan from Examination & Next Steps
required was ‘limited’ in nature and would (in their view) take longer than six months to complete.
2.4As such the Inspectors in ID48 recommended that the Council withdraw the draft Plan from the examination. If the Council decide not to withdraw the Plan, then the Inspectors have indicated they will complete their final report concluding that the Plan is unsound.
2.5The outcome of the Inspectors’ conclusions as set out in ID48 therefore does not provide the Council with a positive path to adoption of the draft Plan. The choice is essentially between withdrawing the Plan, or asking the Inspectors to continue to prepare their final report which would conclude the Plan is unsound. Given the financial position of this Council, and that in any event work would need to commence on a new Local Plan process later in 2025, it is considered this would represent an unnecessary financial cost as well as requiring officers to respond to any inquiries the Inspectors raised before almost inevitably reaching a conclusion of unsoundness.
2.6The proposed withdrawal of the Local Plan means the Council will not be able to adopt the Local Plan as hoped in 2025. This means the current development Plan for the area will remain the adopted Core Strategy and Site Allocation and Management of Development (SAMDev) Plan, adopted by the Council in 2011 and 2015 respectively, as well as a range of adopted Neighbourhood Development Plans. To mitigate this risk, the Council have set out a positive programme of work to commence work on a new Local Plan process under the Government’s new plan making system in January 2026. In line with Government’s expectations this process is expected to lead to an adopted Local Plan in 2028.
Recommendations
3.1Council agrees the withdrawal of the draft Local Plan (2016-2038) from the Examination in accordance with Section 27 of the Town and Country Planning (Local Planning) (England) Regulations 2012.
Report Risk Assessment and Opportunities Appraisal
4.1It is a statutory responsibility for Councils to maintain an up-to-date Development Plan. Under the Government’s ‘plan-led’ approach to development, the Local Plan is a key component of the overall Development Plan for the area and should provide a positive strategy to enable an area to grow in a sustainable manner. Another part of the Development Plan for an area is Neighbourhood Development Plans, usually prepared via Town and Parish Councils.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.