CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Shropshire Council
Housing Supervisory Board, Thursday 18 September 2025 at 2.00pm

Cornovii Developments Limited - Update Report - Quarter 1

Noted Committee 2 papers

Housing Supervisory Board noted this item on Thursday 18 September 2025. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

That the report be noted.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Housing Supervisory Board

Purpose of the report

1.1The purpose of the Monitoring Report is to update Housing Supervisory Board members on Cornovii Development Limited CDL activity to the end of June 2025.

2 Development Summary

2.1A total of seven schemes were approved in the March 2025 Business Plan. The business plan aims to deliver a total of 582 new homes during the life of the business plan. The charts and tables below report on progress against this business plan.

2.2Fig. 1 - Progress to 582 completions in accordance with the approved business plan:

2.3Fig. 2 - Tenure chart approved schemes : The Q1 forecast estimates 21% of the 582 homes to be delivered will be affordable. To date, four sites have been completed delivering 39 affordable homes (34% across the four completed sites). One further development is on site and is due to deliver a further 27 affordable, plus two specialist accommodation properties.

2.4Fig. 3 – Sales forecast within the approved business plan and as at Q1

2.5Fig. 4 - Number of units forecast by tenure over plan period: 2.6 Fig. 5 - Tenure chart (live and completed sites only):

Tenure Type Market Affordable Shared Private Total Total Total Total No. Units Sale Rent Ownership Rent Affordable Market PRS Homes Sale Completed Sites Crowmoor 21 6 6 0 12 21 0 33 Ellesmere 8 6 0 9 6 8 9 23 Wharf Ifton 10 9 6 10 15 10 10 35 Oaklands 10 6 0 7 6 10 7 23 Total 49 27 12 26 39 49 26 114 Completed Sites

London Road 84 21 8 22 29 84 22 135 (Live) Total (All) 68 133 48 249

2.7Homes by house type and bedroom size forecast to complete over the plan period (live and completed sites only): Homes by house type and bedroom size

Completed Sites Live Sites Total

1 bed 8 16 24 10%

2 bed 36 29 65 26%

3 bed 50 32 82 33%

4 bed 20 50 70 28%

5 bed 0 8 8 3%

Total Units 114 135 249

Completed Sites Live Sites Total

Bungalow 17 16 33 13%

House 97 99 196 79%

Apartment 0 20 20 8%

Total Units 114 135 249 2.8 Number of completions in the plan period against the approved business plan of 582 units:

Prior Years 25/26 26/27 27/28 28/29 29/30 30/31 31/32 32/33 Total

Completions 119 109 136 63 155 0 0 0 0 582 Forecast Outright sales 46 66 103 63 98 0 0 0 0 376 Affordable rent 35 33 0 0 57 0 0 0 0 125 & SO PRS 38 10 33 0 0 0 0 0 0 81

2.9Map 1: – Location of sites across the county (approved schemes only)

3.1Ifton Heath Development Update This scheme has now reached practical completion, CDL has delivered the following split of tenures:

 10 x Open market sale properties – one is reserved and expected to complete in quarter two. All other sales are complete.  10 x PRS to Cornovii Investments (Shropshire) Ltd  15 x affordable homes which have been primarily sold to Connexus Housing Group

3.1.1 Ellesmere Wharf Development Update

This scheme has now reached practical completion, CDL has delivered the following split of tenures:

 8 x Open market sale properties – all sales are complete  9 x PRS have all been occupied  6 x affordable homes, all of which have been transferred into the local authority

3.1.2 Oaklands Development Update

This scheme has now reached practical completion, CDL has delivered or is delivering the following split of tenures:

 10 x Open market sale properties – all sold  7 x PRS have all been occupied  6 x affordable homes, all of which have been transferred into the local authority

3.1.3 London Road Development Update

CDL is on site with practical completion due in December 2025. The sales are progressing as follows

 2 x properties have been reserved as first option (buyer has property to sell)  6 x properties have been fully reserved and are going through the conveyancing process  1 x help to own property has been reserved  8 further homes are released and available for sale The private rental homes are progressing as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Agenda Item 6: Appendix A: September 2025 CDL Quarterly Monitoring Report PUBLICAppendix 457 KB DownloadRead as text
PDF
Cornovii Developments Limited: Update Report: Quarter 1Agenda 167 KB Download

At this meeting

Whole meeting

Who was there

8 of 11 attended
RD
Rosemary DartnallChair, present
BW
Beverley WaiteVice-Chair, present
GE
Greg EbbsCommittee Member, apologies
BE
Brian EvansCommittee Member, present
HH
Harry Hancock-DaviesCommittee Member, apologies, sent representative
NL
Nigel LumbyCommittee Member, present
MO
Mark OwenCommittee Member, present
VP
Vivienne ParryCommittee Member, absent
JT
Jon TandyCommittee Member, present
GH
George HollyheadSubstitute, present as substitute
SD
Shelley DaviesDS Officer, expected

On this subject at Shropshire

Search all
  1. Cornovii Developments Limited - Update Report - Quarter 1This decision
  2. Cornovii Developments LtdNoted
  3. Cornovii Developments Limited - Quarter Three Monitoring ReportApproved
  4. Cornovii Developments Limited - Business PlanNoted
  5. Cornovii Developments Limited - Update ReportNoted
  6. Cornovii Developments Limited Overview - PresentationNoted

More from Shropshire Housing Supervisory Board

All decisions
MeetingDecisionOutcome
25 Mar 2026 Exclusion of the Press and PublicThat in accordance with the provisions of Schedule 12A of the Local Government Act 1972, and paragraph 10.4(3) of the... Decided Open
19 Mar 2026 MinutesThat the minutes of the meeting held on 27 th November 2025 be approved as a true record. Approved Open
19 Mar 2026 Cornovii Developments Limited - Quarter Three Monitoring ReportThat the progress made by Cornovii Development Ltd to the end of December 2025 against the approved business plan and... Approved Open
19 Mar 2026 Cornovii Developments Limited - Business PlanThat the update be noted. Noted Open
19 Mar 2026 Exclusion of the Press and PublicThat in accordance with the provisions of Schedule 12A of the Local Government Act 1972, and paragraph 10.4(3) of the... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies