Cornovii Developments Limited - Quarter Three Monitoring Report
ApprovedCommittee2 papers
AI summaryShropshire's Housing Supervisory Board notes Cornovii Developments Ltd progress report covering delivery, tenure mix and finances to end of December 2025.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgress against the approved business plan noted
MoneyNot stated
What happens nextNot stated
Who it affectsCornovii Developments LtdReporting on its Q3 performance
What was decided
The board noted the progress made by Cornovii Development Ltd to the end of December 2025 against the approved business plan.
The board noted the updated delivery profile, tenure mix, and financial performance set out in the Quarter Three Monitoring Report.
Why
The board received the Q3 monitoring report from the Service Director for Commissioning, attached as Appendix A. Report P1
Who and where
Cornovii Developments Ltd
Timeline
End of December 2025: End of the reporting period covered by the Q3 report
March 2026: Date of the Q3 monitoring report Report P1
Plain English for the jargon
CDL: Cornovii Developments Limited
Q3: Quarter Three
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item41
Resolved
That the progress made by Cornovii Development Ltd to the end of December 2025 against the approved business plan and the updated delivery profile, tenure mix, and financial performance outlined in the Quarter Three Monitoring Report be noted.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
Cabinet Member (Portfolio Holder): Cllr James Owen
1. Synopsis This report provides an update on Cornovii Development Ltd.’s performance to December 2025, including progress against the approved business plan, housing delivery, tenure mix, financial performance, and key development milestones.
2. Executive Summary 2.1. This report supports delivery of The Shropshire Plan, particularly the Healthy People priority, by increasing the supply of high‑quality market and affordable homes across the county.
2.2Cornovii Development Ltd (CDL) continues to deliver against its approved March 2025 Business Plan, which aims to deliver 582 homes over the plan period. As at the end of Quarter 3 (December 2025), four sites have been completed, and one site is live on site.
2.3Progress to date shows: 114 homes completed 135 homes currently on site 283 homes within the development pipeline
The total forecast delivery has reduced by 50 units compared to the original business plan, reflecting updated viability and scheme changes. 19th March 2026 - Cornovii Development Ltd – Quarter three Monitoring Report
2.4Affordable housing delivery remains a strong feature of the programme. While the overall forecast is that 21% of homes delivered will be affordable, completed sites have achieved 34% affordable housing, with a further 27 affordable homes and two specialist accommodation properties delivered on the live site.
2.5The tenure mixes across live and completed schemes includes market sale, affordable housing, private rented sector (PRS), and Rent to Own, supporting a broad range of housing needs including first‑time buyers, key workers, and households with local connections. CDL has entered the PRS market, with 41 PRS properties and 9 Rent to Own homes, all currently tenanted. Rental income to date totals £0.440m, with capital growth of £0.922m.
2.6Key development sites, including London Road (Charles View), Sue West Welshpool Road, and Shrewsbury Road Oswestry, continue to progress, with planning, procurement, and funding activity underway.
3. Recommendations 3.1. That Members note the progress made by Cornovii Development Ltd to the end of December 2025 against the approved business plan.
3.2That Members note the updated delivery profile, tenure mix, and financial performance outlined in the Quarter Three Monitoring Report.
Report 4. Risk Assessment and Opportunities Appraisal
4.1The primary risks relate to: Planning timescales and statutory consultees impacting delivery programmes Construction market conditions and procurement capacity Ongoing viability pressures affecting scheme scale and tenure mix Mitigation measures include early engagement with planning authorities and consultees, flexible procurement approaches including joint venture options, and regular review of scheme viability and phasing.
4.2The key opportunity remains CDL’s ability to deliver mixed‑tenure housing, supporting local housing need, affordable delivery, and wider regeneration objectives.
Contact: Laura Tyler – [email protected] 2 19th March 2026 - Cornovii Development Ltd – Quarter three Monitoring Report
4.3Risk table
Risk Mitigation Planning delays Early engagement with planning officers and statutory bodies Market volatility Flexible delivery models and procurement routes
Financial viability Regular monitoring and business plan refresh
Delivery slippage Phased development and pipeline management
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicThat in accordance with the provisions of Schedule 12A of the Local Government Act 1972, and paragraph 10.4(3) of the...
Exclusion of the Press and PublicThat in accordance with the provisions of Schedule 12A of the Local Government Act 1972, and paragraph 10.4(3) of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.